EXHIBIT A

Project: Electric Line Extension (Wanda Circuit) Project, Phase 2 & Union Pacific Railroad Company Wireline Crossing Agreement

The work to be undertaken consists of installing 12kV substructures and electrical equipment along Ball Road between Claudina Street and State College Boulevard.

Account No(s). 528-521-6768-7865-1800664-01, 528-521-6768-7865-1800663-01, 528-521-6768- 7865-2200123-01, 528-521-6768-7865-2200122-01, 272-412-L281-7892 RCP2020-17735

Project Funding Source: Electric Utility Enterprise Funds

LOWEST AND BEST RESPONSIBLE BIDDER: Hampton Tedder Electric Company 4571 State Street
Montclair, CA 91763

PUBLICATION DATES: March 24, 2022 & March 31, 2022

BID OPENING DATE: May 5, 2022

PREVAILING WAGE RATE RESOLUTION NO: Per Current D.I.R. Publication

AWARD DATE: June 7, 2022

CONTRACT PRICE: $6,815,393.90
(Six Million, Eight Hundred Fifteen
Thousand, Three Hundred Ninety Three
Dollars and Ninety Cents)

CONTRACT COMPLETION DAYS: One Hundred Eighty (180) Working Days

LIQUIDATED DAMAGES: One Thousand Dollars ($1,000) Per Day