RECOMMENDATION:
That the City Council, by Motion, award the construction contract to the lowest responsive and responsible bidder, Griffith Company, Santa Fe Springs, CA, Contractor’s License No. 88, Classification A, B, C-8, C-12, C-22, C-27, C-31, and HAZ, in the amount of $4,069,000, for the La Palma Park Way Promenade and Swan Street Improvements project (Re-Bid) (Project); authorize the Director of Public Works, on behalf of the City, to execute the Contract and any other related documents, and to take such actions as are necessary to implement and administer the Contract; direct and authorize the Finance Director to execute the Escrow Agreement pertaining to contract retentions, and determine the Project is categorically exempt under the California Environmental Quality Act (CEQA) pursuant to Sections 15301(b)(c)(d), 15304(b)(e)(f), and 15300.2(c). This project is identified as Class 1 (Existing Facilities) & Class 4 (Minor Land Alteration) pursuant to Title 14 of the California Code of Regulations.
DISCUSSION:
The Project will convert North La Palma Park Way from a two-way street into a one- way, tree-lined pedestrian and bicycle friendly green corridor. The Project will not only enhance the pedestrian, vehicular, and user experience throughout the area, but will also improve access to recreation and promote environmental stewardship. Improvements on La Palma Park Way and Swan Street include new shade trees and flow-through planters with drought-tolerant plantings. Work will also consist of asphalt pavement resurfacing, reconstruction of ADA access ramps, curb and gutter, installation of a new concrete sidewalk, traffic striping and pavement markings, monument sign, fencing, and furnishings.
The initial bids received in September 2023 resulted in prices that significantly exceeded the engineer’s estimate. Staff adjusted the scope of work to align it with the construction budget. Four bids were received in the re-bid.
Determination of the lowest responsive and responsible bidder for the selected Project scope was made in accordance with Public Contract Code 20103.8(d).
Award of Construction Contract for La Palma Parkway Promenade and Swan Street Improvements Project (Re-Bid) July 16, 2024
The bids are summarized as follows:
1. Griffith Company, Santa Fe Springs, CA .............................................$4,069,000.00
2. C.S. Legacy Construction, Inc., Walnut, CA.........................................$4,453,103.95
3. MBC Enterprises Inc., Huntington Beach, CA......................................$4,974,560.00
4. PUB Construction, Inc., Diamond Bar, CA...........................................$5,267,619.00 The selected bid price reflects the current bidding environment, appears to be reasonable, and is within the available funding. Construction is scheduled to begin in the 4th quarter of 2024 and is anticipated to be completed by the 1st quarter of 2025. Liquidated damages are set for $1,500 per day.
This project is in line with City’s Strategic Plan Goal C Invest in Infrastructure and Amenities, Strategy 11 - Review and implement the Parks Master Plan.
COMMUNITY WORKFORCE AGREEMENT (CWA):
This Project is covered “Project Work” as defined in the Amended and Restated Community Workforce Agreement (CWA) the City entered into with the Los Angeles / Orange Counties Building and Construction Trades Council and the Signatory Craft Councils and Local Unions.
ENVIRONMENTAL DETERMINATION:
The Department recommends that City Council determine that the Project is categorically exempt from CEQA pursuant to Sections 15301(b)(c)(d), 15304(b)(e)(f), and 15300.2(c). This project is identified as Class 1 (Existing Facilities) and Class 4 (Minor Land Alteration) pursuant to Title 14 of the California Code of Regulations.
IMPACT ON BUDGET:
Funding for this project is included in the Community Services Department’s FY 2024/25 Capital Improvement Program budget from Development Impact Fees, and through a State California Department of Transportation (Clean California) Grant.
Respectfully submitted, Concurred by, Rudy Emami Sjany Larson-Cash Public Works Director Community Services Director Attachments: