DisneylandForward
Final Subsequent EIR No. 352
R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-1 SECTION 4.0 MITIGATION MONITORING PROGRAM
MITIGATION MONITORING PROGRAM (MMP) NO. 000387 (INCLUDING PROJECT DESIGN

FEATURES) FOR THE DISNEYLAND RESORT PROJECT AS AMENDED BY

THE DISNEYLANDFORWARD PROJECT
CEQA Action Subsequent Environmental Impact Report No. 352 (Resolution No. ____) Project Description General Plan Amendment, Specific Plan No. 92-1 Amendment No. 9, and Specific Plan No. 92-2 Amendment No. 17 Applicant Walt Disney Parks and Resorts U.S., Inc., 500 South Buena Vista Street, Burbank, California, Project Location The Project site is located approximately 35 miles southeast of downtown Los Angeles and seven miles northwest of Santa Ana, in central Orange County, California, and is generally located adjacent to and southwest of the Interstate 5 (I-5), between Ball Road to the north, Walnut Street to the west, and Chapman Avenue to the south. The Project site encompasses The Disneyland Resort, including the Theme Park, Parking and Southeast Districts of the Disneyland Resort Specific Plan (DRSP), and properties in the Anaheim Resort Specific Plan (ARSP) Commercial Recreation (C-R) District (Development Area 1) owned or controlled by Walt Disney Parks and Resorts U.S., Inc. (Disney) or other subsidiaries of The Walt Disney Company.

Terms and Definitions

1. Applicant - Walt Disney Parks and Resorts U.S., Inc.

2. Property Owner/Developer – Any owner or developer of properties owned by Disney or other subsidiaries of The Walt Disney Company within the DRSP or the ARSP.

3. Project Design Features (PDFs) – Measures incorporated into The Disneyland Resort Project as amended by the DisneylandForward Project by the applicant with the intent of minimizing potential environmental impacts. The PDFs included in this Miti gation Monitoring Program will be implemented as mitigation measures.

4. Environmental Equivalent/Timing – To the extent permitted by law, if Disney cannot complete any PDF or Mitigation Measure and timing thereof, the City may specify another substituted measure, which (i) will have the same or superior result, (ii) will have the same or superior effect on the environment, and (iii) has a nexus to the Project. The Planning Department, in conjunct ion with any appropriate agencies or City departments, shall de termine the adequacy of any proposed “environmental equivalent/timing” based on substantial evidence and, if determined necessary, may refer said deter mination to the Planning Commission. Any costs associated with information required to make a determination of environmental equivalency/timing shall be borne by the Applicant.

5. Responsibility for Monitoring – Shall mean that compliance with the subject mitigation measure(s) shall be reviewed and determined adequate by all departments listed for each mitigation measure.

6. Ongoing Mitigation Measures – The mitigation measures that are designated to occur on an ongoing basis as part of this mitigation monitoring program will be monitored in the form of an annual letter from the Property Owner /Developer and/or Applicant in January of each year stating how compliance with the DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-2 subject measure(s) has been achieved. Mitigation Measures are referenced in parentheses by their section number as identified in the Draft Subsequent EIR No. 352. Mitigation Measures and/or PDFs designated to occur on an ongoing basis are noted with an asterisk (*). For mitigatio n measures/PDFs that are to be monitored “Ongoing During Construction”, the annual letter will review those mitigation measures/PDFs only while construction is occurring; monitoring will be discontinued after construction is complete. A final annual letter will be provided at the close of construction.

7. The City recognizes that the certain infrastructure improvement s and service capabilities, as identified in this Mitigation Mon itoring Program, will serve not only the Applicant but also other property owners/developers in the Spec ific Plan area, The Anaheim Resort, and the service are a, each of which should contribute in allocable share of the cost of these improvements. To implement this requirement as it applies to other property owners/developers in the Specific Plan area, The Anaheim Resort, and the service area, the City shall make appropriate arrangements with other public agencies, i f any, to reimburse the Applicant to the extent that its contributions for these improvements exceed the Applicant’s allocable share of the cost. Such arrangements shall include one or more of the following: (1) creation of integrated financing districts; (2) entry into a reimbursement agreement with the Applicant; (3) creation of appropriate community facilities districts, assessment districts and/or use of similar public financing districts and/or mechanisms; and (4 ) creation of such other mechanisms or districts as may be appropriate to provide for the reimbursement of thes e costs. The determination of the allocab le share of improvement costs attributable to the Applicant and other property owners/developers, and reim bursement amounts, shall be based on an appor tionment of the costs of such improvements and equipment and personnel among property owners/developers, including the Applicant, in the Specific Plan area, The Anaheim Resort, or otherwise defined service area, as applicable, depending on the area served.

8. To the extent that this Mitigation Monitoring Program requires the Applicant to submit plans for several phases simultaneously, it is understood that such later phase plans may be considered preliminary and may be subject to change. Such preliminary plans for the later phase will not be required to provide the level of detail required for the initial phase plans provided that more detailed plans will be submitted separately at a later time. Nevertheless, such preliminary plans for the later phase shall provide sufficient schematic or descriptive detail to ensure that plans submitted for said later phase shall comply with the provisions of this Mitigation Monitoring Program and shall be consistent with the provisions of the initial phase plans.

9. Timing – This is the point where a mitigation measure/PDF must be monitored for compliance. In the case where multiple action items are indicated, it is the first point where compliance associated with the mitigation measure/PDF must be monitored. Once the initial action item has been complied with, no additional monitoring pursuant to the Mitigation Monitoring Program will occur, as routine City practices and procedures will ensure that the intent of the measure design feature has been complied with. For example, if the timing is “to be shown on approved building plans” subsequent to issuance of the building permit consistent with the approved plans will be final building and zoning inspections pursuant to the building permit to ensure compliance.

10. Building Permit – For purposes of this Mitigation Monitoring Program, a buildi ng permit shall be defined as any permit issued for construction of a new building or structural expansion/modification of any existing bu ilding, but shall not include any permits required for interior tenant improvements or minor additions of up to 1,000 square feet to an existing structure or building.

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-3 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
Aesthetics
MM AES-1 Prior to issuance of each
building permit; to be
implemented prior to final
building and zoning
inspections
The property owner/developer shall submit pl ans which illustrate that all mechanical equipment and trash areas for the subject bu ildings will be screened from adjacent public streets and adjacent residential areas.

Planning & Building
Department, Planning
Services Division

MM AES-2 Prior to final building and
zoning inspections
Private streets within the Anaheim Resort Specific Plan area shall have street lights installed which are compatible with the design standards used for the public streets as determined by the Public Utilities Department.

Planning & Building
Department, Planning
Services Division;
Public Utilities
Departmen
t

MM AES-3 Prior to issuance of each
building permit for each
parking facility along
Walnut Street; to be
implemented prior to each
final building and zoning
inspection
The property owner/developer shall submit plans which detail the lighting system for the parking facilities along Walnut Street, Ball Road, Haster Street and along interior property lines abutting residential neighborhoods. The systems shall be designed and maintained in such a manner as to conceal light sources to the extent feasible to minimize light spillage and glare to the adjacent uses. The plans shall be prepared and signed by a licensed electrical engineer, with a letter from the engineer stating that, in the opinion of the en
gineer, this requirement has been met.

Planning & Building
Department, Planning
Services Division

MM AES-4 Prior to final building and
zoning inspection or
whenever established; and
on an ongoing basis
The property owner/developer shall part icipate in a landscape assessment and maintenance district for the Anaheim Resort.

Planning and Building
Department, Planning
Services Division
Utilities Department,
Resource Efficiency
Section

MM AES-5 Prior to approval of each
grading plan or issuance of
each demolition or building
permits, whichever occurs
first
A Construction Barrier Plan showing the location and types of barriers shall be in place during grading and construction. Said plan shall provide for all construction areas to be screened from view in compliance with the City of Anaheim Municipal Code and shall include provision for the type and hei ght of the barriers to be placed along all construction perimeters prior to the commencement of demolition, Site preparation or grading, whichever occurs first.

Public Works
Department, Traffic
and Transportation
Division; Planning &
Building Department,
Planning Services
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-4 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM AES-6 Prior to issuance of each
building permit
The proposed Specific Plan in corporates design guidelin es as well as zoning and development standards, many of which have been designed to reduce the potential visual impacts of the project and to present a visually integrated resort area, including:
• The Disneyland Resort Specific Plan provides for h eavily landscaped streetscapes and gives the guidelines for trees and shrubs, light fixtures, benches, monuments, and signs located within the landscaped area. • The East and West Park ing Areas and the hotel parking facilities will have landscaped setbacks from the public right-of-way and are restricted in height. • Rights-of-way will be landscaped to add to the aesthetics of the area. • The landscape treatments will vary to create distinct places visually. • The West Parking Area and hotel park ing facilities will be terraced back from Walnut Street with landscaping treatme nts above 40 feet. In addition, canopy trees will be planted in a center median on Walnut Street, and the parkway along the street will be landscaped.
• A coordinated color theme for major street features will be incorporated into the design.
• The service areas and back-of-house areas will be screened from public view. • All rooftop equipment on buildings will be screened as per the Specific Plan. • A layered landscape treatment in the se tback realm will provide screening of a 9-14 feet in hei
ght sound wall adjacent to the Southwest Parking Area.

Planning & Building
Department, Planning
Services Division

MM AES-7 Prior to issuance of building
permits
All plumbing or other similar pipes and fixtures located on the exterior of the building shall be shown on plans as fully screened from view of adjacent public rights-of-way and from adjacent properties by architectural devices an d/or appropriate building materials. A note indicating that these impr ovements will be installed prior to final building and zoning inspections shall be specifically shown on the plans submitted for building permits.

Planning & Building
Department, Planning
Services Division

MM AES-8 Prior to issuance of each
building permit
All air conditioning facilities and other roof and ground-mounted equipment shall be shown on plans as shielded from public view and the sound buffered to comply with City of Anaheim noise ordinances from any adjacent residential or transient-occupied properties. A note indicating that these improvements shall be installed prior to final building and zoning inspections shall be specifically shown on the plans submitted for building permits.

Planning & Building
Department, Building
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-5 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM AES-9 Prior to issuance of each
building permit for theme
park uses within the Theme
Park District, the Southeast
District, and the ARSP
Theme Park Overla
ys
Plans shall show compliance with the 360-Degree Architectural Treatment Criteria set forth in the Disneyland Resort Specific Plan and the Anaheim Resort Specific Plan.

Planning & Building
Department, Planning
Services Division

MM AES-10 Prior to issuance of each
building permit
Plans shall show that no shuttle/bus/vehicular drop-off areas shall be permitted in hotel or vacation ownership resort front setback area.

Planning & Building
Department, Planning
Services Division

MM AES-11 Ongoing The property owner/developer sha ll be responsible for the removal of any on-site graffiti within 24 hours of its application.

Planning & Building
Department, Code
Enforcement Division

MM AES-12 Prior to final building and
zoning inspections
Root and sidewalk barriers shall be provided for trees within seven feet of public sidewalks.

Planning & Building
Department, Planning
Services Division;
Public Works
Department,
Development Services
Division

MM AES-13 Prior to final building and
zoning inspections
The property owner/developer shall submit to the Planning and Building Department a letter from a licensed landscape architect certifying that all landscaping and irrigation systems have been installed in accordance with landscaping plans approved in connection with the buildin
g permit.

Planning & Building
Department, Planning
Services Division

MM AES-14 Ongoing All on-site non-Public Realm landscaping and irrigation systems, and Public Realm landscaping and irrigation systems, within an area in which dedication has not been accepted by the City, shall be maintained by the property owner/developer, in compliance with City standards.

Planning & Building
Department, Planning
Services Division;

MM AES-15 Ongoing Any tree planted within the Setback Realm shall be replaced in a timely manner in the event that it is removed, damaged, diseased and/or dead.

Planning & Building
Department, Planning
Services Division

MM AES-16 Ongoing A licensed arborist shall be hired by the property owner/developer to be responsible for all tree trimming.

Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-6 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM AES-17 Prior to issuance of each
building permits, unless
records indicate previous
payment
The property owner/developer shall pay a fee for street tree purposes to the City of Anaheim based on the length of street fronta ge in an amount as established by City Council resolution or credit against the fee given for City authorized improvements installed by the property owner/developer.

Public Works
Department,
Development Services
Division

MM AES-18 Prior to issuance of each
building permit
The property owner/developer shall submit a shade and shadow analysis to the Planning and Building Department for review and approval demonstrating that the proposed structure(s) would avoid creating significant shade and shadow impacts on adjacent land uses to the maximum extent feasible. A significan t shade and shadow impact would occur when outdoor active areas (e.g., outdoor eating areas, hotel/motel
swimming pools, and residential front and back yards) or structures that include sensitive uses (e.g., residences) have wind ows that normally receive sunlight are covered b
y shadows for more than 50 percent of the sunlight hours.

Planning & Building
Department, Planning
Services Division

MM AES-19 Prior to issuance of each
building permit
The location and configuration of all lighting fixtures including ground-mounted lighting fixtures utilized to accent buildings, landscape el ements, or to illuminate pedestrian areas shall be shown on all plans submitted for building permits. All proposed surface parking area lighting fixtures shall be down-lighted with a maximum height of 12 feet adjacent to any residentia l properties. All lighting fixtures shall be shielded to direct lighting toward the ar ea to be illuminated and away from adjacent residential propert
y lines.

Planning & Building
Department, Planning
Services Division

Air Quality
MM AQ-1 Prior to final building and
zoning inspection
The property owner/developer shall comply with all SCAQMD offset regulations and implementation of Best Available Control Technology (BACT) and Best Available Retrofit Control Technology (BARCT) for any new or modified stationary sources.

Copies of permits shall be
given to the Planning Department.

Planning & Building
Department, Planning
Services Division

MM AQ-2 Ongoing during operation of
The Disneyland Resort
The property owner/developer shall impl ement the following measures to reduce emissions:
a. To the extent practicable, schedule goods movements for off-peak traffic hours. b. Use clean fuel for attraction rides and other uses, as practicable.

Planning & Building
Department, Planning
Services Division;
Public Works
Department, Traffic
and Transportation
Division; Utilities
Department, Resource
Efficienc
y Section

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-7 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM AQ-3 Prior to issuance of the first
building permit associated
with a cumulative total of
over 10,000 square feet of
theme park development in
the Southeast District or
Theme Park East Overlay,
whichever occurs first

Prior to final building and
zoning inspections
associated with a
cumulative total of over
10,000 square feet of theme
park development in the
Southeast District or Theme
Park East Overlay

Ongoing during project
operation
The property owner/developer shall submit a site and operations plan for this facility showing the location and configuration of the on-site cast financial and dining services in conformance with The Disneyland Resort Specific Plan.

The property owner/developer shall provide cast financial and dining services within the Southeast District or Theme Park East Overlay and the Theme Park District to accommodate cast members.

The property owner/developer shall continue to provide cast financial and dining services in conformance with The Disneyland Resort Specific Plan.

Planning & Building
Department, Planning
Services Division

MM AQ-4 Ongoing during project
operation
The following will be achieved: (1) the 1.5 AVR target for all cast and (2) the average length of the out-of-area guest stay of 1.72 days, or a demonstration that the SCAG VMT reduction targets have been met through other means.

Public Works
Department, Traffic
and Transportation
Division; South Coast
Air Quality
Management District
(SCAQMD)

MM AQ-5 Ongoing during
construction
The following measures will be followed by the property owner/developer to reduce air quality impacts:
a. Normal wetting procedures (at least twice daily) or other dust palliative measures shall be followed during earth-moving operations to minimize fugitive dust emissions, in compliance with the City of Anaheim Municipal Code including application of chemical soil stabilizers to exposed soils after grading is completed and replacing ground cover in disturbed areas as quickly as practicable.

