EXHIBIT A
Project: Underground District No. 67 Sycamore Street
Scope of Work: The work consists of undergrounding of 12kV distribution and telecommunication systems, street light installation, service conversions, and removal of overhead facilities on Sycamore Street from Anaheim Boulevard to East Street; and on East Street from Adele Street to Eastwood Drive, including adjoining portions of Claudina Street, Emily Street, Philadelp hia Street, Olive Street, Sabina Street, Pauline Street, Vine Street, Bush Street, Rose Street, Flower Street, and Glenwood Avenue.
Account No(s). 525-521-6771-7865-2200236-01; 525-521-6771-7865-2200238-01; 525-521-6767- 7865-2200333-02; 525-521-6771-7865-2200240-01; 525-521-6771-7865-2200241-01; 525-521-6771- 7865-2200242-01; 525-521-6771-7865-2200243-01; 525-521-6771-7865-2200244-01; 525-521-6771- 7865-2100271-01; 525-521-6771-7865-2200237-01; 525-521-6771-7865-2200239-01; 528-521-6753- 7865-2200289-01
RCP2021-18164
Project Funding Source: Restricted Electric Utility Enterprise Funds. This project is part of the City of Anaheim Underground Conversion Five-Year Plan and CIP.
LOWEST AND BEST RESPONSIBLE BIDDER: Asplundh Construction LLC 7431 Walnut Ave,
Buena Park, CA 90620
PUBLICATION DATES: 1/13/2022 & 1/20/2022
PRE-BID MEETING 2/07/2022
BID OPENING DATE: 2/17/2022
PREVAILING WAGE RATE RESOLUTION NO: Per Current D.I.R. Publication
AWARD DATE: April 12, 2022
CONTRACT PRICE: Ten Million, Four Hundred Sixty Three
Thousand, Five Hundred Ninety Five Dollars
and Forty-Six Cents
($10,463,595.46)
CONTRACT COMPLETION DAYS: Three Hundred Sixty (360) Working Days
LIQUIDATED DAMAGES: One Thousand Dollars ($1,000.00)
Per Calendar Day