EXHIBIT A

Project: Design-Build Master Agreement for Water Projects

Work Order Packages awarded under this Master Agreement will include, but not be limited to the design, upgrade, construction, alteration, and repair of new and existing water and facilities throughout the City.

Specific work includes abandon, repair, relocate, replace, and install general pipeline infrastructure components; including pipelines, valves, pressure-reducing stations, water meters, and vaults.

Account # 502-521-3743-7865

MASTER AGREEMENT DESIGN-BUILD ENTITY: W. A. Rasic Construction Company, Inc. 4150 Long Beach Blvd.

Long Beach, CA 90807

PUBLICATION DATES: 5/18/2023 and 5/25/2023

BID OPENING DATE: 7/13/2023

PREVAILING WAGE RATE RESOLUTION NO: Per Current D.I.R. Publication

AWARD DATE: September 26, 2023

CONTRACT PRICE: Per Individual Work Order Packages

CONTRACT COMPLETION DAYS: Per Individual Work Order Packages

LIQUIDATED DAMAGES: Assigned and determined per Individual Work Order Package

EXHIBIT A

Project: Design-Build Master Agreement for Water Projects

Work Order Packages awarded under this Master Agreement will include, but not be limited to the design, upgrade, construction, alteration, and repair of new and existing water and facilities throughout the City.

Specific work includes abandon, repair, relocate, replace, and install general pipeline infrastructure components; including pipelines, valves, pressure-reducing stations, water meters, and vaults.

Account # 502-521-3743-7865

MASTER AGREEMENT DESIGN-BUILD ENTITY: T.E. Roberts Inc. 17771 Mitchell North.

Irvine, CA 92614

PUBLICATION DATES: 5/18/2023 and 5/25/2023

BID OPENING DATE: 7/13/2023

PREVAILING WAGE RATE RESOLUTION NO: Per Current D.I.R. Publication

AWARD DATE: September 26, 2023

CONTRACT PRICE: Per Individual Work Order Packages

CONTRACT COMPLETION DAYS: Per Individual Work Order Packages

LIQUIDATED DAMAGES: Assigned and determined per Individual Work Order Package

EXHIBIT A

Project: Design-Build Master Agreement for Water Projects

Work Order Packages awarded under this Master Agreement will include, but not be limited to the design, upgrade, construction, alteration, and repair of new and existing water and facilities throughout the City.

Specific work includes abandon, repair, relocate, replace, and install general pipeline infrastructure components; including pipelines, valves, pressure-reducing stations, water meters, and vaults.

Account # 502-521-3743-7865

MASTER AGREEMENT DESIGN-BUILD ENTITY: Ste phen Doreck Equipment Rentals, Inc. 9075 Telegraph Road
Pico Rivera, CA 90660

PUBLICATION DATES: 5/18/2023 and 5/25/2023

BID OPENING DATE: 7/13/2023

PREVAILING WAGE RATE RESOLUTION NO: Per Current D.I.R. Publication

AWARD DATE: September 26, 2023

CONTRACT PRICE: Per Individual Work Order Packages

CONTRACT COMPLETION DAYS: Per Individual Work Order Packages

LIQUIDATED DAMAGES: Assigned and determined per Individual Work Order Package