ROM ESTIMATE
for
City of Anaheim
Prepared for : City of Anaheim, CA
May 31, 2023
#xx-xxxx

#xx-xxxx
City of Anaheim 31-May-23
Component Description Quantity Unit Cost $

1. Foundations
Reinforced concrete foundations
Column footings, 4'SQ x 3' 35 EA 1,800.00 63,000
63,000$

2. Floor and Roof Structure
Floor at grade
Sawcut, remove and replace concrete slab affected by
foundation work 350 SF 20.00 7,000
Concrete slab concrete crack cut out and repour misc.
locations 50,000
Suspended floor
Mezzanine level (50% area) 12,500 SF - -
Steel framing, columns and beams 30 TNS 7,500.00 225,000 Wood beams, joists and floor sheathing 12,500 SF 50.00 625,000 Roof, structure - no work
Staircase flights, floor to floor, including handrails and guardrails, allow 5' wide 1 EA 30,000.00 30,000
Miscellaneous wood, metal and concrete 1 LS 10,000.00 10,000 947,000$

3. Exterior Cladding
Storefront glazing removal and exterior hardening 135,000 Exterior doors, frames and hardware
Doors, frames and hardware, 3' x 7' - remove and replace existing 4 EA 3,000.00 12,000
Four roll up doors, guides, and motor operator - 120,000 267,000$
( 5 )

#xx-xxxx
City of Anaheim 31-May-23
Component Description Quantity Unit Cost $

4. Roofing and Waterproofing
Roofing
Patch and repair existing roof membrane (50% of roof area) 1 LS 250,000 Caulking and sealants 1 LS 1,500.00 1,500
251,500$

5. Interior Partitions, Doors and Finishes
Office painting 20,000
Office flooring 20,000
40,000$

6. Fixed Equipment, Casework and Specialties
Fixed equipment
Fire extinguisher and cabinets 2 EA 650.00 1,300
Chain link fence and gates
Fence, allow 8' high 430 LF 70.00 30,100
Gates 2 EA 800.00 1,600
33,000$

7. Mechanical
Plumbing
Plumbing Fixtures - Supply and Instal new including
plumbing works as needed - 20,000
Sanitary waste, vent and service piping, existing to remain - - Automatic fire sprinkler system and Mezzanine 1 LS 127,500.00 127,500 HVAC
Air handling equipment, existing to remain - -
( 6 )

1041 N. Grove Street #xx-xxxx
City of Anaheim 31-May-23
Component Description Quantity Unit Cost $
Ventilation equipment, existing to remain - -
Air distribution and return , existing to remain - -
Diffusers and grilles, existing to remain - -
Building controls, existing to remain - -
Exhaust fans and make up louvers 50,000
197,500$

8. Electrical
Main power and distribution - existing to remain - -
Power
Panel boards - existing to remain - -
Equipment connections and switches - existing to remain - - Lighting, switched, controls
New @ mezzanine area 12,500 SF 16.00 200,000
Remove and replace existing (fixture only) 25,000 SF 10.00 250,000 Office lighting 20,000
LED high bay lights warehouse 50,000
Security and intrusion detection system
Cameras, connect to existing security panels 5 EA 3,500.00 17,500 Low Voltage
Office IT cabling and networking 25,000
562,500$

9. Site Preparation and Demolition
Site protective construction, noise and dust control 25,000 SF 0.10 2,500 Hazardous material abatement - NIC - -
Selective building demolition 1 SF 10,000.00 10,000
( 7 )
#xx-xxxx
City of Anaheim 31-May-23
Component Description Quantity Unit Cost $
27,882$

10. Site Development
Fencing and gates @ parking lot
Wrought iron fencing with motorized gates for parking areas 120,000 Miscellaneous repairs, allowance 1 LS 10,000.00 10,000 130,000$
( 8 )