AMERICAN CANYON SR-29
CORRIDOR IMPROVEMENTS:

PROJECT UPDATE & FUNDING

STRATEGY
• September 15, 2026
• Danielle Schmitz
• Executive Director
• Grant Bailey, P.E.
• Program Manager - Engineer
2 R 29 Corridor
American Canyon SR 29 Corridor
Purpose of Today’s Update
• Project Scope Review
• Update on Project Status Since February
2026 Council Meeting & Upcoming
Milestones
• Project Schedule
• Funding Strategy Recommendation
3 R 29 Corridor
American Canyon SR 29 Corridor
Project Scope
Curb
Ramps
Dedicated
Bike & Ped
Trails
Shorter
Crossings,
Median
Refuges
Landscaping
& Trees
Bus
Queue
Jumps
Underground
Utilities
Adaptive
Signals
Leading
Pedestrian
Interval
R 29 Corridor
American Canyon SR 29 Corridor
Since We Last Met
• Selected Preferred Alternative
• Signalization improvements selected as
build alternative in April 2026
• Public Workshop #2 held in May 2026
• Public Feedback Received:
• ClassI trail composition
• Mobility hub location
• General Input
• Upcoming Milestones:
• January 2027 – Release Draft
Environmental Document
• March 2027 – Approve Final ED and
Project Report
• April 2027 – Kickoff design phase work
4 R 29 Corridor
American Canyon SR 29 Corridor
Project Schedule
NOW–MAR 2027
Environmental
clearance
Obtain environmental
clearance and
Caltrans project
approval.
2027–2028
Final design
Prepare plans,
specifications
and estimate.
2028-2029
Right-of-way &
utilities
Acquire property
interests and
relocate utilities.

Construction
Construct
the project –
funding
dependent.
2029 - 2030
5 R 29 Corridor
American Canyon SR 29 Corridor
Project Funding Strategy
6 SR 29 American Canyon Corridor Improvements Funding by Phase Phase Funding Source Amount ($1,000s) Status FY
PAED OBAG 3 3,000committed 23-24
City of American Canyon 1,000committed 23-24
RM 3 700committed 23-24
PAED Subtotal 4,700
PS&E Congressional Earmark/RM3 2,000uncommitted 26-27
Local 2,000uncommitted 26-27
OBAG 4 2,000uncommitted 26-27
PS&E Subtotal 6,000
ROW/UTIL RM 3 1,000uncommitted 28-29
Local 3,000uncommitted 28-29
ROW/Utilities Subtotal 4,000
CON RM 3 3,000uncommitted 28-29
SS4A 10,000uncommitted 28-29
Measure U 3,000uncommitted 28-29
SB 1 30,000uncommitted 28-29
CON Support Measure U 7,000uncommitted 28-29
Construction Subtotal 53,000
Total Project Cost $67,700
American Canyon SR 29 Corridor
Funding Request
$5 million for design and right-of-way
phases
The request is structured to match the two pre-construction funding needs that follow environmental clearance.
$2M
Final Design (PS&E)
Needed as final design begins in 2027
$3M
Right-of-way & utility relocation
7 Anticipated for early 2029
Combined with the $1 million already invested, the City’s total project participation would be approximately $6 million.

American Canyon SR 29 Corridor
Relative City Share
Current project estimate
~$68M
$15M pre-construction + $53M construction
9%
91%
Total City investment
NVTA / regional /
state / federal
~9%
Total anticipated City share
~91%
$62M expected from NVTAand
regional, state and federal partners
8 Every $1 of total City investment is paired with
about $10.33 from other partners.
ouncil Direction
Requested Council Direction
Support a $5 million City contribution to NVTA’s State Route 29 American Canyon Corridor Improvements Project:
• $2 million for final design in 2027; and
• $3 million for right of way and utility relocation activities in 2029.