WEST MIDWAY INTIAL MILESTONE SCHEDULE
Entitlements and Backbone Infrastructure Permitting:
July 5th, 2022: Term Sheet approval by City Council
November 19th, 2022: Planning Board approval of Development Plan and recommendation to City Council of the Development Agreement and Large Lot Tentative Map Delays in approval will have impacts on Milestone Dates below December 20th, 2022: City Council approval of Development Agreement, DDA and Large Lot Tentative Map
Delays in approval will have impacts on Milestone Dates below January 3rd, 2023: City Council 2nd Reading
February 13th, 2023: Permits issued for Demo, Surcharge, Environmental Site Management Permit issuance is subject to timely permit review/approval.
December 4th, 2023: Permits issued for Backbone Infrastructure Permit issuance is subject to timely permit review/approval.
Horizontal Site Construction:
February 28, 2025: Pan Am Way (W. Tower Avenue to West Midway Avenue) – constructed by City ) June 15th, 2025: W. Tower Avenue Phase I Complete (Main Street to Orion Street) and Orion Street from Site A Phase I to W. Tower Avenue complete – constructed by Site A Developer
October 13th, 2025: West Midway Avenue Complete (Pan Am Way to Main Street) October 13th, 2025: Orion Street Complete (West Midway Avenue to W. Tower Avenue) October 1st, 2026: W. Tower Avenue Phase II Complete (Orion Street to Pan Am Way) – constructed by Site A Developer
RESHAP Site Deliveries:
July 31st, 2023: APC Phase 1 – Demolition, site preparation & pad delivery complete Note: APC Building 1 will be pile supported and not require surcharge August 19th, 2024: Operation Dignity – Demolition, surcharge & pad delivery complete June 16th, 2025: Building Futures – Demolition, surcharge & pad delivery complete
676\05\3309581.2
August 5th, 2025: APC Phase II – Demolition, surcharge & pad delivery complete
Market Rate Site Deliveries:
April 14th, 2025: Phase I Demolition, surcharge & pad delivery complete March 23rd, 2026: Phase II Demolition, surcharge & pad delivery complete December 21st, 2026: Phase III Demolition, surcharge & pad delivery complete including building pad delivery complete for Commercial parcel
Note: Vertical development to be phased based on market demand over 7 to 10 years following pad delivery.