Planning & Building
Department, Building
Division; Public Works
Department,
Development Services
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-8 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
b. For projects where there is excavation for subterranean facilities (such as parking) on-site haul roads shall be watered at least every two hours or the on- site haul roads shall be paved.
c. Enclosing, covering, watering twice daily, or applying approved soil binders, according to manufacturer’s specification, to exposed piles. d. Roadways adjacent to the project sh all be swept and cleared of any spilled export material at least twice a day to assist in minimizing fugitive dust; and haul routes shall be cleared as needed if spills of material exported from the project site occur.
e. Where practicable, heavy duty construction equipment shall be kept onsite when not in operation to minimize exhaust emissions associated with vehicles repetitiously entering and exiting the project site.
f. Trucks importing or exporting soil material and/or debris shall either be covered prior to entering public streets or shall comply with the vehicle freeboard requirements of Section 23114 of the California Vehicle Code for both public and private roads. This California Vehicle Code section stipulates that the load, where it contacts the sides, front and back of the cargo container area, remain six inches from the upper edge of the container area, and that the load does not extend, at its peak, above any part of the upper edge of the cargo container area. g. Taking preventive measures to ensure that trucks do not carry dirt on tires onto public streets, including treating onsite roads and staging areas. h. Preventing trucks from idling for longer than 2 minutes. i. Manually irrigate or activate irrigation systems necessary to water and maintain the vegetation as soon as planting is completed.
j. Reduce traffic speeds on all unpaved ro ad surfaces to 15 miles per hour or less. k. Suspend all grading operations when wind speeds (as instantaneous gust) exceed 25 miles per hour and during second stage smog alerts. l. Comply with the SCAQMD Rule 402, which states that no dust impacts offsite are sufficient to be called a nuisance, and SCAQMD Rule 403, which restricts visible emissions from construction.
m. Use low emission mobile construction equipment (e.g., tractors, scrapers, dozers, etc.) where practicable.
n. Utilize existing power sources (e.g., power poles) or clean-fuel generators rather than temporary power generators, where practicable.

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-9 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
o. Maintain construction equipment engines by keeping them properly tuned. p. Use low sulfur fuel for equipm ent, to the extent practicable. q. Should demolition, grading, or, excavation activities of two or more projects within any portion of the Project site occur concurrently, air quality monitoring shall be conducted each day that demolition and grading/excavation activities occur concurrently; mon itoring shall be conduct ed in accordance with SCAQMD Rule 403 and ensure that PM2.5 and PM10 concentrations shall not exceed the established re
gulatory limit of 50 micrograms per cubic meter.

MM AQ-6 Prior to issuance of each
grading permit (for
Import/Export Plan) and
prior to issuance of
demolition permit (for
Demolition Plan)
The property owner/developer shall submit Demolition and Import/Export Plans. The plans shall include identification of offsite locations for material export from the project and options for disposal of ex cess material. These options may include recycling of materials onsite, sale to a soil broker or contractor, sale to a project in the vicinity or transport to an environmentally cleared landfill, with attempts made to move it within Orange County. The property owner/developer shall offer recyclable building materials, such as asphalt or concrete for sale or removal by private firms or public agencies for use in construction of other projects, if not all can be reused on the project site.

Public Works
Department, Traffic
and Transportation
Division

MM AQ-7 Ongoing during
construction
The property owner/developer shall implement the following to limit emissions from architectural coatings and asphalt usage:
a. Use nonsolvent-based coatings on buildings, wherever appropriate. b. Use solvent-based coatings, where they are necessary, in ways that minimize solvent emissions.
c. Encoura ge use of high-solid or water-based coatings.

Planning & Building
Department, Building
Division

MM AQ-8 Prior to issuance of building
permits for each of the east
and west public parking
structures and any parking
structure in the Southeast
District; ongoing during
project operation
All public day-use parking facilities, not including hotel, hotel accessory uses or cast parking facilities, will have a crew of cast members, based on parking predictions, on each lot or facility level, to assist speed pa rking procedures. In addition, the East and West public parking structures and any parking structure in the Southeast District will incorporate the following design features on each facility level, to assist speed parking procedures:

1. Signage designed to enhance smooth traffic flows and reduce traffic flows on each facility level.

2. Speed ramps which will take cars directly to the level that has available spaces, thus eliminating circulation movement and time involved with hunting for a space. The speed parkin
g stripin g and procedures currentl y used at the
Public Works
Department, Traffic
and Transportation
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-10 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
Disneyland theme park parking lot will be adapted to use within the parking structures and will be designed to safely park 60 cars per minute. (Refer to The Disneyland Resort Specific Plan and the Anaheim Resort Specific Plan.)

3. Ceiling clearances and lateral clearances , an open well design, and enhanced lighting levels will eliminate the enclosed feeling of a standard garage, which tends to slow drivers.

MM AQ-9 Ongoing during project
operation
The property owner/developer will implement a comprehensive and aggressive Transportation Demand Management (TDM) program for all project employees.

Public Works
Department, Traffic
and Transportation
Division

MM AQ-10 Prior to the issuance of each
building permit
The property owner/developer shall implement, and demonstrate to the City, that project design will incorporate the following energy-saving features. This energy savings will also contribute to reduced operation-related air quality impacts. These measures may include, but are not limited to the following:
a. Improve thermal integrity of structures and reduced thermal load through use of automated time clocks or occupant sensors.
b. Incorporate efficient h eating and other appliances. c. Incorporate energy conservation measur es in site orientation and in building design, such as appropriate passive solar design and proper sealing of buildings. d. Use water-wise landscaping wherever feasible to reduce energy used in pumping and transporting water.
e. To the extent feasible, provide daycare opportunities for employees or participate in a joint development daycare center.
f. Install facilities for electric vehicle recharging, unless it is demonstrated that the technology for these facilities or availability of the equipment current at the time makes this installation infeasible.

Planning & Building
Department, Building
Division and Planning
Services Division;

MM AQ-11 Prior to issuance of each
building permit for public
day-use parking facilities
The public parking facilities, which may be used for theme park guest parking, shall be designed in accordance with the speed parking procedures set forth The Disneyland Resort Specific Plan and the Anaheim Reso rt Specific Plan which will assist in reducin
g vehicular fuel from idling engines.

Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-11 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM AQ-12 Prior to issuance of the first
building permit
The property owner/developer shall submit a human health risk assessment (HRA) for any proposed sensitive land uses (according to SCAQMD standards at that time) to be located within 500 feet of th e near edge of the I-5 freeway unless it is demonstrated that the health risks have been determined to be acceptable according to the standards of the SCAQMD at the time of building permit application.

Planning & Building
Department, Planning
Services Division

MM AQ-13 During construction
activities
For all offroad engines that are diesel and above 50 brake horsepower, the contractor shall use engines that comply with USEPA Tier 4 offroad engine standards.

Planning & Building
Department, Building
Division; Public Works
Department,
Development Services
Division

MM AQ-14 Prior to issuance of a
grading permit
If two or more dust-generating construction projects, which collectively will disturb 15 acres or more and which have demolition, excavation, or grading activity scheduled to occur concurrently, a Localized Significance Threshold analysis shall be prepared. If the LST analysis determines that the established Localized Significance Thresholds for NOx, PM2.5, or PM10 would be exceeded, then modifications to construction equipment profiles, modifications to cons truction schedules, or additional pollution reduc
tion measures shall be implemented.

Planning & Building
Department, Building
Division; Public Works
Department,
Development Services
Division

PDF AQ-1 Ongoing during project
operation
The project has been designed to reduce dependence on the private automobile, which will reduce and avoid many of the traffic-related emissions associated with the existing Disneyland theme park and Disney California Adventure Park, as well as those normally associated with hotels and day-use only special event activities and those associated with development of theme park uses in the Southeast District or Theme Park East Overlay. Guests will be encouraged to park their cars and leave them for the duration of their visits, thus eliminating th e trips to restaurants and sightseeing, or entertainment attractions normally associated with vacation stays. Marketing efforts in Southern California will promote the Disneyland Resort as a mini-vacation site for Southland residents.

Planning & Building
Department, Planning
Services Division

PDF AQ-2 Ongoing during project
operations
A wide range of entertainment, lodging, retail and restaurant attractions will be located within the project area and will be linked by an electrically powered monorail system, pedestrian ways/guest transportation system to transport visitors from parking facilities to The Disneyland Resort, and/or pedestrian bridges, walkways and promenades.

Convenient walkway access within the Theme Park District, the Southeast District and the Theme Park East Overlay and adjacent uses, such as the City of Anaheim Convention Center, will also facilitate pedestrian trips b y non-project guests who will
Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-12 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
remain within the project area rather than use automobiles to travel to restaurants and entertainment outside of the area.

PDF AQ-3 Ongoing during project
operations
In accordance with transportation and circulation mitigation measures, The Disneyland Resort traffic will be accommodated, and existing traffic conditions and circulation patterns will be improved through implementation of the identified transportation and parking features, including parking facilities, monorail and pedestrian way/guest transportation systems and convenient access to parking facilities from the freeway.

Planning & Building
Department, Planning
Services Division;
Public Works
Department, Traffic
and Transportation
Division

PDF AQ-4 Prior to issuance of building
permits for the East Parking
Facility and ongoing during
project operations
The Disneyland Resort Project will include a special drop-off area on Harbor Boulevard north of Disney Way, or internal or adjacent to the East Parking Area Parking Structure and/or adjacent ARSP Parking Overlay, or other accessible location, for shuttle buses to help encourage use of buses by area visitors.

Planning & Building
Department, Planning
Services Division;
Public Works
Department, Traffic
and Transportation
Division

SR AQ-1 Prior to issuance of the first
grading or building permit,
whichever occurs first
The property owner/developer shall provide written evidence of compliance to the Planning & Building Director or their designee that all construction activities shall comply with SCAQMD Rules 402 and 403, which shall assist in reducing short term air pollutant emissions. SCAQMD Rule 402 requires that air pollutant emissions not be a nuisance off site. SCAQMD Rule 403 (Tables 1, 2, and 3 of Rule 403) requires that fugitive dust be controlled with the best available control measures so that the presence of such dust does not remain visi ble in the atmosphere beyond the property line of the emission source. This requireme nt shall be included as notes on the contractor specifications.

Planning & Building
Department, Building
Division; Public Works
Department,
Development Services
Division

SR AQ-2 Prior to issuance of building
permits
The property owner/developer shall submit evidence that low emission paints and coatings are utilized in the design and construction of all buildings in compliance with SCAQMD regulations, including SCAQMD Rule 1113. This information shall be denoted on the project plans and specifications. The property owner/developer shall also submit an architectural coating schedule and calculations demonstrating that VOC emissions from architectural coating opera tions would not exceed 75 pounds per day averaged over biweekly periods. The calcu lations shall show, for each coating, the surface area to be coated, gallons (or liters) of coating per unit surface area, and VOC Planning & Building
Department, Building
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-13 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
content per gallon (or liter). The property owner/developer shall also implement the following to limit emissions from architectural coatings and asphalt usage:
a. Use nonsolvent-based coatings on buildings, wherever appropriate; b. Use solvent based coatin gs, where they are necessary.

Biological Resources
MM BIO-1 Prior to the issuance of a
demolition permit, grading
permit, or building permit,
whichever occurs first
A letter detailing the proposed schedule for vegetation removal and building demolition activities shall be submitted to the Planning and Building Department, verifying that removal shall take place between August 1 and January 31 to avoid the bird nesting season. If this is not feasible, the property owner/developer shall implement MM BIO-2.

Planning & Building
Department, Planning
Services Division

MM BIO-2 Prior to the issuance of a
demolition permit, grading
permit or building permit,
whichever occurs first, and
if Project demolition and/or
vegetation clearing must
occur during the bird
nesting season (February 1–
July 31)
A pre-construction nesting bird survey of structures to be demolished and/or vegetation to be removed shall be conducted by a qualified Biologist no more than three days prior to such work occurring. If the Biologist does not find any active nests within or immediately adjacent to the impact area, the vegetation clearing/construction work shall be allowed to proceed. The pre-construction nesting bird survey shall be updated following any work stoppage of two weeks or longer.

If an active nest of a bird species protected under California Fish and Game Code or the Migratory Bird Treaty Act is identifie d within or immediately adjacent to the construction area, and the Biologist determines that the nest may be impacted or breeding activities substantially disrupted, the Biologist shall delineate an appropriate no-impact buffer zone (at a minimum of 25 feet) around the nest depending on the sensitivity of the species and the nature of the construction activity. All nests and associated buffers shall be mapped on the co nstruction plans. The active nest shall be protected until nesting activity has ended. The following restrictions to clearing and/or construction activities shall be required until nest(s) are no longer active, as determined by a qualified Biologist: (1) clearing limits shall be established within a buffer around any occupied nest (the buffer shall be 25–100 feet for nesting birds and 300- to 500- feet for nesting raptors), unless otherwise determined by a qualified Biologist; and (2) access shall be restricted within the buffe r of any active nest, unless otherwise determined by a qualified Biologist. Encroachment into the buffer area around a known nest shall only be allowed if the Biologist determines that the proposed activity would not disturb the nest occupants. Once the qualified Biologist has determined that fledglings have left the nest, there is no evidence of a second nesting attempt, or the nest has failed, construction can proceed within the buffer zone.

Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-14 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
Cultural Resources
MM CUL-1 Prior to issuance of each
grading permit
The property owner/developer shall submit a letter identifying the certified archaeologist that has been hired to ensure that the following actions are implemented:
a. The archaeologist must be present at the pre-grading conference in order to establish procedures for archaeological monitoring, as well as for temporarily halting or redirecting work to permit the sampling, identification, and evaluation of artifacts if potentially significant artifacts are uncovered. Specific monitoring procedures will be established based on review of site specific conditions, including presence of native soils, anticipated construction activities, and nature of ground disturbance including depth of excavation. If artifacts are uncovered and determined to be significant, the archaeological observer shall determine appropriate actions in cooperation with the property owner/developer for exploration and/or salvage.
b. Specimens that are collected prior to or during the grading process shall be donated to an appropriate educational or research institution. c. Any archaeological work at the site sh all be conducted under the direction of the certified archaeologist. If any artifacts are di scovered during grading operations when the archaeological monitor is not present, grading shall be diverted around the area until the monitor can survey the area. d. A final report detailing the findings and disposition of the specimens shall be submitted to the Plannin
g and Building Department within ninety days.

Public Works
Department;
Development Services
Division

MM CUL-2 For properties within the
ARSP, prior to approval of
building, grading or
demolition permits,
whichever occurs first
For properties that contain a structure over 45 years old, property owners/developers shall submit to the Planning and Building Department, Planning Services Division, documentation to verify the presence/absence of historic resources. On properties where resources are identified, such documentation in accordance with HABS standards shall provide a detailed mitigation plan, including a monitoring program and recovery and/or in situ preservation plan, based on the recommendations of a qualified specialist.

Planning &Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-15 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM CUL-3 Prior to the issuance of
grading, demolition or
building permits, whichever
occurs first
The property owner/developer shall be responsible for implementing the following and submitting the required documentation to the Planning and Building Department, Planning Services Division: If an individual development project within the potential Disneyland Theme Park Historic District proposes to substantially alter or demolish a contributing feature to the potential Disneyland Theme Park Historic District as identified in the Historic Resources Techni cal Report attached as Appendix E-2 to Subsequent EIR No. 352, that contributing feature shall be documented in the outline format as specified in the HABS History Guidelines, and photographed according to the HABS Photography Guidelines, . The documentation shall be prepared by a historian or architectural historian who meets the Secretary of the Interior’s Historic Preservation Professional Standards in the relevant discipline. Digital copies of the documentation shall be submitted to the Anaheim Planning and Building Department, Planning Services Division for storage with Heritage Services, and housed in the Walt Disne
y Company archives.

