Agenda Item Staff Report
To: Honorable Mayor and Members of City Council
For the Meeting of November 9, 2026
From: Brad McKinney, City Manager
Prepared by: Lauren Marshall, Sr. Management Analyst
Subject: Adopt Resolution 2026-70 Adopting the Initial Study and Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program and Approval of the Conceptual Design for the Lone Hill Park Regional Watershed Management Program Project
____________________________________________________________________________
SUMMARY
The Lone Hill Park Regional Watershed Management Program Project (Project) will capture and infiltrate stormwater to improve water quality and groundwater recharge while enhancing park amenities. Staff recommends that the City Council adopt a resolution (Attachment 1) approving the Initial Study/Mitigated Negative Declaration (IS/MND) and Mitigation Monitoring and Reporting Program (MMRP) (Attachment 2), then approve the conceptual design (Attachment 3). Construction funding has not been secured. The final design, specific improvements, and construction timeline will depend on the funding awarded.
RECOMMENDATION
Staff recommends the City Council:
1. Adopt Resolution 2026-70 (Attachment 1) entitled, “A RESOLUTION OF THE CITY
COUNCIL OF THE CITY OF SAN DIMAS APPROVING AND ADOPTING AN INITIAL
STUDY AND MITIGATED NEGATIVE DECLARATION (MND) AND MITIGATION
MONITORING AND REPORTING PROGRAM FOR THE LONE HILL PARK REGIONAL WATERSHED MANAGEMENT PROGRAM PROJECT LOCATED AT 500 NORTH SHELLMAN AVENUE;” and
2. Approve the conceptual design for the Project, with the final design and specific improvements contingent on construction funding.
GOVERNMENT CODE §84308 APPLIES:
https://leginfo.legislature.ca.gov
No
Adopt the Initial Study and Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program and Approval of the Conceptual Design for the Lone Hill Park Regional Watershed Management Program Project Page 2
For the Meeting of November 9, 2026
FISCAL IMPACT
Adoption of the IS/MND and MMRP has no additional fiscal impact. Preparation of the Initial Study and environmental documentation was included in CWE’s $700,140 design contract, funded by Regional Safe Clean Water (SCW) Funds. Construction is estimated to cost approximately $15 million; funding has not been secured at this time.
BACKGROUND
Los Angeles County's Safe, Clean Water Program (SCW Program), funded through Measure W, provides funding for stormwater projects that improve water quality and support compliance with state and federal stormwater regulations. Under the Municipal Separate Storm Sewer System (MS4) Permit, cities must implement measures, including stormwater infrastructure projects, to reduce pollutants entering local waterways and demonstrate progress toward meeting water quality standards. The Lone Hill Park Project was selected for Regional SCW Program funding to support these regional water quality objectives.
On October 13, 2020, the City Council approved a letter supporting the Lone Hill Park Stormwater Project for the Upper San Gabriel River Watershed Steering Committee. In September 2021, the Los Angeles County Board of Supervisors awarded $900,000 in Regional SCW Funds for project design. On June 11, 2024, the City Council awarded the design contract to CWE. The Council previously reviewed a preliminary design concept when approving the grant funding agreement.
The Parks & Recreation Commission reviewed the Project and provided feedback on public outreach efforts in November 2024, September 2025, and September 2026.
Lone Hill Park, at 500 North Shellman Avenue, is a 9-acre community park on the west side of San Dimas. Existing amenities include softball fields, tennis and basketball courts, playground equipment, and a parking lot. The park is bounded by Gladstone Elementary School to the north, residential properties to the east, Juanita Avenue to the south, and Shellman Avenue to the west (Figure 1).
Adopt the Initial Study and Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program and Approval of the Conceptual Design for the Lone Hill Park Regional Watershed Management Program Project Page 3
For the Meeting of November 9, 2026
Figure 1 – Aerial view of Lone Hill Park
The Project will install a regional stormwater capture and infiltration system beneath the park and improve surface amenities. The system will capture runoff from approximately 335 acres in San Dimas and Glendora, approximately 73 percent of which is in San Dimas. Gravity flow will divert runoff from existing storm drains to an expanded underground system for capture, treatment, and infiltration, preserving the park surface for recreational and community use.
The expanded system has a maximum design diversion rate of approximately 28 cubic feet per second and a calculated 24-hour storm capacity of approximately 12 acre-feet. It will reduce runoff and pollutant loads discharged to downstream receiving waters and recharge groundwater in the Main San Gabriel Basin.
Modeling of the amended Project estimates reductions of approximately 93 percent in runoff volume, 97 percent in zinc loads, and 96 percent in copper loads.
The Project’s goals are to:
• Improve local and downstream water quality by capturing, treating, and infiltrating stormwater runoff and reducing pollutant loads.
• Increase groundwater recharge and support local water supply within the Main San Gabriel Basin.
• Support the City’s Municipal Separate Storm Sewer System (MS4) permit compliance and the East San Gabriel Valley Watershed Management Group’s stormwater capture and water quality goals.
