Alameda City Facilities Plan
Interim and Long-Term Plans and Strategies to Address Infrastructure Needs for City Facilities and Public Safety Facilities July 7, 2026
1 Recommendations
2 Site
Recommendation
Fire Station 1
Expand into Fire Admin area
Fire Admin
Relocate to leased facility and/or new FS5
Fire Station 2
Remodel
Fire Station 4
Remodel
Fire Station 5
New Station at one of Alameda Point locations identified Fire Training Center
New Center at enlarged existing site
Fleet Services Garage
Relocate to combined campus
Maintenance Service Center
Remodel and expand into existing fleet and animal shelter area Rec & Parks Yard
Relocate to combined campus
Animal Shelter
Relocate to combined campus
Cost Summary
3 Site
Project Cost
(construction, escalation and soft costs)
Fire Station 1
$10,304,000
Fire Admin (combined with FS5)
$20,293,000
Fire Station 2
$11,497,000
Fire Station 4
$5,094,000
Fire Station 5
$54,690,000
Fire Training Center
$61,608,000
Combined Campus (Fleet, Rec & Park, Animal Shelter)
$157,684,000
Maintenance Service Center (expanded)
$21,184,000