Planning & Building
Department, Planning
Services Division

MM CUL-4 Prior to the issuance of
grading, demolition or
building permits, whichever
occurs first
The property owner/developer shall be responsible for implementing the following and submitting the required documentation to the Planning and Building Department, Planning Services Division: If any of the individually designated or potentially eligible features or buildings within the theme park , as identified in the Historic Resources Technical Report attached as Appendix E-2 to Subsequent EIR No. 352, are proposed for substantial alteration or demolition, that feature or building shall be documented individually in the outline format as specified in the HABS History Guidelines, and photographed according to the HABS Photog raphy Guidelines. The documentation shall be prepared by a historian or architect ural historian who meets the Secretary of the Interior’s Historic Preservation Professi onal Standards in the relevant discipline.

Digital copies of the documentation shall be submitted to the Anaheim Planning and Building Department, Planning Services Division for storage with the Heritage Services Division, and housed in the Walt Disne
y Company archives.

Planning &Building
Department, Planning
Services Division

SR CUL-1 Before and during
construction
If human remains are discovered on-site, no further disturbance shall occur until the County Coroner has made a determination of origin, and disposition pursuant to California Public Resources Code Section 5097.98 and California Health and Safety Code Section 7050.5 has occurred.

Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-16 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
Energy
MM ENE-1 Prior to issuance of each
building permit
The property owner/developer shall submit plans and calculations to demonstrate that the energy efficiency of each building will exceed the Title 24, Part 6, Building Energy Efficiency Standards current at the time of application by at least 10 percent.

Planning & Building
Department, Building
Division; Utilities
Department, Resource
Efficiency Section

MM ENE-2 Prior to submittal of plans
for electrical system
improvements
Any new system improvements (e.g., substa tion, line connections), if required, shall be constructed in accordance with the City’s Electric Rates, Rules and Regulations and Electrical Specifications. Electrical Service Fees and other applicable fees will be assessed in accordance with the then current Electric Rates, Rules and Regulations and Electrical Specifications.

Planning & Building
Department, Building
Division; Utilities
Department, Electric
Services Division

MM ENE-3 Prior to approval of each
final building and zoning
inspection
The Southern California Gas Company has developed several programs which are intended to assist in the selection of most energy-efficient water heaters and furnaces.

The property owner/developer shall implement a program, as required, to reduce the demand on natural
gas supplies.

Utilities Department,
Resource Efficiency
Section

MM ENE-4 Prior to issuance of each
building permit
The property owner/developer shall demonstrate on plans that fuel-efficient models of gas-powered building equipment have been incorporated into the proposed project to the extent feasible.

Planning & Building
Department, Building
Division; Utilities
Department, Resource
Efficienc
y Section

MM ENE-5 Prior to issuance of a
building permit
The property owner/developer shall incorporate feasible renewable energy generation measures into the project. These measures may include but not be limited to use of renewable biofuels, solar and small wind turbine sources on new and existing facilities and the use of solar powered lighting in parking areas.

Planning & Building
Department, Building
Division; Utilities
Department, Resource
Efficiency Section

PDF ENE-1 Ongoing during project
development and operation
The project shall be developed in conformance with The Disneyland Resort Specific Plan and shall offer a broad diversity of theme park, retail, dining and entertainment experiences which will enhance the destina tion resort character of The Disneyland Resort. As a result, many visitors will extend their length of stay; thus, incremental vehicular trips to and from the site are expected to be reduced.

Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-17 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
SR ENE-1 Prior to the issuance of each
building permit
The property owner/developer shall be required to prepare and submit to the City for review and approval (1) a Landscape Docu mentation Package and (2) landscape and irrigation plans with appropriate water use calculations in accordance with the requirements of Anaheim Municipal Co de Chapter 10.19, Landscape Water Efficiency.

Planning & Building
Department, Planning
Services Division

SR ENE-2 Prior to the issuance of
building permits
The property owner/developer shall be required to demonstrate to the Planning Department, Building Division that building plans meet the applicable California Green Buildin
g Standards.

Planning & Building
Department, Building
Division

Geology
MM GEO-1 Prior to approval of each
grading plan
The property owner/developer shall submit to the Public Works Department, Development Services Division, for review and approval a thorough soils and geological report for the area to be graded, based on proposed grading and prepared by an engineering geologist and geotechnical engineer. The report shall comply with Title 17 of the Anaheim Municipal Code.

Public Works
Department,
Development Services
Division

MM GEO-2 Prior to issuance of each
building permit
The property owner/developer shall submit to the Planning and Building Department, Building Division for review and approval, detailed foundation design information for the subject building(s), prepared by a civil engineer, based on recommendations by a geotechnical engineer.

Planning & Building
Department, Building
Division

MM GEO-3 Prior to issuance of each
foundation permit
The property owner/developer shall submit a report prepared by a geotechnical engineer to the Planning and Building Department, Building Division for review and approval, which shall investigate the subject foundation excavations to determine if soft layers are present immediately beneat h the footing site and to ensure that compressibilit
y does not underlie the footing.

Planning & Building
Department, Building
Division

MM GEO-4 Prior to issuance of each
building permit
The property owner/developer shall submit plans to the Planning and Building Department, Building Division for review and approval showing that the proposed structure has been analyzed for earthquake loading and designed according to the most recent seismic standards in the California Building Code adopted by the City of Anaheim.

Planning & Building
Department, Building
Division

MM GEO-5 Prior to issuance of building
or grading permits
The property owner/developer shall submit to the Planning and Building Department, Building Division geologic and geotechnical investigations in areas of potential seismic or geologic hazards and provide a note on plans that all grading operations shall be conducted in conformance with the recommendations contained in the applicable
geotechnical investigation.

Planning & Building
Department, Building
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-18 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM GEO-6 Ongoing during grading
activities
The property owner/developer shall implemen t standard practices for all applicable codes and ordinances to prevent erosion to the satisfaction of the Planning and Building Department, Building Division.

Planning & Building
Department, Building
Division

MM GEO-7 Prior to issuance of each
grading permit
The property owner/developer shall submit a letter identifying the certified paleontologist meeting the Society of Vertebrate Paleontology (SVP) standards that has been hired to ensure that the following actions are implemented:
a. The paleontologist must be present at the pre-grading conference in order to establish procedures for paleontological monitoring, as well as for temporarily halting or redirecting work to permit the sampling, identification, and evaluation of fossils if potentially significant paleontological resources are uncovered. If fossils are uncovered and found to be significant, the paleontological monitor shall administer appropriate actions based on SVP protocols

7. b. Specimens that are collected prior to or during the grading process shall be reposited in an appropriate educational or research institution. Preparation, storage and curation shall be funded by the property owner/developer. c. Any paleontological work at the site shall be conducted under the direction of the certified paleontologist. If any fossils are discovered during grading operations when the paleontological monitor is not present, grading shall be diverted around the discovery by a buffer of at least 50 feet. Construction shall not resume until the paleontological monitor has given the order to proceed in that location once a determination on the significance of the fossil discovery has been made.
d. A final report detailing the findings and disposition of the specimens shall be submitted. Upon completion of the grading, the paleontologist shall notify the Cit
y as to when the final report will be submitted.

Public Works
Department,
Development Services
Division

SR GEO-1 Ongoing during grading
activities
All grading operations will be conducted in conformance with the Anaheim Municipal Code, Title 17, Land Development and Resour ces, and the most recent version of the California Building Code.

Public Works
Department,
Development Services
Division

7 Society of Vertebrate Paleontol ogy (SVP), Guidelines from the Ethics Education Committee for Colle cting, Document ing and Curat ing Fossils (last updated 2021). https://vertpaleo.org/wp-content/uploads/2021/01/Guidelines-from-the-Ethics-Education-Committee.pdf (accessed August 18, 2023).

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-19 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
Greenhouse Gas Emissions
As discussed in Draft Subsequent EIR No. 352, Section 5.7, Green house Gas Emissions, incorporates SRs, MMs, and PDFs from Secti on 5.1, Air Quality; Section 5.5, Energy; Section 5.9, Hydrology and Water Quality; Section 5.14, Transportation; and Section 5.16, Utilities and Service Systems.

Hazards and Hazardous Materials
MM HAZ-1 Prior to any relocation of
transformers that may
contain PCBs which are
being moved or relocated as
part of project development
The transformers shall be tested by the property owner/developer for PCBs. Utilities Department, Electric Services

MM HAZ-2 Ongoing during demolition
and construction
In the event that hazardous waste, including asbestos, is discovered during site preparation or construction, the property owner/developer shall ensure that the identified hazardous waste and/or hazardous material are handled and disposed of in the manner specified by the State of California Hazardous Substances Control Law (Health and Safety Code, Division 20, Chapter 6.5), according to the requirements of the California Administrative Code, Title 30, Chapter 22.

Fire Department,
Environmental
Protection Section

MM HAZ-3 Prior to approval of a
grading plan or issuance of
a demolition permit,
whichever occurs first
The property owner/developer shall submit a Phase I Environmental Site Assessment (ESA) prepared pursuant to current ASTM Standard Practice for Environmental Site Assessments to identify potential threats to human health and the environment for review by the City. If possible hazardou s materials are identified during the site assessments, the appropriate response/rem edial measures will be implemented in accordance with the requirements of the Orange County Health Care Agency (OCHCA) and/or the Regional Water Qu ality Control Board (RWQCB), as appropriate. The ESA shall detail procedures that shall be taken if a previously unknown underground storage tank (UST) or other unknown hazardous materials or waste is discovered onsite. The ESA shall outline where hazardous materials may be found, types of hazardous materials anticipated, how to screen for them, and what to do in the event they are identified. The ESA shall identify the party responsible for the screening, and training requirements for those responsible for undertaking the screening effort. The ESA shall specify requirements for reporting, handling, staging, disposal, and recordkeeping. The ESA shall also identify contingencies in the event that significant contamination is identified that is 1) above regulatory thresholds and 2) cannot be removed/ remediated b
y proposed construction.

Fire Department,
Environmental
Protection Section;
Orange County Health
Care Agency

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-20 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM HAZ-4 Prior to issuance of a
grading or demolition
permit, whichever occurs
first
In areas known or thought to have been previously occupied by underground storage tanks (USTs), or other hazardous materials or waste, and in areas where tank removal has not been verified prior to excavation or grading; the property owner/developer shall retain the services of a qualified environmental professional to conduct an investigation for known, or the presence of, cryptic tanks using geophysical methods that include the potential use of grou nd penetrating radar (GPR) or similar technolo
gies to determine no abandoned USTs are present.

Fire Department,
Environmental
Protection Section;
Orange County Health
Care Agency

MM HAZ-5 Prior to the removal of
underground storage tanks
(USTs)
The property owner/developer shall obtain a permit from the Hazardous Materials Management section of the Fire Department for removal of such tanks. During removal of the underground storage tank , a representative from the Hazardous Materials Section (HMS) of the Fire Department shall be onsite to direct soil sampling.

Fire Department,
Environmental
Protection Section;
Orange County Health
Care A
gency

MM HAZ-6 Ongoing during remediation A ll remediation activities of surface or subs urface contamination not related to underground storage tanks (USTs), conducted on behalf of the property owner/developer, shall be overseen by the Santa Ana Regional Water Quality Control Board (SARWQCB) and witnessed by Anaheim Fire Department/Hazardous Material Management Section (HMS). Information on subsurface contamination from an underground storage tank shall be provided to the Santa Ana Regional Water Quality Control Board (SARWQCB) with a cop
y to Planning & Building.

Fire Department,
Environmental
Protection Section;
Orange County Health
Care Agency

MM HAZ-7 Prior to issuance of each
demolition permit
A hazardous building material survey shall be conducted to verify the absence of hazardous building materials and, if needed, future abatement by a California-licensed contractor, and/or removal and disposal in accordance with federal, state, and local transportation and disposal regulations.

Fire Department,
Environmental
Protection Section;
Orange County Health
Care Agency

SR HAZ-1 Ongoing during Project
construction
All construction activities, including demolition and renovation of the existing facilities and installation of the new facilities, shall be performed in compliance with all CalOSHA standards (California Code of Regulations, Title 8) to protect worker health and safety.

Fire Department,
Environmental
Protection Section;
Orange County Health
Care A
gency

SR HAZ-2 Ongoing during Project
implementation
The removal and disposal of any lead-based paint (LBP) encountered on site during Project implementation shall be performed by an LBP Abatement Contractor that is licensed and registered in California pursuant to California Code of Regulations Title 17.

Fire Department,
Environmental
Protection Section;
Orange County Health
Care A
gency

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-21 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
SR HAZ-3 Ongoing during Project
construction and operations
Activities at the Project Site shall comply with existing federal, State, and local regulations regarding hazardous material use, storage, disposal, and transport. All on- site generated waste that meets hazardous waste criteria shall be stored, manifested, transported, and disposed of in accordance with the California Code of Regulations (Title 22) and in a manner to the satisfac tion of the local Certified Unified Program Agency (CUPA), as applicable.

All transport and transfer of hazardous materials shall be performed by a licensed hazardous waste hauler in compliance w ith all applicable State and federal requirements, including U.S. Department of Transportation regulations under Title 49 (Hazardous Materials Transportation Act) and Title 40, Section 263 (Subtitle C of the Resource Conservation and Recovery Act) of the Code of Federal Regulations; California Department of Transportation (Caltrans) standards; and Division of Occupational Safety and Healthy (Cal/OSHA) standards.

Fire Department,
Environmental
Protection Section;
Orange County Health
Care Agency

SR HAZ-4 Ongoing during Project
construction
All construction activities, including demolition and renovation of the existing facilities and installation of the new facilities, shall be performed in compliance with South Coast Air Quality Management District (SCAQMD) Rule 1403 requiring a survey for and proper abatement of asbestos-containing materials prior to construction.

Air Quality
Management District

Hydrology and Water Quality
MM HWQ-1 Ongoing during Project
operations
The property owner/developer shall comply with the Master Drainage and Runoff Management Plan (MDRMP) and shall submit updates as required for new grading for review and approval by the City Engineer.

Public Works
Department,
Development Services
Division

MM HWQ-2 Prior to issuance of each
building permit
The property owner/developer shall submit landscaping and irrigation plans and an Irrigation Management Program. This landscape plan shall include a maintenance program to control the use of fertilizers and pesticides, and an irrigation system designed to minimize surface runoff and overwatering. Additionally:
a. The landscape plans shall be prepar ed and certified by a licensed landscape architect. The landscape architect sh all submit plans in accordance with Anaheim’s Landscape Water Efficiency Ordinance and Guidelines including:

1. Project Information

2. Maximum Applied Water Use expresses as annual totals.

3. Soil management report or specifications.

Public Utilities, Water
Services;
Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-22 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion

4. Landscape design plan.

5. Irrigation design plan.

6. Grading design plan.
b. The Irrigation Management Program shall specify methods for monitoring the irrigation system and shall be designed by an irrigation engineer (plans to be submitted in accordance with the Specific Plan). The system shall ensure that irrigation rates do not exceed the infiltration of local soils and that the application of fertilizers and pesticides do not exceed appropriate levels of frequencies.
c. The landscape and irrigation plans shall be developed to be consistent with the provisions of the Specific Plan, which require that the Estimated Applied Water Use (EAWU) to be less than the Maximum Applied Water Allowance (MAWA) or that the landscape irrigation system include water-conserving features such as low-flow irrigation heads, automatic irrigation scheduling equipment, flow sensing controls, rain sensors, soil moisture sensors, and other water-conserving equipment. In addition, all irrigation systems shall be designed so that they will function properl
y with reclaimed water, if it should become available.

MM HWQ-3 Ongoing during operation of
the Disneyland Resort
The property owner/developer shall provide for the following: cleaning of all paved areas not maintained by the City of Anaheim including, but not limited to, private streets and parking lots on not less than a m onthly basis. Using water to clean streets, parking lots, and other areas shall be allowed on a periodic basis if allowed in the property owner/developer’s NPDES permit and allowable based on drought restrictions. Nightly washdown shall be allowed in the theme parks and, where advisable to maintain safe and sanitary working conditions, the back-of-house area, if allowed in the property owner/developer’s and City's NPDES permit. Flushing debris, residue, and sediment down the storm drains shall conform to the property owner/developer’s NPDES requirements. Property owner/developer agrees that material deposited in City storm drains shall not be in violation of the City's NPDES permit.

