Project Status:
Dressing rooms complete
Lighting and AV infrastructure complete
Next Steps:
Fire curtain under fabrication
Challenges:
Existing conditions required fire curtain redesign
Long lead times for fire curtain, and hoists for fire curtain and main curtain 1 Measure B
Alameda High School Kofman Stage Upgrades
Estimated Completion Date: Mid-November 2025
Soft Opening for School use only: December 2025
Open for Permitting: June 2026
2 Alameda High School Kofman Stage Upgrades
Completed standard dressing room
Measure B
Completed large dressing room
Completed new accessible toilet room
3 Alameda High School Kofman Stage Upgrades
View of scaffolding at stage
Fire curtain overlap wall extension above stage
Measure B
Project Status:
Under ACEHD oversight, (Impacted Soil Delineation, Dewatering, etc.) Construction activities resumed after cleanup delay
Next Steps:
Under ACEHD oversight, develop a cleanup plan and execute it Challenges:
Impacted soil found during demolition
Testing and Soils Management Plan development to dispose of impacted soil ACEHD oversight: turnaround time and number of deliverables requested Schedule and cost impacts to date
4 Measure B
Alameda High School Swim Center
Estimated Completion Date: June 2026
Alameda High School Swim Center
Measure B
5 Schematic Design
Current State of the Site
Project Status:
Fencing complete
Soccer/football field complete
Lights, sound system, score board complete
Next Steps:
Synthetic Field Turf installation
Challenges:
Delayed project start due to Bay Conservation & Development Commission (BCDC) Coordination with City on Storm Drain relocation
Site being by the bay = Dewatering impacts
6 Encinal Jr/Sr High School Stadium and Field Renovation Measure B
Estimated Completion Date: Mid-November 2025
Soft Opening for School use only: December 2025
Open for Permitting: June 2026
Encinal Jr/Sr High School Stadium and Field Renovation
Measure B
7 Project Status:
Building 100 (Admin/Media Center) and Building 300 (Gym) : Framing walls, electrical rough-in Building 400 (Classrooms): Steel structure
Challenges:
Responding to neighbor questions and complaints
DTSC review
City’s Grand Street improvement projects starting
8 Measure B
Wood Middle School New Construction
Estimated Completion Date: Summer 2026
9 Wood Middle School New Construction - Classrooms
Measure B
Project Status:
DSA reviewing design
Coordinating with City of Alameda
Contractor performing Preliminary Services
Next Steps:
Planning for the move
Challenges:
City Storm Drain Relocation Coordination
Potential prolonged approval process from Department of Toxic Substances Control (DTSC) Potential neighborhood complaints during pile driving
10 Otis Elementary School New Construction
Measure B
Estimated Completion Date: Summer 2028
Otis move to the Temp Campus: June 2026
11 Otis Elementary School New Construction
Conceptual rendering: Ariel View
Measure B
Conceptual rendering: Campus Entry
Project Status:
Board recently approved Schematic Design
Next Steps:
Submit to Division of the State Architect (DSA) this fall Challenges:
Potential extensive dewatering during excavation
12 Encinal Jr/Sr High School New Gymnasium
Measure B
Estimated Completion Date: Fall 2027
13 Encinal Jr/Sr High School New Gymnasium
Conceptual Rendering: View from the Stadium
Rendering: Weight Room w/ View to Stadium
Measure B
Conceptual Rendering: Gym Interior