EXHIBIT A
PROJECT: Harbor Substation Line Extension Project Phase 1
SCOPE OF WORK: The work consists of installing 12kV substructures and electrical equipment along Disney Way east of Harbor Blvd and within Disneyland Resort.
Account No(s). 525-521-6768-7865-2400136-04
525-521-6768-7865-2400137-01
525-521-6768-7865-2400138-01
525-521-6768-7865-2400459-01
RCP2025-22706
PROJECT FUNDING SOURCE: Electric Utility Enterprise Funds
LOWEST AND BEST RESPONSIBLE BIDDER: Henkels & McCoy West, LLC 2840 Ficus Street
Pomona, CA 91766
PUBLICATION DATES: 3/20/2025 and 3/27/2025
PRE-BID MEETING 4/1/2025
BID OPENING DATE: 4/24/2025
PREVAILING WAGE RATE RESOLUTION NO: Per Current D.I.R. Publication
AWARD DATE: 6/10/2025
CONTRACT PRICE: Three Million Six Hundred Thirteen
Thousand Eight Hundred Twenty-Four
Dollars
($3,613,824.00)
CONTRACT COMPLETION DAYS: Two Hundred and Twenty (220) Working Days
LIQUIDATED DAMAGES: One Thousand Dollars ($1,000.00) Per Calendar Day