Receive an Update on Construction
Impacts from the Oakland Alameda
Access Project (OAAP)
City Council
October 1, 2024
ITEM INSERT#7-C
Oakland Alameda Access Project
• Led by Alameda CTC
• $152M regional project
• Improve access to I-880 & I-980
• Improve safety and reduce traffic in Oakland
Chinatown
• 20+ years planning
• City Council voted to support in 2020 based on EIR
• Construction beginning mid-2025, completed 2028
2 Image source: Alameda CTC, February 2024
Source: Alameda CTC, February 2024
3 Alameda Bike/Ped Improvements
Source: Alameda CTC, February 2024

ACTC PS&E: Expected Construction Impacts
Continuous Single-Lane Tube Closures
• Posey Tube: two-year continuous single lane closure
• Webster Tube: 8-month continuous single lane closure
• The two closures overlap by 5 months.

Intermittent Full Tube Closures
• Posey: 23 nighttime closures and 8 full weekend closures spread over two years • Webster Tube: 10 nighttime closures over six months (no full weekends) PS&E = Plans, Specifications, and Estimates 5

City Concerns re Long-Term Single-Lane Closures
Severe impacts on Alameda community:
• Bus riders. Longer waits and much longer rides on all lines serving Alameda.
• Drivers. Major peak hour congestion at all Alameda
gateways.
• Business community. 380+ businesses in West
Alameda who rely on visitors and employees from
outside Alameda.

Alameda seniors catching the 51A from Mastick Senior Center City Actions to Address Concerns
City approach:

1. Proposing solutions to minimize daytime Tube lane closures

2. Informing and engaging community stakeholders
7 City actions spring/summer 2024 :
• Multiple meetings with ACTC, Caltrans, AC Transit, OakDOT • Transportation Commission, City-AC Transit ILC
• Inform & engage community stakeholders
• Letter to Caltrans supporting project with conditions of approval • ACTC meetings: Programs & Projects Committee (PPC), full Commission

1. Seeking Solutions to Minimize Tube Closures
• Developed construction strategies:
o Posey Tube – Reduce lane closures
o Webster Tube – Eliminate daytime single-lane closures and construct with full Tube closures at night (requires extended hours)
• Submitted comments & markups on PS&E, offering alternatives • Exploring ways to incentivize shorter closures through procurement process • Brought construction and contracting concepts to workshops with ACTC and Caltrans engineers
8 City Proposal Highlights
9 Posey Tube
• Constraint: Construction of large
column and retaining wall requires
lane closure.
• Proposal: Construct more components
simultaneously to reduce months
needed for lane closures.

Webster Tube
• Constraint: Need protection for workers
during construction.
• Proposal: Construct with full closures at
nighttime, and place precast curbs so
both lanes can open safely during the
day.

2. Engaging Community Stakeholders
• Met with business, nonprofit, and community leaders​
• Shared project benefits as well as anticipated closures​ • Will continue to advocate for early community engagement and greater transparency throughout the project
10 Sept 26 Alameda CTC Motion
Approve actions to continue OAAP and direct staff to:
• Analyze opportunities to reduce construction-related impacts on travel through the Webster and Posey tubes
• Work to minimize impacts to transit operators
• Continue engaging in stakeholder workgroups, in particular with the City of Alameda, and effectuate close communication
• Return to the Commission no later than the December 5, 2024, regular Commission meeting with an update
11 Next Steps
12 Immediate / Fall 2024:
• Continue to work with ACTC and Caltrans on construction solutions • Review OAAP communications plan (prepared by Caltrans) • Continue engaging community stakeholders
• November ACTC PPC meeting
December 2024:
• ACTC takes bid-ready project documents to California Transportation Commission (deadline for $70MM funding)
• ACTC reports to full Commission
Staff Recommendation
Receive an update on construction
impacts from the Oakland Alameda
Access Project
13