EXHIBIT A

Project: Euclid Street Improvement Project from Crescent Avenue to Glenoaks Avenue

The work to be done consists of cold planing existing asphalt pavement, constructing a new raised median with landscaping, resurfacing the road, removal and reconstruction of ADA access ramps, driveways, concrete sidewalk, adjustment of survey monument, sewer and storm drain manhole covers, the adjustment of traffic signal pull boxes to grade, replacement of water valve box assemblies, coordination of the adjustment of utility structures with utility purveyors, the replacement of traffic striping, traffic signal modification and all additional work necessary to properly construct the proposed improvements, in accordance with the contract documents. The goal of this improvement project is to provide for the safe and efficient movement of vehicle and pedestrians along this segment of Euclid Street.

Account No(s). 276-412-N839-7892, 278-412-N839-7897, 272-412-L271-7892, 502-521-3743-7856-2001285-01

LOWEST AND BEST RESPONSIBLE BIDDER: EBS General Engineering, Inc. 1345 Quarry Street, Suite 101
Corona, CA 92879

PUBLICATION DATES: 1/20/2022, 1/27/2022, & 2/3/2022

BID OPENING DATE: 2/17/22

PREVAILING WAGE RATES: Per Current D.I.R. Publication

AWARD DATE: April 12, 2022

CONTRACT PRICE: One-Million Five-Hundred Seventy-
Thousand Six-Hundered Seventy –
Eight and no cents
($1,570,678.00)

CONTRACT COMPLETION DAYS: Sixty (60) Working Days

LIQUIDATED DAMAGES: Three-Thousand Seven- Hundred
and Fifty Dollars ($3,750.00) Per
Day