CITY COUNCIL AGENDA REPORT
City of Anaheim
DEPARTMENT OF PUBLIC WORKS
DATE: OCTOBER 24, 2023
FROM: DEPARTMENT OF PUBLIC WORKS
SUBJECT: AWARD OF CONTRACT FOR CONCRETE FACILITIES
REMOVAL AND REPLACEMENT – CITYWIDE PHASE 10
ATTACHMENT (Y/N): YES ITEM # 10
GOVERNMENT CODE § 84308 APPLIES: NO
RECOMMENDATION:
That the City Council, by Motion, award the construction contract to the lowest responsible bidder, Towo Enterprise, Inc., of Fullerton, California, Contractor's License No. 986567, Classification A, in the amount of $1,194,550, for the Concrete Facilities Removal and Replacement - Citywide Phase 10 Project; direct and authorize the Director of Public Works, on behalf of the City, to execute the Contract and any other related documents, and to take such actions as are necessary or advisable to implement and administer the Contract; direct and authorize the Finance Director to execute the Escrow Agreement pertaining to contract retentions; and determine that the Project is categorically exempt from the California Environmental Quality Act (CEQA) pursuant to Sections 15301, Class 1 and 15302, Class 2 of Title 14 of the California Code of Regulations.
DISCUSSION:
The bids are summarized as follows:
1. Towo Enterprise, Inc., Fullerton, CA $1,194,550
2. Onyx Paving Company, Inc., Anaheim, CA $1,424,000
3. Addison-Miller, Inc., Orange, CA $1,752,550
4. EBS General Engineering, Inc., Corona, CA $2,228,788 The Concrete Facilities Removal and Reconstruction - Citywide Phase 10 project is part of an annual concrete rehabilitation program that addresses the replacement of damaged concrete sidewalk, curb, gutter, and drive approaches throughout the city.
The work consists of rehabilitating and constructing new concrete curb and gutter to re- establish drainage patterns to their original design. The project improvements will also include the replacement of uneven and broken sidewalks and constructing Americans with Disabilities Act (ADA) curb access ramps, and all appurtenant work as shown on the plans and delineated in the specifications.
Award of Contract for Concrete Facilities Removal and Replacement - Citywide Phase 10 Project October 24, 2023
The bid for this project from Towo Enterprise, Inc. is found to be favorable when compared to the engineer’s estimate, reflects the current bidding atmosphere, appears to be reasonable and is within available funding.
The construction schedule is set to begin in Fall 2023 and conclude in Spring 2024. Liquidated damages for this project shall be $3,400 per day.
ENVIRONMENTAL DETERMINATION:
Upon review of the California Code of Regulations (CCR), staff recommends the City Council determine that the Project is categorically exempt from CEQA pursuant to Sections 15301, Class 1, and 15302, Class 2, of Title 14 of the CCR. Section 15301 allows for the repair, maintenance, or minor alteration of existing public improvements and Section 15302 allows for the replacement or reconstruction of existing improvements that will be in the same site and will have substantially the same purpose and capacity. The proposed improvements will repair and restore the existing concrete located within existing street right-of-way with no expansion of capacity. Staff will file CEQA Notice of Exemption (NOE) upon approval by City Council.
COMMUNITY WORKFORCE AGREEMENT (CWA):
This project is not covered “Project Work” as defined in the CWA the City entered into with the Los Angeles/Orange Counties Building and Construction Trades Council and the Signatory Craft Councils and Local Unions. The scope of the project does not meet the definition of “Project Work” as defined in the CWA; therefore, this project is exempt.
IMPACT ON BUDGET:
Funding for the project is available in the Public Works’ Fiscal Year 2023/24 General Fund budget.
Respectfully submitted,
Rudy Emami
Director of Public Works
Attachment:
1. Exhibit A