Planning & Building
Department, Code
Enforcement Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-23 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM HWQ-4 Prior to each final building
and zoning inspection (for
non-Setback Realm Areas);
prior to acceptance by City
Engineer (for Setback
Realm Areas)
The property owner/developer shall submit a Certificate of Substantial Completion, as described in the Disneyland Resort Specific Plan, which establishes that the landscape irrigation systems have been installed as specified in the approved landscaping and irrigation plans.

Planning & Building
Department, Planning
Services Division

MM HWQ-5 Ongoing during grading
operations
The property owner/developer shall implement standard practices from all applicable codes and ordinances to prevent erosion.

Public Works
Department,
Development Services
Division

MM HWQ-6 Prior to issuance of a
grading permit for sites that
disturb more than one (1)
acre of soil
The property owner/developer shall obtain coverage under the NPDES Statewide Stormwater Permit for General Construction Activities from the State Water Resources Control Board. Evidence of attainment shall be submitted to the Planning and Building Department, Buildin
g Division.

Planning & Building
Department, Code
Enforcement Division

MM HWQ-7 Prior to issuance of each
building permit
To reduce the project's demand on potable water, the property owner/developer shall install water lines onsite so that reclaimed water may be used for landscape irrigation and other purposes, if and when it becomes available.

Planning & Building
Department, Planning
Services Division

MM HWQ-8 Prior to each final building
and zoning inspection
The property owner/developer shall submit a letter from a licensed landscape architect to the City certifying that the landscape installation and irrigation systems have been installed as specified in the approved landscapin
g and irrigation plans.

Planning & Building
Department, Planning
Services Division

MM HWQ-9 Prior to issuance of building
permits
The property owner/developer shall provide written evidence that all storm drain, sewer, and street improvement plans shall be designed and constructed to the satisfaction of the City Engineer.

Public Works
Department,
Development Services
Division

SR HWQ-1 Prior to the issuance of
preliminary or precise
grading permits
Development projects that will result in soil disturbance of one (1) or more acres of land shall comply with the State’s Construction General Permit by filing a Notice of Intent (NOI) with the State Water Resources Control Board (SWRCB) and implementing a Storm Water Pollution Prev ention Plan (SWPPP). The property owner/developer shall provide the City Engineer with evidence that an NOI has been filed with the SWRCB by providing a copy of the NOI invoice and the assigned Waste Discharger Identification (WDID) No. for the project. The SWPPP shall include Best Management Practices (BMPs) designed with a goal of preventing a net sediment load increase in storm water discharges relative to preconstruction levels and shall prohibit during the construction period discharges of storm water or non-storm water at levels which would cause or contribute to an exceedance of applicable water quality standards contained in the Basin Plan. The BMPs shall address erosion control, sediment control, Public Works
Department,
Development Services
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-24 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
wind erosion control, tracking control, non-storm water management and waste management and materials pollution control during all phases of construction, including a sampling and analysis plan for sediment and non-visible storm water pollutants. The property owner/developer shall be responsible for proper implementation of the SWPPP.

SR HWQ-2 Prior to issuance of the
precise grading permit
The property owner/developer shall prepare Water Quality Management Plans (WQMPs) for review and approval by the Public Works, Development Services. The WQMP shall identify permanent site design, source control and treatment control Best Management Practices (BMPs) that will be used on the site to control predictable pollutant runoff. The WQMP shall also describe the long-term operation and maintenance requirements for the treatment control BMPs and the mechanism for funding the BMPs. The WQMP shall be recorded against the property to ensure long- term compliance.

Public Works
Department,
Development Services
Division

SR HWQ-3 Prior to issuance of the first
building permit for Disney
ARSP Properties
The property owner/developer shall pay the Storm Drain Impact Fees which would go toward future storm drain improvements within The Anaheim Resort area and South Central City area.

Public Works
Department,
Development Services
Division

SR HWQ-4 Ongoing during Project
construction and operations
Chapter 10.09 of the Anaheim Municipal Code is the City’s NPDES Ordinance, which provides regulations to comply with the CWA, the California Porter-Cologne Water Quality Control Act, and the City’s NPDE S permit. This ordinance prohibits the discharge of specific pollutants into the storm water; regulates illicit connections to the storm drain system; requires development projects to implement permanent BMPs on individual sites to reduce pollutants in the storm water; and requires local discharge permits for non-storm water discharges into the storm drain system.

Planning & Building
Department, Code
Enforcement Division

SR HWQ-5 Prior to issuance of grading
permit
The property owner/developer of individual developments shall provide written proof to the Public Works Department, Development Services Division of a water quality certification and/or waste discharge requi rement (WDR) as well as a plan for compliance with the discharge prohibitions , TMDLs, and various programs of the Santa Ana RWQCB. The Santa Ana RWQCB implements the Water Quality Control Plan for the Santa Ana River Basin through the issuance of individual WDRs; discharge prohibitions; water quality certif ications; programs for salt management, non-point sources, and storm water; and monitoring and regulatory enforcement actions, as necessar
y.

Public Works
Department,
Development Services
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-25 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
Land Use and Planning
MM LU-1 Prior to issuance of each
building permit
Building plans shall be submitted by the property owner/developer and will be reviewed for consistency with The Disneyland Resort Specific Plan and The Anaheim Resort Specific Plan.

Planning & Building
Department, Planning
Services Division

MM LU-2 Prior to issuance of each
building permit
The proposed project shall be implemented based on the guidelines and standards in The Disneyland Resort Specific Plan, which includes zoning and development standards, design guidelines, and a Public Facilities Plan. All development proposals within The Disneyland Resort must be consistent with The Disneyland Resort Specific Plan, the Anaheim Resort Specific Plan, and the Cit
y of Anaheim General Plan.

Planning & Building
Department, Planning
Services Division

MM LU-3 Prior to issuance of each
building permit for parking
facilities
The property owner/developer shall submit plans detailing the setbacks for the parking structures and landscaping plans which minimize compatibility impacts of the parking facilities on surrounding areas, consistent w ith The Disneyland Resort Specific Plan and the Anaheim Resort Specific Plan.

Planning & Building
Department, Planning
Services Division

PDF LU-1 Prior to approval of issuance
of each building permit
The property owner/developer shall submit documentation that project design features are in compliance with all building setb acks, height standards, landscaping requirements, and design guidelines as sp ecified in The Disneyland Resort Specific Plan and the Anaheim Resort Specific Plan.

Planning & Building
Department, Planning
Services Division

Noise
MM NOI-1 Ongoing during project
operation
The property owner/developer shall obtain pyrotechnic permits on an annual basis.

Material additions or modifications to firework shoots shall require a separate permit.

Fire Department;
MM NOI-2 Ongoing during project
operations
Lower noise-producing fireworks displays will be used at Disney California Adventure to minimize noise from 11:00 p.m. fireworks shows to meet the noise levels in the City of Anaheim Sound Pressure Level Ordinance.

Fire Department;
Planning & Building
Department, Code
Enforcement Division

MM NOI-3 Ongoing during project
operations and prior to the
commencement of any show
west of Disneyland Drive in
the expanded Theme Park
District, the Southeast
District or the ARSP Theme
Park Overlays areas that
includes fireworks that are
No aerial fireworks show shall be allowed west of Disneyland Drive in the expanded Theme Park District, the Southeast District or the ARSP Theme Park Overlays. Prior to the commencement of any show in these areas that includes fireworks that are non- explosive (i.e., stage pyrotechnics) or explosive fireworks with an explosion point at an elevation less 50 feet (e.g., Fantasmic!), the property owner/developer shall present a noise study to the Planning and Building Department to demonstrate that noise levels from the fireworks would meet the City’s 60 dBA Sound Pressure Levels standard at the property line, and would not create a noise increase greater than 5 dBA over Fire Department;
Planning & Building
Department, Code
Enforcement Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-26 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
non-explosive (i.e., stage
pyrotechnics) or explosive
fireworks with an explosion
point at an elevation less 50
feet (e.g., Fantasmic!)
existing ambient noise at the nearest nois e sensitive receptor, whichever is more restrictive.

MM NOI-4 Prior to issuance of a
building permit for an
amphitheater
Plans submitted for the location of the amph itheater will document that the facility is no closer than 2,000 feet from the nearest existing residence. The design and orientation of the amphitheater will be reviewed by a certified acoustical engineer; the property owner/developer shall submit a report, for review and approval by the City, to ensure that noise from the amphitheater does not exceed the noise levels established by the City of Anaheim Sound Pressure Level Ordinance.

Planning & Building
Department, Planning
Services Division

MM NOI-5 Prior to final building and
zoning inspection for the
amphitheater and within 9
months of commencement
of amphitheater operations
A Noise Monitoring Program prepared by a certified acoustical engineer shall be submitted for review and approval. The property owner/developer shall submit the results of the Noise Monitoring Program condu cted by a certified acoustical engineer to ensure that there are no t violations of the Sound Pressure Level Ordinance from amphitheater operations outside the Disneyland Resort. If noise in excess of the Sound Pressure Level Ordinance is detected, the property owner/developer shall modify operations within three days to bring th e amphitheater into co nformance with the Sound Pressure Level Ordinance.

Planning & Building
Department, Planning
Services Division

MM NOI-6 Ongoing during
construction and project
operations
Engine noise from sweeping equipment used in the parking facilities and any hotel parking facilities adjacent to residential areas shall be muffled. Sweeping operations in the parking facilities and private on-site roadways shall be performed utilizing sweeping/scrubbing equipment which operate at a level measured not greater than 60 dBA at the nearest adjacent property line.

Planning & Building
Department, Building
Division; Public Works
Department,
Development Services
Division

MM NOI-7 Prior to issuance of each
building permit to be
implemented prior to final
building and zoning
inspections
For structures that are adjacent to residential areas or other sensitive uses, the property owner/developer shall present plans and calculations to the Planning and Building Department to demonstrate that noise levels from mechanical ventilation units, loading docks, trash compactors, and other proposed on-site noise sources are designed to meet the City’s 60 DBA Sound Pressure Levels standard at the property line, and not create a noise increase greater than 3 dBA over ex isting ambient noise at the nearest noise sensitive receptor, whichever is more restrictive.

Planning & Building
Department, Building
Division and Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-27 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM NOI-8 Ongoing during
construction
The property owner/developer shall ensure that all internal combustion engines on construction equipment and trucks are fitted with properly maintained mufflers.

Planning & Building
Department, Building
Division; Public Works
Department,
Development Services
Division

MM NOI-9 Prior to issuance of each
building permit
The property owner/developer shall submit a noise study prepared by a certified acoustical engineer to the satisfaction of the Building Official identifying whether noise attenuation is required and defining the attenuation measures and specific performance requirements, if warranted, to comply with the California Building Code and Sound Pressure Level Ordinance. Ultimate noise attenuation requirements, if any, shall depend on the final location of such buildings and noise-sensitive uses inside and surrounding the buildings. Attenuation measures, such as but not limited to acoustic sound barriers, shall be implemented by the property owner/developer prior to final building and zoning inspections.

Planning & Building
Department, Building
Division and Planning
Services Division

MM NOI-10 Prior to issuance of each
building permit for
construction within 75 feet
of noise sensitive receptors
A note shall be provided on building plans indicating that during construction, the property owner/developer shall install and maintain specially designed construction barriers between the project perimeter an d the sensitive recepto r. The construction sound barriers shall be a minimum height of 8 feet with a minimum surface weight of

1.25 pounds per square foot or a minimum Sound Transmission Class (STC) rating of

25. The structure shall be a continuous barrier. Gates and other entry doors shall be constructed with suitable mullions, astragals, seals, or other design techniques to minimize sound leakage when in the closed position. Access doors should be self closing where feasible. Vision ports are perm issible providing they are filled with an acceptable solid vision produc
t.

Planning & Building
Department, Building
Division and Planning
Services Division

MM NOI-11 Ongoing during
construction and project
operation
Pressure washing operations for purposes of building repair and maintenance due to graffiti or other aesthetical considerations and in areas along the property line or accessible by the public shall be limited to daytime hours of operation between 7:00 AM and 8:00 PM.

Planning & Building
Department, Code
Enforcement Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-28 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM NOI-12 Ongoing during
construction
Property owners/developers shall pay for a ll reasonable costs associated with noise monitoring which shall include monitoring conducted by a certified acoustical engineer under the direction of the Planning and Building Department four times a year on a random basis to ensure that outdoor construction-related sound levels at any point on the exterior project bounda ry property line do not exceed 60 dBA between the hours of 7:00 PM and 7:00 AM of the following day where outside construction is occurring.

If a complaint is received by the City, add itional noise monitoring shall be conducted at the discretion of the City. If the monitoring finds that the 60 dBA threshold is being exceeded, construction activities will be modified immediately to bring the sound level below the 60 dBA requirement, with additional follow-up monitoring conducted to confirm compliance.

Planning & Building
Department, Planning
Services Division

MM NOI-13 Prior to issuance of each
building permit
A note shall be provided on plans indicating that there shall be no operation of clam shovel drops or vibratory rollers within 25 feet of any existing home.

Planning & Building
Department, Building
Division

MM NOI-14 Prior to issuance of each
building permit on Disney
ARSP Properties
If pile driving and blasting is anticipated during construction, a noise and vibration analysis must be prepared and submitted to the Planning and Building Department to assess and mitigate potential noise and vibr ation impacts related to these activities, including site design features such as setbacks and trenches.

Planning & Building
Department, Building
Division

MM NOI-15 Prior to issuance of each
building permit and to be
implemented prior to final
building and zoning
inspections
The property owner/developer shall present area development plans if part of a new theme park land or building plans if part of one theme park attraction to the Planning and Building Department to demonstrate any development of theme park uses in the expanded Theme Park District (west of Disn eyland Drive), the Southeast District, or the ARSP Theme Park Overlays includes 30-f oot-tall buildings or structures between the property line near residential or other noise sensitive land uses and the proposed theme park land or theme park attraction. If a noise barrier is provided, such as a ride façade, the material used shall have a mi nimum surface weight of 1.25 pounds per square foot or a minimum Sound Transmission Class (STC) ratin g of 25.

Planning & Building
Department, Planning
Services Division
MM NOI-16 Ongoing during project
operations
The property owner/developer shall pay all reasonable costs associated with noise monitoring which shall include monitoring conducted by a certified acoustical consultant or engineer under the direction of the Planning Department to ensure that The Disneyland Resort ongoing operations do not exceed 60 dBA at any point on the property line between the hours of 7:00 p.m. and 7:00 a.m. of the following day. If the monitoring finds that the 60 dBA threshold is being exceeded, modifications to the ongoing operations, such as adjustments to volume at the source or orientation of speakers, shall be commenced immediatel
y to bring the sound level below the 60 dBA
Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-29 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
requirement with additional follow-up monito ring conducted to confirm compliance.

Monitoring shall be conducted as follows:
(a) Ongoing: Semi-annually on a random basis for a three (3) day period. (b) During the first five (5) years of oper ation of theme park uses in the expanded Theme Park District west of Disneyland Drive, the Southeas t District, and/or the ARSP Theme Park Overlays: Four (4) times a year on a random basis for a three (3) day period.
(c) In response to a noise complaint, at the City’s discretion: For a three (3) day period at the location of the noise exceedance.

MM NOI-17 Prior to the issuance of each
building permit, grading
permit or demolition permit
A note shall be provided on the plans stating that ongoing during construction, the property owner/developer shall designate a noise disturbance coordinator who would respond to neighborhood complaints about construction noise by determining the cause of the noise complaints and requiring implementation of reasonable measures to correct the noise issue.

Planning & Building
Department, Planning
Services Division

MM NOI-18 Ongoing during
construction
The property owner/developer shall locate all stationary noise-generating equipment such as air compressors and portable generators a minimum of 75 feet from noise sensitive receptors.

Planning & Building
Department, Building
Division

MM NOI-19 Ongoing during
construction
No impact driven piles shall be allowed in conjunction with the construction of parking structures.

