CITY COUNCIL AGENDA REPORT
City of Anaheim
DEPARTMENT OF PUBLIC WORKS
DATE: APRIL 18, 2023
FROM: DEPARTMENT OF PUBLIC WORKS
SUBJECT: AWARD OF 2023 MASTER AGREEMENT FOR LANDSCAPE AND
IRRIGATION CONSTRUCTION, REPAIR, AND IMMEDIATE
RESPONSE SERVICES
ATTACHMENT (Y/N): YES ITEM # 17
GOVERNMENT CODE § 84308 APPLIES: YES
RECOMMENDATION:
That the City Council, by Motion:
1) Determine that the projects to be performed under the attached Master Agreement shall be categorically exempt under the California Environmental Quality Act (CEQA), Sections 15302, 15303, and/or 15304 of Title 14 of the California Code of Regulations;
2) Approve the Master Agreement for Landscape and Irrigation Construction, Repair, and Immediate Response Services (Master Agreement) between the City of Anaheim (City) and prequalified contractors, for a three-year period, with three (3) one-year optional extensions, and approve a not-to-exceed award amount of $1,000,000 per work order package excluding change orders; 3) Authorize the Director of Public Works or designee, on behalf of the City, to execute the Master Agreements with C.G. Landscape, Inc., Greentech Landscape, Inc., Oakwest Services, Inc. and SGD Enterprises DBA Four Seasons Landscaping, and such other prequalified contractors as may be prequalified during the term of the agreement; and to take such actions as are necessary to implement and administer the Master Agreements, including any extensions; and 4) Authorize de minimis changes that do not substantially change the terms and conditions of the Master Agreement, as determined by the City Attorney.
DISCUSSION:
The Department of Public Works is recommending that the City Council award contracts to the listed responsive and qualified contractors to supplement the Department’s efforts, which fall outside routine maintenance activities, which include but are not limited to: tree removal and/or replacement; irrigation system renovation; palm tree root pruning and tree stump grinding; removal and replacement of ground cover, shrub and sod; top soil replacement; root and debris removal from electrical boxes all at various locations within the City limits.
Award of 2023 Master Agreement for Landscape and Irrigation Construction, Repair, and Immediate Response Services April 18, 2023
The City Council approved the existing agreement on March 10, 2020, with an effective date of April 17, 2020. The existing agreement is set to expire on April 23, 2023.
The use of this Master Agreement provides the Department with the flexibility to respond urgently to matters which impact the traffic, businesses, and the public. This Master Agreement helps to reduce time and/or cost by providing the Department with a mechanism to competitively and expeditiously contract with qualified contractors to perform time sensitive, specialized maintenance and/or repair activities as needed from time to time without increasing the burden on staff or the need to rent or purchase specialized equipment.
Liquidated damages for this project will be $500 per day, or as assigned and determined per work order package.
Pre-Qualification Process
All interested contractors were invited to complete a pre-qualification questionnaire and provide supplemental background information demonstrating their expertise, skills, and breadth of experience in dealing with projects such as those that will be required in this Master Agreement. The pre- qualification process is in line with the Public Contract Code Section 20101and city staff utilized the questionnaire format developed by the California Department of Industrial Relations.
On February 9, 2023, the prequalification application package was advertised on the City’s electronic bidding system and thirty (30) companies downloaded the package. Public Works received four qualification proposals; all were determined to meet the minimum pre-qualification requirements and are recommended for the Master Agreement.
ENVIRONMENTAL DETERMINATION:
The projects to be undertaken under this Master Agreement will consist of replacements, repairs, and maintenance, which fall into the following CEQA Categorical Exemptions: Section 15302, Section 15303 and/or Section 15304 of Title 14 of the California Code of Regulations.
IMPACT ON BUDGET:
Adequate funds are available in the Public Works Department’s Fiscal Year 2022/2023 Budget.
Respectfully submitted,
Rudy Emami
Director of Public Works