Project: Lincoln Avenue Sanitary Sewer and Street Improvements from Dale Avenue to Magnolia Avenue
The
work consists of removal of existing sanitary sewer facilities, installation of new 12-inch, 15-inch, and 21- inch diameter
Vitrified Clay Pipe (VCP), construction of sanitary sewer manholes, manhole modification, rehabilitating
the asphalt concrete roadway, Portland Concrete Cement (PCC) sidewalks, ADA access ramps, curb & gutter, pavement markings, repainting curbs, and all appurtenant work as shown on the plans and specifications.
Account No.: 591-412-I788-7895; 211-412-I788-7895, 592-412-L277-7895; 502-521-3743-7865-1901128;
RCP #2019-15708 & RCP #2021-18877
LOWEST AND BEST RESPONSIBLE BIDDER:
PUBLICATION DATES:
BID OPENING DATE:
PREVAILING WAGE RATES:
AWARD DATE:
CONTRACT PRICE:
CONTRACT COMPLETION DAYS:
LIQUIDATED DAMAGES:
CEM Construction Corporation
1412 Espanol Ave.
Montebello, California 90640
8/11/2022, 8/18/2022, & 8/25/2022
9/1/2022
Per current D.I.R. Publication
10/4/2022
$1,721,945.50
One Million Seven Hundred Twenty One
Thousand Nine Hundred Forty Five
Dollars and Fifty Cents
One Hundred Twenty (120) Working
Days
One Thousand Six Hundred Dollars
($1,600) Per Day