Planning & Building
Department, Building
Division

MM NOI-20 Prior to issuance of a
building permit for a
parking structure
The property owner/developer will submit plans to the Planning and Building Department indicating noise from the parking structure will be reduced by the provision of convenient access to the parking structure, sound attenuation devices (louvers and walls), and the use of textured deck surfaces to reduce tire squealin g.

Planning & Building
Department, Planning
Services Division

MM NOI-21 Prior to issuance of each
building permit
The property owner/developer shall present plans to the Planning and Building Department to demonstrate development of theme park uses in the expanded Theme Park District (west of Disneyland Drive), the Southeast District, or the ARSP Theme Park Overlays shall include installation and maintenance of at least 12-foot-tall noise barriers along the property line to reduce back-o f-house noise, such as vehicle pass- bys and truck deliveries with a minimum surface weight of 1.25 pounds per square foot or a minimum Sound Transmission Class (STC) ratin
g of 25.

Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-30 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM NOI-22 Prior to issuance of each
building permit and to be
implemented prior to final
building and zoning
inspections
The property owner/developer shall present a noise study and area development plans if part of a new theme park land or building plans if part of one theme park attraction in the expanded Theme Park District (wes t of Disneyland Drive), the Southeast District, or the ARSP Theme Park Overlays to the Planning and Building Department to demonstrate any Thrill (Indoor) and Family (Indoor) attractions shall be located no less than 200 feet from the center of the ri de or attraction to noise-sensitive receptors and shall include a 30-foot-high building or a 30-foot high noise barrier between the attraction and the property line near noise-sensitive receptors, provided a 30-foot-high building or 30-foot-high noise barrier shall not be required if the proposed ride or attraction is located within an enclosed building or structure. The planning of each attraction shall take into account any openin gs or outdoor areas of the attractions and directionally orient the openings away from noise-sensitive receptors and towards the center of the new theme park development
Planning & Building
Department, Planning
Services Division

MM NOI-23 Prior to issuance of each
building permit and to be
implemented prior to final
building and zoning
inspections
The property owner/developer shall present a noise study and area development plans if part of a new theme park land or building plans if part of one theme park attraction in the expanded Theme Park District (wes t of Disneyland Drive), the Southeast District, or the ARSP Theme Park Overlays to the Planning and Building Department to demonstrate any Thrill (Outdoor), rides taller than 50 feet, Parades and Large Shows shall be located:

1. For 1st to 3rd Offsite Fl oor Receptors: No less than 550 feet from the center of the ride to any noise-sensitive receptor and shall include a 30-foot-high building or a 30-foot-high noise barrier between the attraction and the property line near noise-sensitive receptors.

2. For 4th Floor Offsite Receptors and above (i.e., no shielding from 30-foot buildings/barriers): No less than 1100 f eet between the center of the ride and any noise-sensitive receptor. If the distance of 1100 feet cannot be met, an indoor rollercoaster shall be considered . If a distance less than 1100 feet is considered with exposure to 4th Floor receptors, the distance to noise-sensitive receptors and layout shall be reviewed by a certified acoustical consultant or engineer prior to finalizing the site plan. In general, the entire full height of the ride shall include a solid barrier shielding it from any noise-sensitive receptors.

The material used for the barrier shall have a minimum surface weight of 1.25 pounds per square foot or a minimum Sound Transmission Class (STC) rating of 25.

Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-31 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM NOI-24 Prior to issuance of each
building permit and to be
implemented prior to final
building and zoning
inspections
The property owner/developer shall present a noise study and area development plans if part of a new theme park land or building plans if part of one theme park attraction in the expanded Theme Park District (wes t of Disneyland Drive), the Southeast District, or the ARSP Theme Park Overlays to the Planning and Building Department to demonstrate any Family (Outdoor), Round and Small Show attractions shall be located at least 400 feet from sensitive r eceptors and include a 30-foot-high building or a 30-foot-high noise barrier between the attraction and the property line near noise- sensitive receptors.

Planning & Building
Department, Planning
Services Division

SR NOI-1 Prior to issuance of grading
and/or building permits
Contractor specifications shall include a note indicating that noise-generating construction activities which produce a sound pressure level at any point along the property line in excess of 60 dBA shall be limited to between the hours of 7:00 AM to 7:00 PM on any day. This requirement is iden tified in Section 6.70.010 of the City of Anaheim’s Noise Ordinance. Additional work hours may be permitted if deemed necessar
y by and on approval of the Director of Public Works or Building Official.

Planning & Building
Department, Building
Division

SR NOI-2 Prior to issuance of building
permits
Development shall comply with Title 24 of the California Code of Regulations, also known as the California Building Standards Code, which establishes building standards applicable to all occupancies throughout the state. Title 24 requires that new hotels, motels, and multi-family residences be designed to prevent the intrusion of exterior noise so that the interior noise, attributable to exterior sources, shall not exceed the 45 dBA Community Noise Equivalent Level (CNEL) in any habitable room with windows closed.

Planning & Building
Department, Building
Division

SR NOI-3 Ongoing during Project
construction
No commercial use shall produce noise associated with continual loading or unloading of heavy trucks at the site between the hours of 8:00 PM and 6:00 AM (Municipal Code Section 18.32.130).

Planning & Building
Department, Building
Division

Population and Housing
PDF POP-1 Ongoing during project
operations
The Walt Disney Company will recruit workers who are already a part of the resident work force in the region. Implementation of The Disneyland Resort Specific Plan will further efforts in offering employment opportunities at various socioeconomic levels.

Planning & Building
Department,
Planning Services
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-32 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
Public Services
Fire
MM PS-1 Prior to issuance of each
building permit for
development in the ARSP
Parking and Theme Park
Overla
ys
The property owner/developer shall pay all applicable fire fees in the amount then in effect and in accordance with the City-adopted Fire Protection Facilities and Paramedic Services Impact Fee Program (initially es tablished through City Council Resolution No. 95R-73). Alternatively, the City and the Property Owner/Developer may enter into alternative financing arrangements.

Fire Department
MM PS-2 Prior to commencement of
structural framing on each
parcel or lot
Onsite fire hydrants shall be installed an d charged, as required, by the property owner/developer.

Fire Department
MM PS-3 Prior to approval of each
grading plan
The property owner/developer shall submit an emergency fire access plan to ensure that service to the site is in accordance with the Fire Department service requirements.

Fire Department
MM PS-4 Prior to issuance of each
building permit
The property owner/developer shall submit a Construction Fire Protection Plan which shall include detailed design plans for accessi bility of emergency fire equipment, fire hydrant location, and any other construction features required by the Fire Marshal. The property owner/developer shall be responsible for securing facilities acceptable to the Fire Department and hydrants shall be operational with required fire flow. A construction plan providing a complete timeline and construction goals shall be provided and approved by the Fire Department for all new construction projects.

Fire Department
MM PS-5 Prior to issuance of each
building permit; to be
implemented prior to each
final building and zoning
inspection
Plans shall indicate that all buildings shall have sprinklers installed by property owner/developer, to include all open and closed parking structures, exclusive of one- story detached accessory buildings of less than 120 square feet in floor area, and free standing shade structures that are open on at least two sides to sufficiently prevent the accumulation of smoke and hot gases. Additionally, alternatives to automatic sprinkler systems (e.g., self-contained water mist systems) that provide an equivalent level of fire protection may be approved for other buildings on a case-by-case basis upon review and approval by the Fire Department.

Fire Department
DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-33 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM PS-6 Prior to issuance of each
building permit
Plans shall be submitted to ensure that development is in accordance with the City of Anaheim Fire Department Standards, including:
a. Overhead clearance shall not be less than 14 feet for the full minimum width of 26 feet for all designated fire access roads.
b. All fire access roads, bridges and under ground structures to be used for Fire Department access shall be designed to support Fire Department vehicles weighing 78,000 pounds.
c. All underground tunnels shall have sprinklers. Water supplies (hydrants) are required at the entrances. Standpipes shall also be provided when determined to be necessary by the Fire Department.
d. Adequate off-site public fire hydrants contiguous to the Specific Plan area and onsite private fire hydrants shall be provided by the property owner/developer.

The precise number, types, and locations of the hydrants shall be determined during building permit review. Hydrants are to be a maximum of 300 feet apart. e. A minimum residual water pressure of 20 psi shall remain in the water system.

Flow rates for all structures shall be a minimum of 1,500 gallons per minute f. Fire access roads shall be provided with vertical and horizontal clearance in compliance with Fire Department standards. Any changes to emergency vehicle access roads shall be included in the overall emergency vehicle access plans for the Resort area, and maintained by property owner/developer. The Fire Code Official shall review all proposed cha nges and determine whether to approve any deviations from these standards.
g. Temporary structure regardless of type of construction shall be considered temporary if at a location for less than 6 months. Other than pre-fabricated construction trailers, structures that ar e at a location for more than 6 months shall be provided with a fire suppression system and/or fire notification/life safety systems applicable to the use of the structure.
h. Integrated Safety Systems (ISS) testing as designed by the property owner/developer or an updated equivalent shall be required for all attractions on an annual basis. The property owner/developer shall provide advance notice to the Fire Department to coordinate witnessing of such testing at the Fire Code Official’s discretion.

Fire Department
DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-34 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM PS-7 Prior to issuance of the first
building permit for the
DisneylandForward Project
or as otherwise specified in
the Development
Agreement between the City
and Disne
y
The property owner/developer shall enter into a Fire Operations Agreement with the City of Anaheim to pay or cause to be paid its fair share of the funding to address the Operations and Community Risk Reduction staffing needs to maintain adequate levels of service of response and ongoing fire in spection of the Project and in the Anaheim Resort.

Fire Department; City
Attorney’s Office

MM PS-8 Prior to approval of street
improvement plans and
water improvement plans
The water supply system shall be designed by the property owner/developer to provide sufficient fire flow pressure and storage for the proposed land use and fire protection in accordance with Fire Department requirements.

Fire Department
MM PS-9 Prior to the final building
and zoning inspection for a
hotel
The property owner/developer shall submit an emergency evacuation response plan for review and approval by the Fire Department . The plan shall require posted notices in all hotel rooms on emergency evacuation procedures and incorporate ongoing emer
gency evacuation training for hotel staff to the satisfaction of the Fire Department.

Fire Department
MM PS-10 Prior to issuance of each
building permit
Plans shall be reviewed and approved by the Fire Department as being in conformance with the California Fire Code.

Fire Department
MM PS-11 Prior to the placement of
building materials on a
building site
An all-weather fire access road shall be pr ovided from the roadway system to and on the construction site and for fire hydrants at all times, as required by the Fire Department. Such routes shall be paved or, subject to the approval of the Fire Department, shall otherwise provide adequate emergency access. Every building constructed must be accessible to Fire Department apparatus. The width and radius of the driving surface must meet the requirements noted in the Anaheim Municipal Code and in accordance wi
th City of Anaheim Fire Department Standards.

Fire Department
MM PS-12 Prior to approval of building
plans
The property owner/developer shall provide written evidence to the satisfaction of the Fire Department that all lockable pedest rian and/or vehicular access gates shall be equipped with “knox box” devices as required and approved by the Fire Department.

Fire Department
MM PS-13 Prior to approval of on-site
water plans
Unless each commercial building is initially co nnected to separate fire services, an unsubordinated covenant satisfactory to the City Attorney’s Office shall be recorded prohibiting any individual sale of buildings until separate fire services are installed in the building(s) subject to the sale.

Fire Department; City
Attorney’s Office

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-35 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM PS-14 Prior to the issuance of
construction permits
associated with
development of over 10,000
sf within the Theme Park
District or as otherwise
specified in the
Development Agreement
between the City of
Anaheim and Walt Disney
Parks and Resorts U.S., Inc.

The property owner/developer shall locate and design a Fire Substation within the Theme Park District, in a location approved by the Fire Chief. The Substation shall meet the below minimum criteria, and is subject to the review and approval of the Fire Chief:

1. Designated parking stalls, for a medic truck, ambulance, medic golf cart, and 2 staff vehicles

2. Equipped with dedicated fiber op tic line (services for cable, wifi)

3. Two offices with two workstations each

4. Breakroom/kitchen type area

5. Day room able to accommodate up to 8 personnel (4 paramedics, 2 ambulance, 2 Community Risk Reduction)

6. Restrooms with showers/locker rooms
Fire Department;
Planning & Building
Department,
Planning Services
Division

MM PS-15 Prior to issuance of building
permits for any structure
greater than 75 feet tall
The property owner/developer shall conduct an analysis to determine if the structure would interfere with the Emergency Radio Response Communication (ERRC) System signal. If warranted based on the analysis, the property owner/developer shall be responsible for installation of new or relocated equipment.

Fire Department
PDF PS-1 Ongoing during project
operation
The existing services and capabilities of th e Disneyland Fire Department shall be maintained for the DisneylandForward Pr oject Site. Existing services include preconstruction checks, pre-investigation of fires and alarms, preplanning for fires and evacuations, fire prevention program activities, and monitoring of pyrotechnics and special effects.

Fire Department
Police
MM PS-16 Prior to issuance of each
applicable building permit
The property owner/developer shall pay all applicable police prot ection fees in the amount then in effect. Alternatively, the City and the property owner/developer may enter into alternative financing arrangements.

Police Department
MM PS-17 Ongoing during operation of
the Disneyland Resort
The operator of the public parking facilities sh all provide an adequate staff of private security officers for patrol and surveillance of the facilities.

Police Department
DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-36 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM PS-18 Prior to the issuance of the
first building permit for
DisneylandForward Project
or as otherwise specified in
the Development
Agreement between the City
of Anaheim and Walt
Disney Parks and Resorts
U.S., Inc.

The property owner/developer shall enter in to Police Operations Agreement with the City of Anaheim to pay or cause to be paid its fair share of the funding for police personnel and equipment necessary to meet the service need of the Anaheim Resort as determined by the Chief of Police.

Police Department;
City Attorney’s Office

MM PS-19 Prior to issuance of each
building permit for parking
structures
The Police Department shall review the safety measures incorporated into the building plans for the parking structures within the DisneylandForward Project Site to be submitted by the property owner/developer. The security measures shall include the following or other substitute security measures as may be approved by the Police Department:
 Immediate access in priority criminal cases, where an urgent need or demand exists and time is of the essence.
 Closed circuit television surveillance and recording equipment or other adequate security measures reviewed and approved by the Police Department .

Police Department
MM PS-20 Ongoing during operation of
the Disneyland Resort
The property owner/developer shall continue to provide anti-gang, human trafficking, child exploitation and substance abuse ed ucational programs which are currently provided for park security cast members.

Police Department
MM PS-21 Ongoing during operations The Disneyland Security De partment shall be maintained to provide equivalent levels of service to the entire Disneyland Resort. These services will include initial response, investigation, and report writing. Entry points to the theme parks will be patrolled by the Disne
yland Security Department.

Police Department
MM PS-22 Prior to issuance of each
building permit for a hotel
The property owner/developer shall submit plans to the Police Department for review and approval by the Chief of Police, or their designee, for safety, accessibility, crime prevention, and security provisions during both the construction and operative phases for the purpose of incorporating safety me asures in the project design including the concept of crime prevention through environmental design (e.g., building design, circulation, site plannin
g, and lighting of parking structures and parking areas).

Police Department
MM PS-23 Prior to issuance of each
building permit for or
including a parking lot
and/or parking structure
The project design shall include parking lots and parking structures with controlled access points to limit ingress an d egress if determined to be necessary by the Police Department and shall be subject to the review and approval of the Police Department.

Police Department
DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-37 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM PS-24 Prior to issuance of the first
building permit for the
DisneylandForward Project
or as otherwise specified in
the Development
Agreement between the City
of Anaheim and Walt
Disney Parks and Resorts
U.S., Inc.

