CITY OF ALAMEDA RESOLUTION NO. _______
APPROVING A FINAL MAP AND AUTHORIZING THE CITY
MANAGER, OR DESIGNEE, TO EXECUTE A SUBDIVISION
IMPROVEMENT AGREEMENT FOR TRACT 8561, NORTH HOUSING
SITE – PHASE 1, AS A CONDITION TO FINAL MAP APPROVAL
WHEREAS, the Housing Authority of the City of Alameda (Housing Authority) , submitted an application for Tract 8561, North Housing Site – Phase 1, to subdivide 12.07 acres located at 501 Mosley Avenue for residential purposes; and
WHEREAS, On August 17, 2020, the Plan ning Board held a duly noticed public hearing and adopted Resolution No. PB -20-16 approval of the Ten tative Map Tract No. 8561 to allow the subdivision of 11 lots on approximately 12.07 acres in up to three phases; and
WHEREAS, on September 15, 2020, pur suant to Resolution No. 15689, the City Council approved the Tentative Map Tract No. 8561; and
WHEREAS, the City Engineer has determined that the Final Map for Tract No. 8561, North Housing Site – Phase 1 is substantially in accordance with the previousl y approved tentative subdivision map approved by the City Council and complies in all manners with the provisions of Government Code sections 66410 et seq. (Subdivision Map Act) and the City of Alameda’s local subdivision ordinance (Alameda Municipal Code (AMC) Article VI); and
WHEREAS, the Housing Authority , has hired a competent design professional, who is licensed by the State of California to practice civil engineering, to prepare plans and specifications for the construction of required public infras tructure improvements in the public right of way; and
WHEREAS, pursuant to Government Code section 66462 and AMC section 30 -
85.3, as a condition precedent to approval of the Final Map for Tract 8561 – Phase 1, the Housing Authority, has executed a Subdivision Improvement Agreement (SIA) to assure the timely construction, unconditional warrantee, and prescribed maintenance of all required public infrastructure improvements; and
WHEREAS, the City Engineer has approved the Phase 1 plans and specifications prepared by CBG Civil Engineers entitled “ North Housing – Phase 1 (Tract 8561) Backbone Improvement Plans ” permitted as PWD2 2-0004 and filed in the office of the Public Works Director; and
WHEREAS, pursuant to Government Code section 66499 and AMC section 30-
85.3, and as required by the SIA s, the Housing Authority , has deposited adequate security in the form of surety bonds, and in sufficient amounts as estimated by the City Engineer, to secure the Housing Authority’s performance of the required Phase 1 public infrastructure improvements identified in the Phase 1 SIA; and
WHEREAS, pursuant to Public Resources Code section 21080(b)(1) and California Environmental Quality Act (CEQA) Guidelines section 15 268, approval of the Final Map for Tract 8561 is exempt from the requirements of CEQA because the project approval is ministerial; and
WHEREAS, on May 16, 202 3, the City Council reviewed Tract Map No. 8561, North Housing Site – Phase 1, and all pertinent maps, documents, and exhibits.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Alameda that the Final Map for Tract 8561, North Housing Site – Phase 1, conforms to all the requirements in Government Code sections 66410 et seq., AMC Article VI, and CEQA, and is hereby approved; and
BE IT FURTHER RESOLVED, that all easements offered are accepted on behalf of the public for use in conformity with the terms of the offers of dedication; and
BE IT FURTHER RESOLVED, that the easement s designated as East Bay Municipal Utility District (EBMUD) are not offered, nor accepted for dedication by the City of Alameda; and
BE IT FURTHER RESOLVED, that the approval of the Final Map and the acceptance of said parcels of land and easements are conditioned upon completion to the satisfaction of the City Engineer of public improvements as required by the SIA; and
BE IT FURTHER RESOLVED, that the City Surveyor and City Engineer, and City Clerk are hereby authorized to endorse the Final Map for Tract 8561, North Housing Site – Phase 1; and
BE IT FURTHER RESOLVED, that the agreement for construction and completion of the public improvements in Tract 8561 pursuant to the SIA and all its terms and conditions be, and hereby are, approved and the City Manager and the City Clerk are authorized and directed to execute and attest to, respectively, said agreement on behalf of the City of Alameda; and
BE IT FURTHER RESOLVED, that upon said executions of the Final Map and SIA, the City Engineer is hereby authorized to release the Final Map and SI A for recording with the Alameda County Clerk – Recorder; and
BE IT FURTHER RESOLVED, that the security guaranteeing full and faithful performance of said public improvements, labor, and materials are hereby approved as sufficient in amount.
* * * * *
I, the undersigned, hereby certify that the foregoing Resolution was duly and regularly adopted and passed by the Council of the City of Alameda in a regular meeting assembled on the 16th day of May 2023, by the following vote to wit:
AYES:
NOES:
ABSENT:
ABSTENTIONS:
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of said City this 17th day of May 2023.
______________________________
Lara Weisiger, City Clerk
City of Alameda
Approved as to form:
_____________________________
Yibin Shen, City Attorney
City of Alameda