EXHIBIT A
Project: Arterial Sidewalk Removal and Replacement at Various Locations - Cycle 2-Phase 1
The work consists of the replacement of uneven and broken sidewalks and adjacent damaged curbs and gutters, and all appurtenant work as shown on the plans and delineated in the specifications.
Account Number(s): 272-412-3257-7710 & 101-412-3258-7710
LOWEST AND BEST RESPONSIBLE BIDDER: We R Builders, Inc. 3746 Foothill Blvd., #304
Glendale, CA 91214
PUBLICATION DATES: November 30, 2023 &
December 7, 2023
BID OPENING DATE: January 4, 2024
PREVAILING WAGE RATE: Per current D.I.R. Publication
AWARD DATE: January 23, 2024
CONTRACT COST ESTIMATE: $354,800
Three Hundred Fifty-Four
Thousand Eight Hundred Dollars
and No Cents
CONTRACT COMPLETION DAYS: Thirty-Five (35) Working Days
LIQUIDATED DAMAGES: Two Thousand Dollars
($2,000) Per Day