Cities Index.
1. Change Order No. 1

Anaheim City Council
June 7, 2022

Document
1. Change Order No. 1
Meeting
June 7, 2022
Body
Anaheim City Council
Pages
2
Original file
280 KB
Text extracted from the city's file for reading and search. Open the original on local.anaheim.net. That file is the official record.
Page 1 of 2 ends

CHANGE ORDER: # 1 DATE:
1O F 1
TO:

ITEM UNIT $ QTY. UNIT $ QTY. TOTAL
1 8,711.16 $           1 8,711.16 $
2 7,936.76 $           1 7,936.76 $
TOTAL  16,647.92 $
Original Work Order Amount: 88,400.00$
Previous Change Orders: ‐$
Revised Work Order Amount: 88,400.00$
This Change Order: 16,647.92$
Revised Work Order Amount: 105,047.92$
Total Percentage Cost Increase this EWO: or Total Percentage Cos t Increase to Date: 18.83% By reason of this order, the NEW time of completion will be adjusted as follows: Add 0 working days Recommended: Date:

Recommended: Date:

Approved: Date:

Approved: Date:

CITY OF ANAHEIM
RFWOP 2021 ‐ Nohl Ranch Road Sanitary Sewer Improvements (RCP2021‐18626, AGR11511 On‐Call Contract)
592‐412‐I799‐7809
Mike Prlich and Sons, Inc.

You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the p lans and specifications on this contract.

Attn: Michael Prlich
4/28/2022
SHEET ACCOUNT NO.

DESCRIPTION

ADD DELETE
NOTE: This order is not effective until approved by the Director of Public Works, or an authorized representative. Include description of the work to be done, estimate of quantities, and prices to be paid. Segregate between addition al work at contract price, agreed price and force account. Unless otherwis e stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time.

Operating Department Manager
Unforeseen Utility ‐ Verification and removal of 2"
inactive Spectrum cable conduit located on top of
proposed sewer improvement, 18" below ground
surface.

Unforeseen Utility ‐ 4" High Pressure Gas line not
identified by USA markings, found adjacent to
proposed sewer improvement at STA 11+87 inside
the trench. Increased effort and time for contractor
to safely proceed with work.

STATUS OF CONTRACT
Contract Administration
Construction Services Manager
Public Works Director

Page 2 of 2 ends

CHANGE ORDER: # 1 DATE:
1O F 1
TO:

RFWOP 2021 ‐ Nohl Ranch Road Sanitary Sewer Improvements (RCP2021‐18626, AGR11511 On‐Call Contract)
592‐412‐I799‐7809
Mike Prlich and Sons, Inc.

You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract.

Attn: Michael Prlich
4/28/2022
SHEET ACCOUNT NO.

NOTE: This order is not effective until approved by the Director of Public Works, or an authorized representative. Include description of the work to be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time.

Accepted By: Title:

Date Accepted: Contractor:

We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all labor & materials, except as may be otherwise noted above, and perform all services necessary to complete the above specified work, and will accept as full payment which includes compensation to the Contractor for all direct costs, profit, indirect costs and expenses it has or may incur in connection with this change in the Contractor's work, including but not limited to all costs, expenses and damages for any delay, interference or hindrance in connection with the performance of Contractor's original work.  Contractor also agrees that payments under this Change Order are full satisfaction and settlement of all such costs, expenses and damages related thereto.  This Change Order is accepted by Contractor unless written objection is delivered to Owner within 10 days of the date of this Change Order.

Project Manager
5/2/22
MIKE PRLICH & SONS, INC.

EUGENIO MATEO

← All documents from this meeting