EXHIBIT A
Project: Anaheim Resort Safety Bollards Project Phase II - Harbor Boulevard at Disney Way Intersection
The work includes installation of bollards, bollard frames, foundations, ADA compliant access ramps, sidewalk, curb and gutter, conduit, pull boxes, minor utility relocations, fencing, and all appurtenant work necessary for the proper construction of the proposed improvements, in accordance with the plans, specifications and contract documents. The goal of this project is to provide for additional safety and security for pedestrians at the intersection of Harbor Boulevard and East Shuttle Area.
Account No. 542-412-F791-7892
(RCP 2022-20548)
LOWEST AND BEST RESPONSIBLE BIDDER: Cali State Paving, Inc., 8207 Arlington Ave Unit #185
Riverside, CA 92503
PUBLICATION DATES: 9/19/2024, 9/26/2024 & 10/3/2024
BID OPENING DATE: 10/10/2024
PREVAILING WAGE RATES: Per Current D.I.R. Publication
AWARD DATE: 11/19/2024
CONTRACT PRICE: $863,930.00 Eight hundred sixty three thousand nine
hundred thirty dollars and no cents
CONTRACT COMPLETION DAYS: Construction 25 (Twenty Five) Working Days
LIQUIDATED DAMAGES: One Thousand Two Hundred Dollars
($1,200) Per Day