Housing Authority
Agenda Item Staff Report
To: Board of Directors of the San Dimas Housing Authority For the Meeting of October 27, 2026
From: Brad McKinney, City Manager
Prepared by: Shari Garwick, Director of Public Works
Subject: Appropriation of $34,074 from the Housing Authority Trustee Administration Fund and Authorization of Contract Amendment with Geo-Advantec Incorporated for Geotechnical Engineering Services for CC 2025-05 Charter Oak Mobile Home Estates North Property Wall Project
____________________________________________________________________________
SUMMARY
On May 27, 2025, the San Dimas Housing Authority approved $35,000 for engineering and inspection services as part of the $1,318,040 budget for the Charter Oak Mobile Home Estates North Property Wall Project. Due to construction delays and the extended project duration, additional geotechnical observation and testing services are required. Staff is requesting an additional appropriation of $34,074 to cover these services through project completion.
RECOMMENDATION
Staff recommends that the Housing Authority:
1. Appropriate $34,074 from the Housing Authority Trustee Administration Fund to Account 113.4120.020.001 for additional geotechnical engineering and testing services for CC 2025-05, Charter Oak Mobile Home Estates North Property Wall Project, increasing the account’s total budget to $1,965,187 for this project and other scheduled capital projects and facility improvements.
2. Authorize a contract amendment with Geo-Advantec Incorporated in the amount of $34,074 for a contract total of $61,184.00.
GOVERNMENT CODE §84308 APPLIES:
https://leginfo.legislature.ca.gov
Yes
Authorize contract amendment of an additional $34,074 for Geo-Advantec Incorporated for geotechnical engineering services on CC 2025-05 Charter Oak Mobile Home Estates North Property Wall Project. Page 2
For the Meeting of October 27, 2026
FISCAL IMPACT
The proposed action requires an additional appropriation of $34,074 from the Housing Authority Trustee Administration Fund, account number 113.4120.020.001, increasing the Geo-Advantec contract from $27,110 to $61,184. Expenditures will be based on actual services performed, up to the authorized contract amount. The overall budget in the account will be adjusted to $1,965,187 which includes other scheduled capital improvement projects and facility improvements. The 113 Housing fund reserve totaled $4,889,482 at the end of the 2025-26 fiscal year.
BACKGROUND
On May 27, 2025, the San Dimas Housing Authority awarded Construction Contract CC 2025-05 for the Charter Oak Mobile Home Estates North Property Wall Project. The approved project budget included $35,000 for engineering and inspection services (Attachment 1), of which $27,110 was allocated to Geo-Advantec Incorporated for geotechnical observation and testing based on an estimated construction duration of 90 working days. The original agreement with Geo-Advantec is included as Attachment 2.
The Charter Oak Mobile Home Estates North Property Wall Project replaces approximately 1300 linear feet of chain link fencing along the north property line with a new slump stone block wall.
The block wall is approximately six feet tall with a two foot high wrought iron attachment and includes pilasters spaced at 24 feet. New lighting is incorporated into the wall. Once complete, the wall will enhance the park‘s security and provide better aesthetics.
DISCUSSION/ANALYSIS
Construction has extended beyond the original 90-working-day estimate due to several factors, including railroad requirements, unforeseen utility conflicts, and slower-than-anticipated construction progress. The proximity of the wall to the Metrolink railroad tracks adds complexity to construction activities and requires careful coordination.
Due to the depth of the excavations and proximity to the railroad, continued geotechnical observation and testing are necessary to verify proper soil compaction and suitability of backfill materials. These services help reduce the risk of future wall settlement or other conditions that could affect the wall or adjacent railroad facilities.
Geo-Advantec has provided an estimate of $34,074 for additional geotechnical observation and testing services, including costs already incurred due to the extended construction duration and anticipated services needed through project completion (Attachment 3). The contract is based on actual field observation time and required materials testing. The additional authorization will allow these services to continue through project completion, with payment limited to work performed.
Any unexpended funds will remain available in the Housing Authority Trustee Administration Fund.
The project is approximately 75% complete, with construction anticipated to be completed by December 2026.
Authorize contract amendment of an additional $34,074 for Geo-Advantec Incorporated for geotechnical engineering services on CC 2025-05 Charter Oak Mobile Home Estates North Property Wall Project. Page 3
For the Meeting of October 27, 2026
ALTERNATIVES
None Recommended.
ENVIRONMENTAL REVIEW
The proposed project is Categorically Exempt under the California Code of Regulations, Title 14, Section 6, Chapter 3, Article 19, Section 15301 Existing Facilities Class 1 operations which consists of the operation, repair, maintenance or minor alteration of existing public or private facilities involving negligible or no expansion of existing or former use.
Respectfully submitted,
Shari Garwick
Shari Garwick
Director of Public Works
Attachments:
1. May 27, 2025 Housing Authority Staff Report CC 2025-05
2. Geo-Advantec Incorporated - Original Geotechnical Services Agreement
3. Geo-Advantec Incorporated - Additional Geotechnical Services Cost Estimate
4. Levine Act Form