Willie Stargell Ave
Complete Street Corridor:

Concept Plan
City Council
April 15, 2025
alamedaca.gov/stargell
1 Background
and Goals
2 Project Location
Stargell Ave
from Main St
to Mariner
Square Loop
3 Project Goals
Improve safety for all roadway users,
including by slowing traffic
Improve safe routes to schools
Improve transit service for re-routed Line 19
Increase walking and rolling connectivity
Reduce flooding
4 History and Existing Conditions
5 • Stargell originally planned as 4-
lane road from Main to Webster
• Today:
– Main to Fifth St is 2 lanes with City-
owned vacant land on north side
– Fifth to Webster is 4-6 lanes, with
turn pockets

Project Timeline
6 2020
Engagement
Kickoff
2022
Draft Concept
2024
Concept
Revisions
2025-2026
Environmental,
Design
2027/28
Begin
Construction
Community Engagement
7 460
Online Survey
Responses
20 Stakeholder
Groups
Involved
5 Focus Meetings:

Affordable
Housing
2 Community
Workshops
Key Community Concerns
• Excessive Speeding
– “Harrowing because of speeding cars”
• Challenging Pedestrian Crossings
– “Many speeders who just don’t stop for
pedestrians and children coming home
from school”
• Lack of Bike Facilities
– “I don't feel safe riding a bike on the
street.”
8 Concept Plan Review
9 10
Corridor Concept Features
Traffic calming
Walking path and crosswalk safety enhancements
Bike path and separated bike lanes
New bus stops for the re-routed Line 19
Two intersection roundabouts
Concept Cross Section
11 Draft Concept Plans: Main Street
12 Bicycle
Path
New ADA
Ramps Pedestrian
Path
Draft Concept Plans: Mosley Avenue
13 Horizontal
DeflectionNew Bus
Stop
Median
Refuges with
RRFBs
New Bus
Stop
Bicycle and
Pedestrian
Paths
Draft Concept Plans: Coral Sea Street
14 New Bus
Stop
Median
Refuges with
RRFBs
New Bus
Stop
To Shared
Path at Bette
Draft Concept Plans: Mariner Square
Loop to 5th Street
15 Separated
Bike Lane
Roundabout
(Mariner Square
Loop)
Roundabout
(5th Street)
Roundabout
Concepts
16 17
Intersection Crash History
High Injury Corridor
Reported Collisions, 2013-2023
• High Injury Corridor in Vision Zero Action Plan
• 11 crashes at intersections & between
• 2 pedestrian crashes between intersections
• 7 intersection broadside crashes
At 5th:
5 injury
crashes
At Mariner
Square:
2 injury crashes
Between:
4 injury
crashes
Sources: Federal Highway Administration,
NCHRP Report 1043 – Guide for Roundabouts

1. Proven Safety Treatment

2. More Resilient Infrastructure

3. Lower Life Cycle Costs

4. Reduced Congestion / Emissions

5. Landscaping / Green Infrastructure

6. Access Management
Why Build Roundabouts?
Stargell/5th Street

Stargell/Mariner Square Loop

Roundabout Phasing Approach
Phase 1 (2027-28):
• Build full corridor improvements plus Stargell/5th
Street roundabout
• Use modular materials, capture safety benefit
• Full construction at corners, with modular
construction in the middle of the circle
Phase 2 (2029+):
• Build Stargell Ave/Mariner Sq Loop, when funds
available
• Upgrade Stargell Ave/5th St with landscape and
green infrastructure, when funds available
Phase 2: Stargell/Mariner Square Loop
Phase 1: Stargell/5th Street
Opportunities for cost savings while
achieving safety benefit
• Permanent corners & ADA ramps
• Lower-cost materials at medians
and round center circle
Modular Roundabout Construction
Modular Roundabout Design

Phase 1 Funding
23 • Total Phase 1 Cost: $11.4 million
• Grant Funding to Date:
– MTC Safe Routes to Transit/Bay Trail (RM3) - $4.9 million – MTC Regional Active Transportation Program - $673,000 – MTC Active Transportation Design Technical Assistance - $300,000 • Other Potential Funding Sources:
– Alameda CTC Measure BB
– California Affordable Housing and Sustainable Communities Grant Resolution of
Local Support
Next Steps
24 • Finalize Funding Plan (2025)
• Re-routed Line 19 begins service, with interim bus stop improvements (Aug 2025) • Finalize Design/Environmental (2025)
• Plans, Specifications, and Engineering (2026)
• Construction (2027/28)
Recommendation
25 1) Endorse the design concept for the Willie Stargell Avenue Complete Street Corridor
2) Adopt a Resolution of Local Support authorizing the filing of an application for funding assigned to MTC, committing any necessary matching funds and stating assurance to complete the project.
26 Questions?