EXHIBIT A
Project: Santa Ana Canyon Road South Slope Repair and Storm Drainage Improvements East of Lakeview Avenue
The work consists of excavation, installation of a slope retention system, backfilling and compaction, installation of jute matting and a bonded fiber matrix, hydroseeding, construction of slope drains, removal of an existing catch basin structure and installation of a new transition structure connected with a new 12-inch RCP pipe to an existing catch basin along the south side of Santa Ana Canyon Road, traffic control, and all appurtenant work as shown on the plans and specifications.
Account No.: 592-412-J739-7892
RCP #2021-18910
LOWEST AND BEST RESPONSIBLE BIDDER: ACE Capital Engineering 21771 Fernleaf Drive
Lake Forest, CA 92630
PUBLICATION DATES: 5/25/2023, 6/1/2023, 6/8/2023
BID OPENING DATE: 6/15/2023
PREVAILING WAGE RATES: Per current D.I.R. Publication
AWARD DATE: 7/11/2023
CONTRACT PRICE: $189,950.83
One Hundred eighty-nine
thousand, nine hundred fifty
dollars and eighty-three cents
CONTRACT COMPLETION DAYS: Thirty (30) Working
Days
LIQUIDATED DAMAGES: One Thousand Dollars
($1,000) Per Calendar Day