Project:
EXHIBIT A
Catch Basin Screen Installation Project – Phase 4
The work consists of retrofitting approximately 309 storm water catch basins citywide with Connector Pipe Screens (CPS) , full capture trash baskets (baskets), and automatic retractable screens (ARS). The project includes but is not limited to: survey and measurements of all catch basin locations, fabrication of the CPS trash capture devices, traffic control and installation of the CPS devices.
Account # 274-412-J745-7893, 592-412-J745-7893
RCP2024-22093
LOWEST AND BEST RESPONSIBLE BIDDER:
PUBLICATION DATES:
BID OPENING DATE:
PREVAILING WAGE RATES:
AWARD DATE:
CONTRACT PRICE:
CONTRACT COMPLETION DAYS:
LIQUIDATED DAMAGES:
G2 Construction, Inc. 1352
E. Borchard Ave
Santa Ana,
CA 92705
License #:
801253
7/18/2024, & 7/25/2024
8/15/2024
Per Current D.I.R.
Publication
September 24, 2024
Five hundred nine thousand
nine hundred eight dollars
and no cents ($509,908.00)
Seventy-five (75) Working
Days
Eight Hundred Dollars
($800) Per Day