The property owner/developer shall coordinate with the Police Department to construct and maintain a Substation in the Theme Park District which meets the following minimum criteria:
• Designated parking stalls, including EV charging stations, for approximately 4- 6 EV, 15-20 regular spaces
• Equipped with dedicated fiber optic line
• Minimum of two private offices
• Conference/briefing room
• Interview room
• Kitchen
• Breakroom
• Locker rooms with showers, restrooms, and lockers
• Enclosed bicycle storage for at least 12 bicycles
• Equipment storage (size equivalent to two offices)
The location and facility components are subj ect to the review and approval of the Chief of Police. A designee of the Chief of Police shall be included in the initial design phase of the Substation, and shall be regularly consulted during design and construction. Any subsequent modification or relocation to either facility is subject to the review and approval of the Chief of Police.

Police Department;
Planning & Building
Department,
Planning Services
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-38 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM PS-25 Prior to issuance of the first
building permit for
development of over 10,000
sf in the Southeast District
or Theme Park East Overlay
or as otherwise determined
in the Development
Agreement between the City
of Anaheim and Walt
Disney Parks and Resorts
U.S., Inc.

The property owner/developer shall coordinate with the Police Department to construct and maintain a Satellite Office in the Southeast District or the Theme Park East Overlay which meets the following minimum criteria:
• Designated parking stalls, including 2 -4 EV charging stations, 6 - 8 regular spaces
• Equipped with dedicated fiber optic line
• Breakroom
• Conference/briefing room
• Interview room
• Restrooms
• Enclosed bicycle storage for at least 6 bicycles
The location and facility components are subj ect to the review and approval of the Chief of Police. A designee of the Chief of Police shall be included in the initial design phase of the Satellite Office, and shall be regularly consulted during design and construction. Any subsequent modification or relocation to either facility is subject to the review and approval of the Chief of Police.

Police Department;
Planning & Building
Department,
Planning Services
Division

PDF PS-2 Ongoing during project
operation
The property owner/developer shall continue to provide and expand its Court Liaison program to meet the needs of the Disneyland Resort.

Police Department
Schools
MM PS-26 Prior to issuance of each
building permit
The property owner/developer shall provide proof that school impact fees have been paid consistent with State statute.

Planning & Building
Department, Building
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-39 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
PDF PS-3 Ongoing during project
operations
The Disneyland Resort has developed and/or engaged in a series of educational programs in cooperation with the local community and regional agencies and organizations, designed to enhance and complement the educational opportunities and experiences for the youth. The 10 educati onal programs that currently exist are indicated below

1. Anaheim Union High School Distri ct’s Anaheim’s In novative Mentoring Experience (AIME) program

2. Big Brothers & Big Sisters of Orange County’s Workplace Mentoring Program at Anaheim Union High School District

3. United Way’s Youth Career Connections and Speakers Bureaus at the Anaheim Union High School District

4. Anaheim Family YMCA Avanza Program

5. Orange County Asian Pacific Islander Community Alliance’s ROOTED Career Development Program at Anaheim Union High School District

6. Hola Readers at Anaheim Elementary School District

7. Anaheim Elementary School District’s Broadway Bound: Empowering Young Performers in Anaheim

8. Boys & Girls Clubs of Greater Anaheim-Cypress gEARed Up for the Future

9. School Support Programs Girls Inc.’s Girls Meet the Workforce/Project Accelerate

10. CIF Champion Celebration Girl Scouts of Orange County’s Career Exploration Program – Dreams to Reality
The property owner/developer will continue these programs and/or substitute similar programs of equal importance.

Planning & Building
Department, Planning
Services Division

Parks
PDF PS-4 Ongoing during operations Substantial area within the Disneyland Resort shall be designed to encourage utilization by pedestrians in a park-like setting linking key areas of the project as described in the Disneyland Resort Specific Plan.

Planning & Building
Department, Planning
Services Division;
Community Services
Department, Parks
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-40 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
PDF PS-5 Ongoing during operations The property owner/developer shall provide space(s), outside the ticketed theme park gates, easily accessible to theme park guests and non-ticketed visitors, where those who have brought their own food can eat. The proximity of amenities such as drinking fountains, vending machines, and restrooms/locker facilities will be considered in the siting and design or such space(s).

Planning & Building
Department, Planning
Services Division;
Community Services
Department, Parks
Division

Libraries
MM PS-27 Prior to the issuance of a
building permit for
development in the ARSP
Parking and Theme Park
Overlays, with the exception
of theme park square
footage transferred from the
DRSP
The property owner/developer shall comply with the Anaheim Municipal Code, Section 17.08.385, Public Library Faciliti es Services Areas – Payment of Fees Required.

Planning & Building
Department, Building
Division

Transportation
MM TRA-1 Ongoing during project
development and operations
The property owner/developer shall implement the improvements and pay in lieu fees described in Table 19 (Recommended Intersection Improvements) and Table 20 (Other Transportation Improvements) of the Op erational Traffic Analysis for the DisneylandForward Project (Gibson 2023), as set forth in Appendix J-2 of Subsequent EIR No. 352, within the time frames described in those tables. Prior to the issuance of each building permit, any remaining appli cable Traffic Signal Assessment Fees and Transportation Impact and Improvement Fees (Fees) relating to the building permit site shall be paid by the property owner/developer to the City of Anaheim in the amounts determined by the City Council Resolution in effect at the time of issuance of the building permit, except to the extent such fees may have been previously paid or satisfied pursuant to one or more separate agreements between Walt Disney Parks and Resorts U.S., Inc. and the City of Anaheim relating to The Disneyland Resort Project or The DisneylandForward Project.

Public Works
Department, Traffic
and Transportation
Division

MM TRA-2 Prior to approval of the first
final subdivision map or
issuance of the first building
permit, whichever occurs
first, or as otherwise
established in Development
The property owner/developer shall irrevocably offer for dedication (with subordination of easements), including necessary construction easements, the ultimate arterial highway right(s)-of-way adjacent to their property as shown in the Circulation Element of the Anaheim General Plan.

Public Works
Department,
Development Services
Division; Public Works
Department, Traffic

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-41 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
Agreement between the City
of Anaheim and Walt
Disney Parks and Resorts
U.S., Inc. or as approved
pursuant to a Discretionary
Exemption to establish the
timing of Street and Other
Right-of-Way Dedications
and Improvements
(Anaheim Municipal Code
Section 18.40.060
Dedications and
Improvements)
and Transportation
Division
MM TRA-3 Prior to demolition of an
existing Disneyland Resort
parking lot

Ongoing during project
operation
Replacement parking for the ex isting parking spaces remove d will be constructed or secured.

Access Improvements and Public Parking Facilities Included in Project Design (Exhibit 4.3.1b – Interstate 5-West St reet/Disneyland Drive Interchange (Showing Entrance to West Parking Facility) and Exhibit 4.3.1c – Interstate 5/Katella Interchange (Showing Entrance to East Parking Facility)

Public Parking Facilities. New public parking facilities will be constructed at opposite sides of The Disneyland Resort Specific Plan area to receive traffic from the I-5. A minimum of 24,500 guest and cast parking spaces will be provided. The West Parking Area is oriented to receive southbound I-5 traffic, and the parking facilities in the East Parking Area and adjacent ARSP Parkin g Overlay will be oriented to receive northbound I-5 traffic.

Planning & Building
Department, Planning
Services Division;
Public Works
Department, Traffic
and Transportation
Division

MM TRA-4 To be implemented prior to
final building and zoning
inspections for the east and
west parking structures/
facilities
To be shown on street improvement plans:

Improved Access. Access roads leading up to the parking facilities shall be sized to accommodate traffic at peak ho urs, thereby substantially reducing the likelihood of backups onto City streets and freeway ramps, subject to the approval of the City Engineer.

No cast or guest access or egress will occur from Walnut Street.

Planning & Building
Department, Planning
Services Division;
Public Works
Department, Traffic
and Transportation
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-42 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM TRA-5 Prior to issuance of each
building permit; to be
implemented prior to final
building and zoning
inspections for both the east
and west parking structures
Speed Parking. Building plans shall show dir ect ramps to each level of the East and West Parking Area facilities to minimize inte rnal circulation within the garages and accommodate the project's "speed parking" operation.

Planning & Building
Department, Planning
Services Division;
Public Works
Department, Traffic
and Transportation
Division

MM TRA-6 To be implemented prior to
final building and zoning
inspection for each parking
structure and/or facility
To be shown on street improvement plans:

Conveyance Systems. In addition to an extensive network of landscaped pedestrian thoroughfares, conveyance syst ems will transport Disneyland Resort guests around The Anaheim Resort. Guest transportation systems will move guests from the parking facilities to the Theme Park District. The monorail/guest transportation systems shall move guests within the Theme Park District. Future connections may also be provided to the Southeast District.

Planning & Building
Department, Planning
Services Division;
Public Works
Department, Traffic
and Transportation
Division

MM TRA-7 To be implemented prior to
final building and zoning
inspections for the second
theme park for Phase II; and
if pursued, to be
implemented prior to final
building and zoning
inspections for the East
Parking Area or adjacent
ARSP Parking Overlay
parking structure(s) or other
accessible location in Phase
IV
To be shown on street improvement plans:

Theme Park Drop-Off Area. To provide access to the attrac tions in the Specific Plan area to people staying outside of The Disneyland Resort area, a bus and shuttle drop- off area will be located adjacent to Harbor Boulevard north of Disney Way as shown on Exhibit 4.4.2a of the Specific Plan; or , in Phase IV, the facility may be located adjacent or internal to the East Parking Ar ea or the adjacent ARSP Parking Overlay Parking Structure(s), or other accessible location in the Theme Park District. The types of vehicles served at this facility may include public and private passenger shuttles and buses.

Planning & Building
Department, Planning
Services Division;
Public Works
Department, Traffic
and Transportation
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-43 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM TRA-8 Ongoing during project
operation
Transportation Demand Management Program
The need to minimize cast vehicle trips to reduce congestion and improve air quality, consistent with the goals of both the Ai r Quality Management Plan (AQMP) of the South Coast Air Quality Management District (SCAQMD) and with the Regional Mobility Plan of the Southern California Association of Governments (SCAG), is recognized. The Disneyland Resort will implement and administer a comprehensive Transportation Demand Management (TDM) program for all cast, which will strive to achieve an average vehicle ridership (AVR) goal of 1.5 persons per vehicle and, an average length of out-of-area guest stay of 1.72 days.

At this point in project development, it is not possible to predict precisely which programs and activities would be most su ccessful for The Disneyland Resort in meeting these goals. In addition, property ow ner/developer will review annually with the City any changes to the TDM Program and the Program's effectiveness toward achieving a 1.5 AVR. In consultation with the SCAQMD, the City of Anaheim and other agencies, and after analyzing the effectiveness of these items, Walt Disney Parks and Resorts U.S., Inc. will select specific programs for implementation.

Objectives of the TDM program are:
• Increase ridesharing and use of alternative transportation modes by guests. • Meet the cast 1.5 AVR target.

Public Works
Department, Traffic
and Transportation
Division; South Coast
Air Quality
Management District

• Provide a menu of commute alterna tives for The Disneyland Resort cast, to reduce project-generated trips.
• Provide transportation "linkages" to existing and future transportation modes (other than single-occupant vehicle travel) for both The Disneyland Resort cast and guests.

Implementation strategies and elements of the TDM program for cast and guest trips are described below.

Cast
Making a commitment to commute management and trip reduction will become an integral part of the new-hire training. A menu of TDM program strategies and elements for both, existing and future cast commute options would be examined, including, but not limited to, the following:

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-44 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
• Onsite Service. Onsite services, such as the food, retail, and other services may be provided to the cast.
• Ridesharing. An online listing of all cast members living in proximity to The Disneyland Resort may be developed for the purpose of providing a "matching" of members with other cast members who live in the same geographic areas and who could rideshare to The Disneyland Resort.
• Vanpooling. An online listing of all cast memb ers living in proximity to The Disneyland Resort may be developed for the purpose of matching numbers of cast who live in geographic proximity to one another and could comprise a vanpool to The Disneyland Resort.
• Transit Pass. Southern California Rapid Transit District and Orange County Transportation Authority (including commuter rail) passes may be promoted through financial assistance and onsite sales to encourage cast to use the various transit and bus services to The Disneyland Resort from throughout the region. • Commuter Bus. As commuter "express" bus service expands throughout the region, passes for use on these lines may be provided for cast members who choose to use this service. Financial incentives will be provided. • Shuttle Service. A computer listing of all cast members living in proximity to The Disneyland Resort may be generated, and a local shuttle program will be offered to encourage cast members to trav el to work by means other than the automobile.
• Bicycling. A Disneyland Resort Bicycling Program may be developed to offer a bicycling alternative to cast members. Secure bicycle racks, lockers, and showers will be provided as part of th is program. Maps of bicycle routes throughout the area would be provided to inform potential bicyclists of these options.
• Rental Car Fleet. A "fleet vehicle" program may be developed to provide cast members who travel to work by means other than an automobile with access to automobiles in case of emergency, medi cal appointments, etc. This service would help cast members use alternative modes of transportation by ensuring that they would be able to have personal transportation in the event of special circumstances.
• Emergency Ride Home Program . The program may provide cast members who rideshare, or use transit or other means of commuting to work, with a prearranged ride home in a taxi, rental car, shuttle, or other vehicle, in the event DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-45 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
of emergencies during the work shift. In essence, this program addresses the concerns of the cast member who rideshares and might be stranded without a vehicle in the event of an emergency.
• Local Hiring Efforts . Continue to actively recruit prospective employees within 20 miles.
• Target Reduction of Longest Commute Trip . Design an incentives program for ridesharing and other alternative transportation modes to put highest priority on reduction of longest employee commute trips.
• Work Schedule
- Staggered Shifts. The Disneyland Resort cast may work different hours throughout the daily hours of park operation. A thorough review of cast shifts would be undertaken to provide the potential for cast shifts during nonpeak travel times, thus lessening peak hour congestion. - Compressed Work Week . The Disneyland Resort may review the possibility of developing a "compressed work week" program, which provides for fewer work days but longer daily shifts, as an option for cast members. This program would help eliminate certain trips on certain days that would otherwise be generated daily by The Disneyland Resort Cast. - Telecommuting. The Disneyland Resort employs cast members in a wide a variety of jobs including clerical, administrative and professional roles. Sometimes that work can be completed at home. Telecommuting will be encouraged on a limited basis as operational needs allow. • Work Environment/Facility Management
- Parking Management. The Disneyland Resort may develop a parking management program that provides incentives to those who rideshare or use transit means other than single-occupant auto to travel to work. - Management Staff. The existing Disneyland theme park transportation management staff may be expanded onsite to accommodate new employees and to explore relations hips with adjacent employers to determine whether joint efforts can lead to greater reductions in VMT by Disneyland Resort cast members an d other employees in the Anaheim Resort.

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-46 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
- Amenities. Transit systems, transit shelters, bicycle storage areas, and other amenities may be provided with efficient parking management for cast and guests.
- Access. Preferential access to high occupancy vehicles and shuttles may be provided.
- Delivery Management . Schedule deliveries in nonpeak traffic congestion hours to the extent reasonably practicable.
• Financial Incentives
In addition to the above items, certain financial incentives will be integrated into The Disneyland Resort TDM program, such as:
- Financial Incentive for Ridesharing and/or Public Transit. Currently, federal law provides tax-free status for up to $300 per month per employee contributions to employees who vanpool or use public transit (including commuter rail and/or express bus pools). In addition, The Disneyland Resort provides free OCTA passes and a 75% subsidy (up to $100/month) for other transit passes.
- Financial Incentive for Bicycling and Walking. Cast members may be offered financial incentives for bicycling to work; they would be provided with secure bicycle racks, lockers, and showers. Cast members may also receive a cash incentive for reporting a bike or walk commute. - Financial Incentive for Carpooling . Cast members may be offered a cash incentive for carpooling to work.
- Special “Premium" for the Participation and Promotion of Trip Reduction. Tickets/passes to project theme parks and/or vacations could be offered to employees who recruit other cast members for vanpool, carpool, or other Disney trip reduction programs.
• Guests
- Even though visitors to The Disneyland Resort are estimated to average nearly four persons per vehicle, additional programs and incentives could and will be provided to encourage even more guest use of ridesharing, transit, and other modes of travel to and from The Disneyland Resort.

