Anaheim's Portion of Placentia 21-22 Arterial Rehab
Project ALL AMERICAN
ASPHALT
Jefferson St. (From Miraloma Ave to Orangethorpe), Van Buren St. (From Miramola Ave to Orangethorpe Ave.) , and Richfield Rd. (From La Palma to Miraloma Ave)
ITEM
NO. ITEM DESCRIPTION BID QTY. UNIT
PRICE TOTAL
1 Mobilization 0.055 LS $115,00
0.00 $6,325.00
2 Traffic Control and Public safety 0.055 LS $122,00
0.00 $6,710.00
3 Best management practices 0.055 LS $35,000.
00 $1,925.00
4 Surface preparation and crack seal 0.055 LS $50,000. 00 $2,750.00
5 2" cold mill 102,27
5 SF $0.14 $14,318.50
6 3.25" cold mill 7,753 SF $0.58 $4,496.74
7 AC pavement 58.551
31 TON $96.00 $5,620.93
8 ARHM placement 1,357.0
12 TON $120.00 $162,841.44
9 Saw cut and remove existing (joint to joint) and
reconstruct 4" PCC sidewalk per SPWWC Std.
Plan 113-2
845 SF $13.00 $10,985.00
10 Saw cut and remove existing (joint to joint) and
reconstruct PCC curb and gutter (height to match
existing) per SWPPWC 120-2, Type A, include 1'
wide AC slot trench
100 LF $85.00 $8,500.00
11 Saw cut and remove existing (joint to joint) and
reconstruct 6" pcc curb per SPPWC 120-2, type
A1-6, include 1' wide AC slot patch
31 LF $90.00 $2,790.00
12 Saw cut and remove existing (joint to joint) and
reconstruct PCC curb (height to match existing)
per SPPWC 120-2, TYPE A1, include 1' wide AC
slot patch
28.5 LF $90.00 $2,565.00
13 Remove survey ring and cover. Contractor to
Coordinate with City Surveyor before removal of
existing ring and cover
1 EA $1,000.0
0 $1,000.00
14 Lower, raise and adjust COA sewer manhole to
final grade per COA std plan 205-1 2 EA $1,000.0
0 $2,000.00
15 Remove existing surface and construct a 6"
depth PCC driveway per COA std plan 115-B,
case 2. include 1' AC slot patch.
800 SF $22.00 $17,600.00
16 APU to adjust all electric utility vaults. Please
contact APU Electrical Engineering to plan for
electric utility vault adjustment
3 EA $100.00 $300.00
17 Lower, Raise and adjust water valve box
assembly to final grade per COA std. W-152,
Case 1
21 EA $900.00 $18,900.00
18 Lower, raise and adjust water valve box
assembly to final grade per COA std. W-152,
Case 3. Replace 4ttt box with Bingham & taylor
Mark V 10"
1 EA $900.00 $900.00
19 Adjust existing sewer manholes to grade 1 EA $1,000.0 0 $1,000.00
20 Adjust existing traffic signal pullbox to grade 1 EA $800.00 $800.00 21 Adjust existing monitoring wells to grade 1 EA $900.00 $900.00 22 Remove and clear existing surface tree roots 32 LF $25.00 $800.00 23 Grind existing sidewalk 7 SF $20.00 $140.00
24 Survey Markers and monument preservation and
restoration and construction staking 0.055 LS $48,204. 00 $2,651.22
25 Signing, striping, markings and pavement
legends. 0.060 LS $200,00
0.00 $12,000.00
Subtotal $288,818.83
Construction Contingency (10%) $28,881.88
Construction Management (10%) $28,881.88
Grand Total $346,582.59