EXHIBIT A
Project: La Palma Park Way Promenade & Swan Street Improvements (RE-BID)
The project will convert North La Palma Park Way, from a two-way street, into a one-way tree- lined, pedestrian and bicycle friendly green corridor. Improvements on La Palma Park Way and Swan Street include new shade trees, flow through planters and drought-tolerant plantings. The project will not only enhance the pedestrian / vehicular / user experience in and around La Palma Park, but will also improve access to recreation, promote environmental stewardship, and improve pedestrian safety and connectivity throughout the area.
Work consists of asphalt concrete pavement resurfacing within the existing right-of-way, removal and reconstruction of ADA access ramps, curb and gutter, and concrete sidewalks, flow -through curb extensions, adjustment of utility structures, traffic stripi ng and pavement markings, signage and striping, monument sign, new landscaping and irrigation, decomposed granite, fencing, furnishings, and other appurtenant work.
Account No. 216-213-4727-9601
RCP2022-20230
LOWEST AND BEST RESPONSIBLE BIDDER: Griffith Company
12200 Bloomfield Avenue
Santa Fe Springs, CA 90670
PUBLICATION DATES: 5/9/2024 & 5/16/2024
BID OPENING DATE: 6/6/2024
PREVAILING WAGE RATE RESOLUTION NO: Per Current D.I.R. Publication
AWARD DATE: 7/16/2024
CONTRACT PRICE: $4,069,000
Four Million, Sixty Nine Thousand
Dollars and Zero Cents
CONTRACT COMPLETION DAYS: Eighty (80) Working Days
LIQUIDATED DAMAGES: One Thousand Five Hundred Dollars ($1,500) Per Day