The property owner/developer is currently developing a list of potential programs and is workin g with the Cit y of Anaheim and OCTA on the DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-47 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
provision of convenient linkages to other modes of transportation.

Marketing materials for The Disneyland Resort will describe it as an "auto-free" zone with a range of tr ansportation amenities where cars are not needed.
- Bicycle spaces for guests shall be visible from the primary entrance, illuminated at night, and protected from damage from moving or parked vehicles.
• Construction Contractors
The property owner/developer shall provide notification to the general construction contractors regarding the coordination of rideshare services for construction employees provided by the Anaheim Transportation Network (ATN).

MM TRA-9 Ongoing during project
operations
The property owner/developer shall continue to participate in a clean fuel shuttle program, and shall participate in the Anaheim Transportation Network (ATN) in conjunction with the ongoing operation of The Disneyland Resort, including the Disney ARSP Properties. Proof of compliance with this measure shall be submitted to the Cit
y Traffic Engineer.

Public Works
Department, Traffic
and Transportation
Division

MM TRA-10 Ongoing during
construction
If Anaheim Police Department or Anaheim TMC personnel are required to provide temporary traffic control services, the pr operty owner/developer shall reimburse the City, on a fairshare basis, if applicable, for reasonable costs associated with such services.

Police Department;
Public Works
Department, Traffic
and Transportation
Division

MM TRA-11 Ongoing during project
operations
The property owner/developer will establish an onsite public information office (which is conveniently and accessibly located) where construction scheduling and phasing information will be available to the public. The public information office shall be open during construction hours. A telephone "hotline" will be provided to the community to allow members of the public to call the office with questions or comments during business hours. At least one liaison officer will be staffed at the office. The liaison officer shall be available to answer questions from the public and shall coordinate with the City of Anaheim, other public agencies, and major developers in the area regarding the coordination of construction activities and infrastructure improvements. The City shall be provided with a monthl
y summary of the calls received and follow-up actions.

Public Works
Department, Traffic
and Transportation
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-48 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM TRA-12 Prior to issuance of each
building permit for The
Disneyland Resort or, any
other timing specifically
provided in this measure
The property owner/developer shall submit a Traffic Mitigation and Construction Phasing and Control Plan. To the extent ne eded, as determined by the Public Works Department, the Traffic Mitigation and Construction Phasing and Control Plan shall identify the following:
a. A Construction Staging Area Plan showing the location and size of the construction staging area. The Plan shall also show how the staging area will be screened from view in compliance with the Cit
y of Anaheim Municipal Code.

Public Works
Department, Traffic
and Transportation
Division

MM TRA-13 Prior to approval of each
grading plan or issuance of
each demolition or building
permit, whichever occurs
first; implemented during
grading and construction
A Truck Route Plan identifying truck routes along arterials, avoiding residential areas to the extent feasible and in compliance with the Sound Pressure Level Ordinance. The Plan shall show conformance with the external noise limits for construction between 7 p.m. and 7 a.m. The Plan shall also prohib it construction traffic on residential streets where improvements are not planned and shall provide measures to ensure that truck drivers are directed away from residential st reets and travel on approved routes only.

Measures to assist in guiding truck movement on the arterial roadway system include, but are not limited to, provision of truck route maps to truck drivers and placement of flagpersons and construction signage at appropriate locations. The Truck Route Plan shall provide for monitoring of street conditions and potential repairing and/or repaving by property owner/developer after completion of construction as required by the City En
gineer.

Public Works
Department, Traffic
and Transportation
Division

MM TRA-14 Prior to approval of each
grading plan or issuance of
each demolition or building
permit, whichever occurs
first; implemented during
grading and construction
A Construction Traffic Management Plan which includes mechanisms to reduce construction-related traffic congestion which shall be implemented during grading and construction, including, but not limited to, the following:

1. Configure construction parking to minimize onsite and offsite traffic interference.

2. Minimize obstruction of through-traffic lanes.

3. Provide fla
gpersons to guide traffic, as determined in the plan.

Public Works
Department, Traffic
and Transportation
Division

MM TRA-15 Prior to approval of each
grading plan or issuance of
each demolition or building
permit, whichever occurs
first; implemented during
construction
A Trip Reduction Plan for construction crew vehicles shall be prepared to reduce potential vehicle trips on the road and identify parking locations for construction employees and equipment.

Public Works
Department, Traffic
and Transportation
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-49 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM TRA-16 Prior to approval of each
building permit
A Traffic Management Plan for phasing of roadway improvements, specifying the sequencing of construction to do the following:

1. Coordinate scheduling with other planned construction in the area.

2. Coordinate scheduling with other infrastructure improvements to allow them to be facilitated efficiently during roadway improvements, such as sewer, storm drain, and water line improvements.

3. Outline procedures for any required traffic detours during construction, including provision of tour bus stops.

4. Phase each roadway improvemen t to allow access to all existing businesses/residential areas. In some in stances this will require lane-by-lane renovation, temporary bypass roads, or traffic reroutes.

5. Employ vertical shoring as often as possible. This will minimize the amount of road surface that will be disturbed at a given location.

6. Sequence the construction of each roadway improvement to minimize disruption to residents and businesses.

7. Establish offsite parking and staging areas, where practical and possible, to minimize the impact to existing level of service on adjacent roadways. These offsite parking and staging areas will a llow a dispersion of traffic flow to noncritical areas and will encourage bu ssing of construction workers from the offsite areas to the construction sites.

8. Identify how the project improvement construction schedules and haul routes will be coordinated with other area wide improvements. The property owner/developer shall coordinate w ith the City of Anaheim Traffic Management Center (TMC), the Anaheim Convention Center and area hotels to ensure continued operations of these facilities, as well as the continued operation of The Disneyland Resort.

Public Works
Department, Traffic
and Transportation
Division

MM TRA-17 Ongoing during project
construction
The property owner/developer shall submit a quarterly update report showing construction activities for the upcoming quarter which shall include traffic mitigation and control planning and construction scheduling.

Public Works
Department, Traffic
and Transportation
Division

MM TRA-18 Prior to approval of each
grading plan
The property owner/developer shall show how the project will be in compliance with the Traffic Mitigation and Construction Phasing and Control Plan.

Public Works
Department, Traffic
and Transportation
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-50 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM TRA-19 Prior to the issuance of the
first building permit
The location of any proposed gates across a driveway shall be subject to the review and approval of the City Engineer. Gates shall not be installed across any driveway or private street in a manner which may adversely affect vehicular traffic on the adjacent public streets. Installation of any gates shall conform to the current version of Engineering Standard Detail No. 475.

Public Works
Department, Traffic
and Transportation
Division

MM TRA-20 Prior to the issuance of
building permits
Plans shall show that all driveways shall be constructed with a minimum fifteen (15) foot radius curb returns as required by the City Engineer, unless otherwise approved by the City Engineer.

Public Works
Department, Traffic
and Transportation
Division

MM TRA-21 Prior to the issuance of
building permits or final
map approval, whichever
occurs first
Security in the form of a bond, certificate of deposit, letter of credit, completion guarantee, or cash, in an amount and form satisfactory to the City Engineer shall be posted with the City to guarantee the sa tisfactory completion of all engineering requirements of the City of Anaheim, including preparation of improvement plans and installation of all improvements, such as curbs and gutters, sidewalks, water facilities, street grading and pavement, sewer and drainage facilities and other appurtenant work, as required by the City Engineer and in accordance with the specifications on file in the office of the City Engineer, as may be modified by the City Engineer. Installation of said improvements shall occur prior to final buildin g and zoning inspections.

Public Works
Department,
Development Services
Division
MM TRA-22 Prior to approval of each
tentative tract or parcel map
The following Street Design Elements shall be shown on each tentative tract or parcel map:
a. Street cross-sections, including dimensions, labels, circulation designation (i.e., Resort Secondary) and whether public or private.
b. Street grades and vertical alignment.
c. Horizontal ali
gnment, including radii, and cul-de-sac radii.

Public Works
Department,
Development Services
Division

Tribal Cultural Resources
MM TCR-1 Prior to the issuance of any
permits allowing ground-
disturbing activities that
cause excavation to depths
greater than current
foundations
Tribal Cultural Resources Monitoring. The property owner/developer or contractor as designee shall provide evidence in the form of an executed Agreement to the City of Anaheim Planning and Building Department that they have retained a qualified Native American tribal monitor to provide third-party monitoring during construction- related ground disturbance activities and to r ecover and catalogue tribal resources as necessary. The tribal monitor shall be from or approved by the Gabrieleño Band of Mission Indians – Kizh Nation. The agreement shall include (i) professional qualifications of Native American monitor; (ii) detailed scope of services to be provided includin g but not limited to pre-construction education, observation, Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-51 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
evaluation, protection, salvage, notification, and/or curation requirements, as applicable, with final documentation/report to Public Works Inspector; (iii) contact information; (iv) communication protocols between Contractor and Monitor for scheduling to facilitate timely performance; (v) acknowledgment that if the tribal monitor is unavailable or unresponsive based on terms stipulated in the agreement, property owner/developer or contractor as designee may contract with another qualified tribal monitor acceptable to th e City. The selection of the qualified professional(s) shall be subject to City acceptance based on generally accepted professional qualifications and certificatio ns, as applicable. The cover sheet of the grading plans shall include a note to identify that third party tribal monitoring is required during excavation and grading activities in accordance with the City-approved Agreement. Contact information for approved tribal monitor shall be provided by the contractor to the Cit
y inspector at the pre-construction meeting.

SR TCR-1 Prior to approval of any
amendment to the ARSP or
the City of Anaheim
General Plan
The project property owner/developer shall coordinate with the City Planning Department to undergo a solicitation of Native American consultation pursuant to Senate Bill (SB) 18 (California Government Code, Section 65352.3).

Planning & Building
Department, Planning
Services Division

Utilities and Service Systems
Public Services and Utilities - Water
MM UTIL-1 Prior to issuance of building
permits
Among the water conservation measures to be shown on plans and implemented by the property owner/developer within the Specific Plan area include the following:
• Use of low-flow sprinkler heads in irrigation system. • Use of waterway re-circulation systems.
• Low-flow fittings, fixtures, and equipment, including low flush toilets and urinals.
• Use of self-closing valves on drinking fountains.
• Use of reclaimed water for irrigation and washdown when it becomes available. • Continuation of the existing cooling tower recirculation system. • Use of efficient irrigation systems such as drip irrigation and automatic systems which use moisture sensors.
• Low-flow shower heads in hotels.

Utilities Department,
Resource Efficiency
Section; Planning &
Building Department,
Building Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-52 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
• Water-efficient ice machines, dishwasher s, clothes washers, and other water- using appliances.
• Use of irrigation systems primarily at night when evaporation rates are lowest. • Provide information to the public in conspicuous places regarding water conservation.
• Use of water-conserving landscape plant materials wherever feasible. • Use of vacuum and other equipment to reduce the use of water for washdown of exterior areas.

MM UTIL-2 Prior to each final building
and zoning inspection
The property owner/developer shall submit a certified water audit for landscape irrigation systems except for areas within the Theme Parks.

Utilities Department,
Resource Efficiency
Section

MM UTIL-3 Prior to issuance of each
building permit
All water supply planning for the project will be closely coordinated with, and be subject to the review and final approval of, the Public Utilities Department, Water Engineering Division and Fire Department.

Utilities Department,
Water Engineering
Division; Fire
Departmen
t

MM UTIL-4 Prior to issuance of each
building permit
Water pressure greater than 80 pounds per square inch (psi) shall be reduced to 80 psi or less by means of pressure reducing valves installed at the property owner/developer’s service.

Utilities Department,
Water Services

MM UTIL-5 Prior to issuance of building
permits
Plans shall specifically show that the wa ter meter and backflow equipment and any other large water system equipment will be in stalled to the satisfaction of the Public Utilities Department, Water Engineering Division, aboveground and behind the building setback line in a manner fully screened from all public streets and alleys and in accordance with Ordinance No. 4156. Prior to the final building and zoning inspections, the water meter and backflow equipment and any other large water system equipment shall be installed to the satisfaction of the Public Utilities Department, Water En
gineering Division, in accordance with the building permit plans.

Utilities Department,
Water Services

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-53 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM UTIL-6 Prior to final building and
zoning inspections
A separate water meter shall be installed for landscape water on all projects where the landscape area exceeds 1,000 square feet for non-residential uses in accordance with Ordinance No. 6160.

Utilities Department,
Water Services

MM UTIL-7 Ongoing during project
development and operations
The property owner/developer shall implem ent the following required improvements to the water supply system, in accordan ce with Anaheim’s Water Rates, Rules and Regulations, Water Services Administrative Procedures and Design Guidelines (APDG), and Water Services Standard Specifications (WSSS), within the timeframes described below or as further determined by the Public Utilities Department, Water Engineering Division. The cost of all Main Extensions, Main Enlargements, abandonments, relocations, and easements documents shall be paid for by the property owner/developer of the properties served by these mains in accordance with Rule 15A. • In the Theme Park District, west of Disneyland Drive, all new fire water connections, including but not limited to, those that would serve, private fire hydrants, in The Disneyland Resort shall be made to water mains served by the 335 Pressure Zone. Specifically, no new fire water connections are permissible on existing water mains in Walnut Street or Magic Way. Any new fire connections for buildings ad jacent to these mains sha ll connect to the 20-inch water main in Disneyland Drive.
• The Southeast District shall be served by at least two points of connection with internal looping.
o Any new water service connections along Harbor Boulevard shall require the construction of a 12-inch water main from Convention Way intersection to a point approximately 400-ft north of the intersection. o Any new connection to the existing water main in Clementine Street, north of Orangewood Avenue, shall require replacement of the existing 8-inch water main with a new 12-inch water main.
• Abandon the existing 12-inch water main within the Esplanade between Harbor Boulevard and Disneyland Drive. This work shall be completed concurrently with any proposed improvements along Disneyland Drive or Harbor Boulevard. • New easements may be required where public water infrastructure are located within private property through abandonment(s) of a public right-of-way. Such easements shall limit improvements that impact access for operation and maintenance of existing facilities. Alternatively, the property owner/developer may abandon and/or relocate existing public water infrastructure provided the property owner/developer prepares an analysis to determine any associated and Utilities Department,
Water Services

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-54 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
appropriate improvements due to the work. The property owner/developer shall submit the analysis and any associated improvement plans to the Public Utilities Department, Water Engineering Division for review and approval. • Prior to issuance of building permits, the property owner/developer shall submit hydraulic analyses to determine the adequacy of existing and proposed facilities if required by the Public Utilities Department, Water Engineering Division.

Public Services and Utilities – Wastewater/Sewer
MM UTIL-8 Prior to issuance of any
Building Permit for any new
hotel development within
the Theme Park District that
proposes a portion or the
entirety of the hotel
project’s sewer flow to
discharge to the City sewer
system on Harbor
Boulevard, north of Katella
Avenue
The property owner/developer shall prepare a Sewer Study for review and approval by the City Engineer, funded by the property owner/developer. Said Sewer Study shall evaluate whether there is adequate capacity in the Harbor Boulevard sewer system to accept the flow from the proposed new hote l use. The Sewer Study shall determine whether the proposed hotel project would create a deficiency in the Harbor Boulevard sewer system or the downstream City sewer system. If the Sewer Study shows there would be deficiency in the Harbor Boulevard sewer system or the downstream sewer system, the Sewer Study shall identify the required sewer system upgrades. If a sewer system upgrade is required, the property owner/developer shall be responsible for the design and construction of the upgrade to the sewer system and all associated improvements [collectively, “Sewer Im provements”]. The City-identified and approved cost of the Sewer Improvements may be credited toward the applicable sewer impact fees for the hotel project upon completion of the Sewer Improvements and acceptance by the City. The design of the Sewer Improvements and the related sewer improvement plans shall be completed prior to issuance of any Building Permit for the hotel project and the sewer improvemen t plans shall identify all associated improvements required for the required Sewer Improvements. Construction of Sewer Improvements shall be completed prior to final building and zoning inspections for the hotel. If no sewer system upgrade is required, the developer shall be required to pay the applicable sewer impact fees, pursuant to A.M.C. 10.12.085, with applicable credits applied for sewer flows from existin
g uses to be removed.

