CITY COUNCIL AGENDA REPORT
City of Anaheim

DEPARTMENT OF PUBLIC WORKS
DATE: FEBRUARY 28, 2023
FROM: DEPARTMENT OF PUBLIC WORKS
SUBJECT: AWARD OF CONTRACT FOR CONCRETE FACILITIES
REMOVAL AND REPLACEMENT – CITYWIDE PHASE 9
ATTACHMENT (Y/N): YES ITEM # 14
GOVERNMENT CODE § 84308 APPLIES: NO
RECOMMENDATION:

That the City Council, by Motion, award the construction contract to the lowest responsible bidder, Stance Construction Company of Chino, California, Contractor's License No. 1071898, Classifications A, in the amount of $1,205,691.50, for the Concrete Facilities Removal and Replacement - Citywide Phase 9 Project; direct and authorize the Director of Public Works, on behalf of the City, to execute the Contract and any other related documents, and to take such actions as are necessary or advisable to implement and administer the Contract; direct and authorize the Finance Director to execute the Escrow Agreement pertaining to contract retentions; and determine that the Project is categorically exempt from the California Environmental Quality Act (CEQA) pursuant to Sections 15301, Class 1, and 15302, Class 2, of Title 14 of the California Code of Regulations.

DISCUSSION:

The bids are summarized as follows:

1. Stance Construction Company, Chino CA $1,205,691.50

2. Towo Enterprise, Inc., Fullerton, CA $1,324,193.75

3. Onyx Paving Company, Inc., Anaheim, CA $1,572,000.00

4. CT&T Concrete Paving, Inc., Diamond Bar, CA $1,828,360.00

5. EBS General Engineering, Inc., Corona, CA $2,255,141.00 The Concrete Facilities Removal and Replacement - Citywide Phase 9 project is part of an annual concrete rehabilitation program that addresses the replacement of damaged concrete throughout the city.

The work consists of rehabilitating and constructing new concrete curb and gutter to re- establish the drainage patterns to their original design. The project improvements will also include the replacement of uneven and broken sidewalks and constructing Americans with Award of Contract for Concrete Facilities Removal And Replacement - Citywide Phase 9 Project February 28, 2023

Page 2 of 2 ends

Disabilities Act (ADA) curb access ramps, and all appurtenant work as shown on the plans and delineated in the specifications.

The bid for this project from Stance Construction Company is found to be favorable when compared to the engineer’s estimate, reflects the current bidding atmosphere, appears to be reasonable, and is within available funding.

Construction schedule is set begin in Spring 2023 and conclude in Summer 2023. Liquidated damages for this project shall be $3,400 per day.

COMMUNITY WORKFORCE AGREEMENT (CWA):

This project is acknowledged “Project Work” as defined in the CWA the city entered into with the Los Angeles/Orange Counties Building and Construction Trades Council and the Signatory Craft Councils and Local Unions.

ENVIRONMENTAL DETERMINATION:

Upon review of the California Code of Regulations (CCR), staff recommends the City Council determine that the Project is Categorically Exempt from CEQA pursuant to Sections 15301, Class 1, and 15302, Class 2, of Title 14 of the CCR. Section 15301 allows for the repair, maintenance, or minor alteration of existing public improvements and Section 15302 allows for the replacement or reconstruction of existing improvements that will be in the same site and will have substantially the same purpose and capacity. The proposed improvements will be restoring and repairing the existing concrete located within existing street right-of-way with no expansion of capacity. Staff will file CEQA Notice of Exemption (NOE) upon approval by City Council.

IMPACT ON BUDGET:

Funding for the project is available in Public Works’ Fiscal Year 2022/23 General Fund budget.

Respectfully submitted,
Rudy Emami
Director of Public Works