DEPARTMENT OF PUBLIC WORKSCITY OF ANAHEIMCITY OF ANAHEIM CALIFORNIAFOUNDED 1857 CITY OF ANAHEIMDEPARTMENT OF PUBLIC WORKSVICINITY MAPOrangethorpe Ave. Rehabilitation from 850’ west ofCommunity Dr. to Kraemer Blvd. Project
ITEM NO. DESCRIPTION QTY UNIT UNIT PRICE COST
1 Concrete Replacements (4 ramps) 1 LS $20,000.00 $20,000.00 2 Miscellaneous (Traffic control, Etc) 1 LS $10,000.00 $10,000.00 3 Signing and Striping 1 LS $5,000.00 $5,000.00
4 Utility Adjustment 1 LS $10,000.00 $10,000.00
5 Cold mill/A.C. planing (2" deep minimum) 5,250 SY $2.50 $13,125.00 6 Asphalt concrete 2" ARHM 600 TON $150.00 $90,000.00
$148,125.00
$14,812.50
$14,812.50
$177,750.00
$6,436.50
$643.65
$643.65
$7,723.80
$185,473.80
$200,000.00
Project Total (A+B)
Not to Exceed Amount
Design Costs (Anaheim's Portion)
Inspection Costs (Anaheim's Portion)
Construction Engineering Costs (Anaheim's Portion)
Subtotal Total (B)
Subtotal
Contingency (10%)
Construction Management (10%)
Construction Total (A)
CITY OF ANAHEIM -PUBLIC WORKS DEPARTMENT
DESIGN SERVICES DIVISION
COST & QUANTITY ESTIMATE
(Anaheim's Portion) Orangethorpe Rehab from 900' W/O Community Dr. to Kraemer Blvd.
Co-op with Placentia as lead