Public Works
Department,
Development Services
Division and Design
Division

MM UTIL-9 Prior to issuance of a
plumbing permit resulting in
a cumulative flow of more
than 50 gpm peak in the
Theme Park District
resulting in redirected
existing sewer flows that
currentl
y do not flow to
The property owner/developer shall prepare a Sewer Study for review and approval by the City Engineer, funded by the property owner/developer. Said Sewer Study shall evaluate whether there is adequate capacity in the Harbor Boulevard sewer system to accept the proposed redirected flow. The Sewer Study shall determine whether the proposed redirected flow wo uld create a deficiency in the Harbor Boulevard sewer system or the downstream City sewer syst em. If the Sewer Study shows there would be deficiency in the Harbor Boulevard sewer system or the downstream sewer system, the Sewer Study shall identify the required sewer system upgrades. If a sewer system Public Works
Department,
Development Services
Division and Design
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-55 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
Harbor Boulevard to instead
flow to Harbor Boulevard
via non-gravity flow (e.g.
lift station, force main,
ejector pump, etc.)
upgrade is required, the property owner/developer shall be responsible for the design and construction of the upgrade to the sewe r system and all associated improvements [collectively, “Sewer Improvements”]. The City-identified and approved cost of the Sewer Improvements may be credited toward the applicable sewer impact fees for the hotel project upon completion of the Sewer Improvements and acceptance by the City.

The design of the Sewer Improvements and the related sewer improvement plans shall be completed prior to issuance of any Building Permit for the hotel project and the sewer improvement plans shall identify all associated improvements required for the required Sewer Improvements. Construc tion of Sewer Improvements shall be completed prior to final building and zoning inspections for the hotel. If no sewer system upgrade is required, the developer shall be required to pay the applicable sewer impact fees, pursuant to A.M.C. 10.12.085, with applicable credits applied for sewer flows from existin
g uses to be removed.

MM UTIL-10 Prior to issuance of the first
building permit for
development of over 10,000
sf in the Southeast District
or Theme Park East Overlay
The property owner/developer shall prepare a Sewer Study for review and approval by the City Engineer, funded by the property owner/developer. Said Sewer Study shall evaluate whether the total sewer flow proposed to the Katella Avenue sewer system, east of Harbor Boulevard, for development authorized by the DisneylandForward project for the Theme Park East Overlay/ Southeast District does not exceed a peak flow of 285 gpm. And that the total sewer flow proposed to be directed to the Harbor Boulevard sewer system, south of Katella Avenue, for development authorized by the DisneylandForward project for the Theme Park East Overlay/Southeast District does not exceed a peak flow of 2,000 gpm (total allowable development within Theme Park East Overlay/Southeast Distri ct). If the projected sewer effluent flow exceeds these stipulated amounts for either the Katella Avenue or Harbor Boulevard sewer system, the Sewer Study shall determine whether the development project creates a deficiency in the Katella Avenue sewer system, east of Harbor Boulevard, or the Harbor Boulevard sewer system, south of Katella Avenue, sewer collections systems and the downstream City sewer system. Should a deficiency be created, the Sewer Study shall identify the required sewer system upgrades and improvements (“Sewer Improvements”). If Sewer Improvements are required, the property owner/developer shall be responsible for the design and construction of the Sewer Improvements. The City-identified and approved cost of the sewer improvements may be credited toward the applicable sewer impact fees for the development project upon completion of the Sewer Improvements and acceptance by th e City. The design of the Sewer Improvements and the sewer improvement plans shall be completed prior to issuance of any Building Permit for development in the Theme Park East Overlay/Southeast District and shall identif
y all associated improvements required for the required Sewer Public Works
Department,
Development Services
Division and Design
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-56 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
Improvements. Construction of Sewer Improvements shall be completed prior to the first final building and zoning inspection for development within the Theme Park East Overlay/Southeast District. If no improvement is required, the developer shall be required to pay the applicable sewer impact fees, pursuant to A.M.C. 10.12.085.

MM UTIL-11 Prior to issuance of any
Building Permit for any new
hotel development within
the Parking Overlay
(between Harbor Boulevard
and Manchester Avenue)
The property owner/developer shall prepare a Sewer Study for review and approval by the City Engineer, funded by the property owner/developer. Said Sewer Study shall evaluate the sewer flow from the hotel(s) directed to Clementine Street and ultimately Katella Avenue. Sewer improvements required to address deficiencies in the sewer systems in Clementine Street and/or Katella Avenue, east of Harbor Boulevard, shall be the sole responsibility of the property owner/developer (“Clementine and Katella Sewer Improvements”). Should a deficiency be created, the Sewer Study shall identify the required sewer system upgrades and im provements. If a sewer system upgrade is required, the property owner/developer shall be responsible for the design and construction of the Clementine and Katella Sewer Improvements and all associated improvements. The City-identified cost of the Clementine and Katella Sewer Improvements may be credited toward the applicable sewer impact fees for the hotel project(s) upon completion of the Sewer Improvements and acceptance by the City.

The design of the Clementine and Katella Sewer Improvements and the sewer improvement plans shall be completed prior to issuance of any Building Permit for the hotel project(s) and identify all associated improvements required for the Sewer Improvements. Construction of sewer improvements shall be completed prior to issuance of the first certificate of occupancy for the first hotel development. If no improvement is required, the developer shall be required to pay the applicable sewer impact fees, pursuant to A.M.C. 10.12.085.

Public Works
Department,
Development Services
Division and Design
Division

Public Services and Utilities – Storm Drains
MM UTIL-12 Prior to approval of a final
subdivision map, or
issuance of a grading or
building permit, whichever
occurs first
The property owner/developer shall participate in the City’s Master Plan of Storm Drains and related Infrastructure Improveme nt (Fee) Program to assist in mitigating existing and future storm drainage system deficiencies as follows:

The property owner/developer shall submit a report for review and approval by the City Engineer to assist with determining the following:
a. If the specific development/redevelopment does not increase or redirect current or historic storm water quantities/flows, then the property owner/developer’s responsibility shall be limited to participation in the Infrastructure Improvement (Fee) Program to provide storm drainage facilities in 10- and 25-year storm frequencies and to protect properties/structures for a 100-year storm frequency.

Public Works
Department,
Development Services
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-57 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
b. If the specific development/redevelopment increases or redirects the current or historic storm water quantity/flow, then the property owner/developer shall be required to guarantee mitigation to the satisfaction of the City Engineer and City Attorney’s office of the impact prior to approval of a final subdivision map or issuance of a grading or building permit, whichever occurs first, pursuant to the improvements identified in the Master Plan of Drainage for the South Central Area. The property owner/developer shall be required to install the storm drainage facilities as recommended by the Master Plan of Drainage for the South Central Area to provide storm drainage facilities for 10- and 25-year storm frequencies and to protect properties/structures for a 100-year storm frequency prior to acceptance for maintenance of public improvements by the City or final building and zoning inspection for the building/structure, whichever occurs first.

Additionally, the property owner/developer shall participate in the Infrastructure Improvement (Fee) Program as determined by the City Engineer which could include fees, credits, reimbursements, or a combination ther eof. As part of guaranteeing the mitigation of impacts on the storm drainage system, a storm drainage system improvement phasing plan for the project shall be submitted by the property owner/developer to the City Engineer for review and approval and shall contain, at a minimum, (1) a layout of the complete system; (2) all facility sizes, including support calculations; (3) construction phasing; and, (4) construction estimates.

MM UTIL-13 Prior to the issuance of
building permits
The City shall require that building plans indicate that new developments will minimize stormwater and urban runoff into drainage facilities by incorporating design features such as detention basins, on-site water features, and other strategies.

Public Works
Department,
Development Services
Division

Public Services and Utilities – Electricity
MM UTIL-14 Prior to issuance of each
building permit; to be
implemented prior to each
final building and zoning
inspection
In order to conserve energy, the Disneyland Resort shall comply with the California Energy Code (Title 10), which may include the following:
• Consultation with the City energy-conservation experts at the Anaheim Public Utilities Community and Sustainability Division for assistance with energy- conservation design features.
• Use of high-efficiency air conditioning systems, connected if feasible to a computerized central energy management system, and meeting all control, scheduling and load efficiency requirements of the California Energy Code (Title 24, Building Efficiency Standards).

Utilities Department,
Resource Efficiency
Section

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-58 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
• Use of electric high-effici ency (NEMA) motors intended to conserve energy. • While recognizing the unique lighting apparatus required for some theme park uses, use of motion sensing lightswitch devices and light-emitting diode (LED) energy-efficiency lighting fixtures for indoor and outdoor lighting when feasible, T8 lamps, metal hallide and/or high-pressure sodium (HID) lamps. • Incorporation of electric vehicle char gers into parking structures.

MM UTIL-15 Prior to issuance of a
building permit
If the property owner/developer incorporates grid-tied renewable energy generation systems into the project, they shall comply with the Anaheim Public Utilities Department’s most recent Interconnection Guidelines.

Utilities Department,
Resource Efficiency
Section

MM UTIL-16 Two to five years prior to
energizing new switching
stations
The property owner/developer shall provide Anaheim Public Utilities Department electrical engineering staff with its forecasted electric demand and schedules to allow for sufficient lead time for planning, design, engineering, materials procurement, and construction of new electrical facilities, if required, to accommodate the Project’s additional or modified electrical demand. Forecasts must be at least two to five years:
e.g., two years for the construction of up to two line extensions and five years for the construction of three line extensions or a new substation.

Utilities Department,
Electric Services
Division

Public Services and Utilities – Natural Gas
As discussed in Draft Subsequent EIR No. 352, Section 5.16, Utilities and Service Systems, Natural Gas, incorporates MMs Section 5.5, Energy.

Public Services and Utilities – Solid Waste
MM UTIL-17 Ongoing during theme park
operations and prior to final
building and zoning
inspections of new theme
park development
The property owner/developer shall implement a solid waste management plan which has been reviewed and approved by the Public Works Department to ensure that the project plans comply with AB 939, SB 1383 related to reducing organic waste in landfill, the Solid Waste Reduction Act of 1989, as administered by the City of Anaheim, and the County’s and City’s Integrated Waste Management Plans.

Implementation of said plan shall commence upon occupancy and shall remain in full effect as required by the Street and Sanitation Division and may include the following plan components:
a. Detailing the locations and design of on-site recycling facilities. b. Providing on-site recycling recep tacles to encourage recycling. c. Complying with all Federal, State, an d City regulations for hazardous material disposal.
d. Continuing participation in the City of Anaheim’s voluntary “Recycle Anaheim,” program or other substitute program as may be developed by the City.

Public Works
Department, Streets
and Sanitation Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-59 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
In order to meet the requirements of the Solid Waste Reduction Act of 1989 (AB 939), the property owner/developer shall implement numerous solid waste reduction programs at the Disneyland Resort, including:
• Facilitating paper recycling by providing chutes or convenient locations for sorting and recycling bins.
• Facilitating cardboard recycling (especia lly from retail areas) by providing adequate space and centralized locations for collections and baling. • Facilitating glass recycling (especially fr om restaurants) by providing adequate space for sorting and storing.
• Providing trash compactors for nonrecyc lable materials whenever feasible to reduce the total volume of solid waste a nd the number of trips required for collection.
• Prohibition of curbside pic k-up within The Disneyland Resort.

MM UTIL-18 Ongoing during project
operation
The existing solid waste recycling and waste minimization practices at The Disneyland Resort shall be expanded as feasible to serve new development in The Disneyland Resort. Existing practices include:
• Usage of recycled paper products for stationary, letterhead, and packaging. • Recovery of materials such as aluminum and cardboard. • Collection of office paper for recycling.
• Collection of polystyrene (foam) cups for recycling.
• Collection of glass, plastic, kitchen grease, laser printer, toner, cartridges, oil, batteries, and scrap metal for recycling or recovery.

Public Works
Department, Streets
and Sanitation Division

MM UTIL-19 Prior to issuance of building
permits

Ongoing during project
operation
Plans shall show that trash storage areas shall be provided and maintained in a location acceptable to the City of Anaheim Department of Public Works, Streets and Sanitation Division. On an ongoing basis, trash storage areas shall be provided and maintained in accordance with approved plans on file with said Department.

Public Works
Department, Streets
and Sanitation Division

MM UTIL-20 Prior to issuance of each
building permit
The property owner/developer shall demonstrate that the plans include provisions for the installation of trash and recycle receptacles near all benches and near high traffic areas such as plazas, transit stops and retail and dining establishments.

Planning & Building
Department, Planning
Services Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-60 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
MM UTIL-21 Ongoing during project
operation
Upon City request and no less than annually or more than semi-annually, the property owner/developer shall prepare and submit to the Planning & Building Director or their designee a consolidated Construction Waste Management Report for all development projects on Disney Properties demonstrating that at least 75 percent of non-hazardous construction and demolition debris has been recycled or salvaged, or has otherwise complied with the City’s waste diversion program, which Report shall identify the materials diverted from disposal and whether the materials have been sorted on site or co-mingled.

Planning & Building
Department, Planning
Services Division

Public Service and Utilities – Television
MM UTIL-22 Ongoing during project
operation
If the City of Anaheim determines that the proposed project creates a significant impact on broadcast television reception at local residences, the property owner/developer shall install a signal booster or relay system on the roof of the tallest project building to restore broadcast television reception to its original condition as soon as practicable.

Planning & Building
Department, Planning
Services Division

Public Services and Utilities – Standard Requirements
SR UTIL-1 Prior to the issuance of each
building permit
The property owner/developer shall be required to prepare and submit to the City for review and approval (1) a Landscape Docu mentation Package and (2) landscape and irrigation plans with appropriate water use calculations in accordance with the requirements of Anaheim Municipal Co de Chapter 10.19, Landscape Water Efficiency.

Planning & Building
Department, Planning
Services Division

SR UTIL-2 Prior to issuance of building
permits
The property owner/developer shall provide evidence to the Planning & Building Director or their designee that all sewage and wastewater disposal into the sewer system shall comply with OCSD’s Wastewater Discharge Regulations, including the procurement of the necessary permits by food service establishments that would be developed in the ARSP area.

Planning & Building
Department, Building
Division

SR UTIL-3 Prior to issuance of building
permits
The property owner/developer shall provide proof of payment to the Planning & Building Director or their designee for a sanitary sewer service charge to OCSD.

Planning & Building
Department, Building
Division

SR UTIL-4 Prior to issuance of building
permits
The property owner/developer shall provide proof of payment to the Planning & Building Director or their designee for a capital facilities connection charge to OCSD.

Planning & Building
Department, Building
Division

DisneylandForward
Final Subsequent EIR No. 352

R:\Projects\WDI\3WDI000400\Environmental Documentation\Final SEIR\Final_SEIR-022824.docx 4-61 Mitigation
Measure/Project
Design Feature
Number
Timing Measure Responsible for
Monitoring Completion
SR UTIL-5 Prior to issuance of building
permits
The property owner/developer shall be required to demonstrate to the Planning Department, Building Division that building plans meet the applicable Title 24 Energy Efficiency Standards for Residential and Nonresidential Buildings (24 CCR 6). These standards are updated, nominally every three years, to incorporate improved energy efficiency technologies and methods.

Planning & Building
Department, Building
Division

SR UTIL-6 Prior to issuance of building
permits
The property owner/developer shall be required to demonstrate to the Planning Department, Building Division that building plans meet the applicable California Green Buildin
g Standards (24 CCR11).

Planning & Building
Department, Building
Division