Adopt the Initial Study and Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program and Approval of the Conceptual Design for the Lone Hill Park Regional Watershed Management Program Project Page 4
For the Meeting of November 9, 2026
• Enhance recreational opportunities and accessibility while restoring and improving park space.
• Increase native and drought-tolerant vegetation.
• Preserve recreational use by locating stormwater infrastructure underground.
DISCUSSION/ANALYSIS
Staff recommends adopting the IS/MND and approving the MMRP before approving the conceptual design. Although environmental adoption typically accompanies final design approval, staff recommends conceptual design approval at this stage because construction funding remains pending. Completing the design and environmental documentation will support applications for construction funding and help the Project proceed once funding is secured.
Conceptual Design and Public Outreach
City staff presented the evolving conceptual design at community events to gather feedback on proposed amenities and the park layout:
• Holiday Extravaganza – December 6, 2025
• Marchant Park Outreach Event – March 21, 2026
• San Dimas Farmers Market – June 10, 2026
The conceptual design includes the following amenities based on public input (Attachment 3):
• Fort-themed playground (Attachment 4)
• Interpretive and educational signage highlighting butterflies, water conservation, native landscaping, and stormwater management
• Full-size basketball court
• Pickleball courts
• New parking area
• Walking paths
• Butterfly garden
• Low-water-use landscaping
• Additional shade trees
Staff shared the design with approximately 400 residents. Feedback was generally favorable, with most residents looking forward to the park enhancements. The design combines these improvements with the Project’s primary purpose of improving water quality and groundwater recharge.
At its September 15, 2026, meeting, the Parks & Recreation Commission supported the conceptual design and acknowledged that the final design and construction timeline will depend on the availability and amount of construction funding.
Adopt the Initial Study and Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program and Approval of the Conceptual Design for the Lone Hill Park Regional Watershed Management Program Project Page 5
For the Meeting of November 9, 2026
ALTERNATIVES
The City Council may defer adoption of the IS/MND and approval of the conceptual design.
Deferral would delay implementation of a project that supports MS4 permit compliance and could require updated environmental documentation at additional cost. The current review is grant-funded; future review costs could reduce funds available for park improvements.
ENVIRONMENTAL REVIEW
The City prepared a Draft IS/MND under the California Environmental Quality Act (CEQA) to evaluate the Project’s potential environmental impacts. The Initial Study found that all potentially significant impacts could be mitigated to a less-than-significant level, supporting adoption of an MND rather than preparation of an Environmental Impact Report.
The Draft IS/MND was available for public review from March 4 through April 3, 2026, pursuant to State CEQA Guidelines Section 15105(b). The Notice of Intent to adopt the IS/MND was published, recorded with the Office of Planning and Research and the Los Angeles County Recorder’s Office, circulated to interested parties, and posted on the City’s website with the Draft IS/MND and technical appendices. Hard copies were available at the Public Works Counter at City Hall, 245 East Bonita Avenue. The City also submitted a Notice of Completion and the Draft IS/MND to the State Clearinghouse for review by relevant state agencies. The State Clearinghouse assigned number 2026021076.
The City received comments during the public review period from:
• Joseph Jamoralin, California Department of Transportation: General requirements are reflected in the MND and associated mitigation measures. • Patricia Horsley, Los Angeles County Sanitation District: A utility identified in the Project area is being addressed through design coordination.
The City conducted tribal consultation under Assembly Bill 52 and Public Resources Code Section 21080.3.1. Notification letters were sent to nine tribes on September 4, 2025. The Gabrielino Band of Mission Indians – Kizh Nation participated in consultation, and tribal monitoring mitigation measures were incorporated into the IS/MND based on its feedback.
The Final IS/MND includes the MMRP and a separate document containing public comments and responses. The comments required no changes to the Draft IS/MND. The Final IS/MND identifies no new or substantially more severe impacts than those analyzed in the draft; therefore, recirculation is not required under State CEQA Guidelines Section 15073.5.
Under State CEQA Guidelines Section 15074, the City Council must consider the Final IS/MND, which must reflect the City’s independent judgment and analysis, before approving the Project.
The City must adopt the IS/MND and approve the MMRP before project approval. Following approval, the City must file a Notice of Determination with the County Clerk within five working days and send a copy of the filed notice to the State Clearinghouse.
The public hearing for the IS/MND was noticed in the Inland Valley Daily Bulletin on October 20, 2026, and November 3, 2026.
Adopt the Initial Study and Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program and Approval of the Conceptual Design for the Lone Hill Park Regional Watershed Management Program Project Page 6
For the Meeting of November 9, 2026
Respectfully submitted,
Lauren Marshall
Sr. Management Analyst
Attachments:
1. Resolution 2026-70
2. Initial Study and Mitigated Negative Declaration
3. Conceptual Design Rendering
4. Proposed Playground Equipment
5. November 9, 2026, Public Notice Comment Letter
6. Response to Comment Letter