2 Alameda High School – Replacement Swim Center
AGENDA
• Project Background
• Present Status of Replacement Pool Design
• Replacement Pool Design
• Timeline
We are here to share progress on the replacement
swim center
3 Alameda High School – Replacement Swim Center
BACKGROUND
• Facility Shared by City and School District
• Current Facility Not Meet Current Code
Requirements
• Years of Significant Maintenance Issues
• Funding for Replacement Pools from Alameda
Unified School District and City of Alameda
• During Design, Multiple Meetings Held With District,
Coaches, community, and City Staff
4 Alameda High School – Replacement Swim Center
REPLACEMENT POOL AMENITIES
• 12-Lane, 25-Yard by 30-Meter Main Pool – Swim, Water Polo & PE • 4-Lane, 25-Yard Practice Pool – Shallow for Lessons & Swim Practice • New Pool Deck – With New Deck Lighting and Room for Deck Storage • Bleachers and Scoreboard
• One-Meter Diving Board
• New non-Climbing Fencing with Fabric Cover
• All new Pool Equipment Including New Pool Equipment Area • Deck Mounted or Building Mounted Showers
• Replacement Tennis Court – Displaced by New Pools
No Work Planned for the Existing Pool Building
Alameda High School – Alameda USD Master Plan Diagram
School Board Approved in 2022
Aquatic Center
6 Alameda High School – Replacement Swim Center
6 EXISTING SWIM
BUILDING – NO WORK
Main Pool
New Tennis Court
Practice Pool
7 Alameda High School – Replacement Swim Center
7 Bleachers Moved Here
For Water Polo
No Pool Building Renovation
12-Lane x 25-Yard Pool
4-Lane x 25-Yard Pool
New Pool Eq. New Deck
Showers On
Pool Building
New Entry
Gates
One Meter
Diving Board
New Bleachers
Scoreboard
on Pool Bld.
8 Alameda High School – Replacement Swim Center
8 PRACTICE POOLMAIN POOL
Alameda High School – Project Schedule
Project Schedule
Schematic Design Approval June 2023
Complete Construction Drawings January 2024
State Approval (Required for School Projects) Spring 2024 Construction Complete Spring 2025