95 Enterprise • Suite 200 • Aliso Viejo, CA 92656 • Phone: 949.448.1600 • Fax: 949.448.1696
LEN A
October 10, 2022
Mr. Scott Koehm
City of Anaheim
Planning & Building Department
200 South Anaheim Boulevard
Anaheim, CA 92805
Via Email Delivery
Subject: Development Agreement Annual Review - A-Town
Dear Mr. Koehm,
Pursuant to Section 26.1 of Development Agreement No. 2005-00008, Lennar is submitting this letter to the City of Anaheim for the annual review of good faith compliance with the terms of the Development Agreement.
1) All the 5th anniversary milestones listed in the Exhibit G of the Development Agreement have been completed:
o Dedication of ultimate right-of –way for Gene Autry Way (remaining perimeter arterial), Market Street and internal connector streets:
Resolution Numbers 2019-145, 2019-146 and 2019-147 approved on December 3, 2019 and corresponding Easement Deeds (Instrument Numbers 2020000074849 and 20200000072245) recorded on February 20, 2020
o Completion of all Public Facilities/Infrastructure (Phase 1 and Phase 2 Infrastructure) Street Improvements (including landscape) Phase 1 - completed in June, 2018, Street Improvements (including landscape) Phase 2 - completed in August, 2019, Water Installation Phase 1 – completed in March, 2017, Water Installation Phase 2 – completed in February, 2018, Sewer Improvements – completed in December, 2016,
Strom Drain Installation – completed in October, 2017, Traffic Signal Installation – completed in August, 2018. o Completion of the Public Park:
Construction completed in October 2020.
o A full Final Site Plan application for 150 residential units:
Final Site Plan approved for a total of 238 residential units: 84 on Development Area H and 154 on Development Area G.
DocuSign Envelope ID: 0DCDA6BD-58B7-48C5-BC26-24BA265B1855
95 Enterprise • Suite 200 • Aliso Viejo, CA 92656 • Phone: 949.448.1600 • Fax: 949.448.1696
o Completion (approval of final building inspections) of 400 residential units:
4oo residential units completed on June 26, 2019 on Development Area A.
2) 7th and half year milestones:
o Completion (approval of final building inspections) of an additional 150 residential units (550 total residential units completed):
Development Area G: construction of 126 units completed; the remaining 28 units are scheduled to be completed by November 2022.
Development Area H: construction of 69 units completed the remaining 15 units are scheduled to be completed by November 2022.
In addition, three (3) more Final Site Plans were approved by the Planning Commission:
a) On January 19, 2022, Final Site Plan No. 2021-00002 for Parcel B to construct a mixed-use project with 270 residential units and 21,669 sqft of ground floor commercial space with 505 square feet of accessory outdoor dining. Construction to begin in a first quarter of 2023. b) On January 19, 2022, Final Site Plan No. 2021-00003 for Parcel E to construct a multiple-family development with 257 residential dwelling units. Construction to begin in a first quarter of 2023. c) On July 6, 2022, Final Site Plan for Parcel F (Development Permit No. 2021-00131) to construct a for-sale single-family attached development with 73-residential dwelling units. Construction to begin in a first quarter of 2023.
Furthermore, Final Site Plan application for the Development Areas C and D have been submitted to the City for mid-2023 approval.
Please feel free to contact me with any questions or concerns. Thank you for your assistance with this matter.
PT METRO, LLC, a limited liability company
By: Lennar Homes of California, Inc.,
a California corporation
Its: Sole M ember
By: _______________
Name: Ryan Gatchalian
Its: Vice President
DocuSign Envelope ID: 0DCDA6BD-58B7-48C5-BC26-24BA265B1855