Alameda Unified School District – City of Alameda Subcommittee September 10, 2025
Clement Avenue /
Tilden Way
Improvement Project
City of Alameda

Agenda
• Location and Overview
• Timeline
• Construction Impacts
• Construction Outreach

Location
Overview
Project Goals and Intended Outcomes
 Prioritize safety
 Improve mobility for all roadway users
 Improve bicycle and pedestrian access
 Provide landscaping opportunities
 Reduce greenhouse gas emissions
 Comply with City plans and policies

Project Overview
Project Scope (includes but not limited to)
• Cross Alameda Trail gap closure at Clement Avenue
• SF Bail Trail Connection
• Roundabout at Tilden/Blanding/Fernside Intersection
• Road diet at Tilden Way with vehicle travel lane
reductions
• Clement Avenue extension between Tilden and
Broadway
• Landscape Improvements
• Dog Park Construction
• Bike/Pedestrian improvements at Tilden Way/Broadway
• Bicycle/Pedestrian improvements and paths
• Rail platform/track removal

Timeline
2022 – Preliminary
Concept Plan
•Public Input:
•surveys
•workshops
•open house
•Public Input:
•surveys
•workshops
•open house
2023 – Final
Concept Plan
•Transportation
Commission
endorsement
•City Council
approval
•Transportation
Commission
endorsement
•City Council
approval
2024 - Design
•Begin PS&E
•Begin PS&E
2025 - Design
•Finalize PS&E
•Bidding
•City Council award
contract
•Finalize PS&E
•Bidding
•City Council award
contract
2025 - Fall
•Pre-construction meeting
•Schedule review
•Pre-construction outreach
•Start Construction
•Construction updates outreach
2026-Fall
Complete Construction
WHERE WE’VE BEEN
WHERE WE’RE
GOING
Construction Impacts – Stage 1

TILDEN WAY
Construction Impacts – Stage 2

TILDEN WAY

BLANDING

Construction Impacts

TILDEN WAY

BLANDING
• Staged construction –
5 phases
• Biggest impacts to
Edison – Phases 2 & 3
Construction Impacts – Stage 4

TILDEN WAY

BLANDING

Construction Impacts – Stage 5

TILDEN WAY

BLANDING

Citywide/AUSD Impacts
City Impacts/AUSD During Phases 2 & 3
• Local traffic to detour at Versailles/Buena
Vista when Fernside is closed
• Electronic Message Board Signs ( )
will encourage city/island wide traffic to
use Encinal Avenue when Fernside is
closed
• Close coordination with Edison
Elementary/AUSD on school traffic
routing

Impacts at Edison

ENCINAL
• Staged construction – 5 phases
• Biggest impacts to Edison – Phases
2 & 3
• Local traffic to detour at Versailles >
Buena Vista when Fernside is
closed
• CMS Signage - Island-wide Traffic
encouraged to use High > Encinal
• Close coordination with Edison
Elementary/AUSD on school traffic
routing and schedule
Local Traffic
Island-wide
Traffic

Impacts at Lincoln
• Island-wide traffic encouraged
to use Otis > High > Encinal
during Fernside closure
• CMS Signage - Detoured traffic
to avoid Fernside and Lincoln
Middle School
Island-wide
Traffic

Recent and Upcoming Outreach
City
 Meeting with AUSD Construction Manager and Edison Principal: September 4  Letters/Mailers to Businesses/Property Owners/Residents within 300ft of the work area and detours:

September 10
 Virtual Open House Meeting: September 30
 Meet with businesses at Bridgeside Shopping Center
 Construction/Schedule Updates on Project Website
 Press Releases/Social Media
 Monthly Email updates to stakeholders
Contractor
 Hand deliver notices to impacted businesses/residents  Parking restriction signage, with dates/hours
 Notify area services (AC Transit, ACI, Emergency, USPS)