EXHIBIT A
P
roject: Installation of Protected Left Turn Signal Phasing at Four Intersections - Ball Road at Western Avenue, Orange Avenue at Western Avenue, Orange Avenue at Dale Avenue, and Broadway at Manchester Avenue
T
he work to be done consists of the upgrade of four (4) existing traffic signals for left-turn phasing operation improvements. This shall include installation of traffic signal poles; foundations; signal heads; signal controller and cabinet; conduit; pull boxes; conductors; accessible pedestrian signals; traffic signing; removal and reconstruction of ADA access ramps; concrete sidewalk and all additional work necessary to properly construct the proposed improvements, in accordance with the contract documents.
The goal of this project is to provide for the safe and efficient movement of vehicles and pedestrians at the project intersections.
A
ccount No.: 275-412-N854-7897, 271- 412-L268-7892, and 278-412-N853-7897 RCP2023-21388
LO
WEST AND BEST RESPONSIBLE BIDDER:
P
UBLICATION DATES:
B
ID OPENING DATE:
P
REVAILING WAGE RATES:
AW
ARD DATE:
CO
NTRACT PRICE:
Select Electric, Inc.
1700 E. Via Burton
Anaheim, California 92806
2/6/25, 2/13/25 & 2/20/25
2/27/2025
Per Current D.I.R. Publication
April 8, 2025
Two-Million Two Hundred
Forty Seven Thousand Five
Hundred Dollars and No Cents
($2,247,500.00)
C
ONTRACT COMPLETION DAYS: Sixty (60) Working Days
L
IQUIDATED DAMAGES: Three Thousand Two Hundred
Dollars ($3,200) Per Day