1. Proposed Five-Year Underground Conversion Plan for FY 2025/26 Projects List

Anaheim City Council
July 22, 2025

Document
1. Proposed Five-Year Underground Conversion Plan for FY 2025/26 Projects List
Meeting
July 22, 2025
Body
Anaheim City Council
Original file
77 KB
Text extracted from the city's file for reading and search. Open the original on local.anaheim.net. That file is the official record.

Attachment 1
(1) SCE undergrounding costs reimbursed from General Fund (2) Awarded partial funding through Federal Emergency Management Agency (FEMA) Proposed Five-Year Underground Conversion Plan
Fiscal Year 2025/26 Projects List
Projects Council
District
Constr.

Cost
($M)
Construction Schedule
Orangewood: Orangewood from Eugene
Street to Lewis Street
4 $9.2M
Undergrounding complete by
City and telecommunication
companies. Pole removals in
progress.

Santa Ana Canyon Rd: Santa Ana Canyon,
Lakeview to Imperial Highway 6 $11M
Undergrounding complete by
City and telecommunication
companies. Pole removals in
progress.

Beach: Beach Boulevard within City limits,
from Crescent Avenue to Ball Road
1 $27.2M(1) October 2023 – December 2025
Cerritos / Nutwood: Cerritos Avenue, from
Nutwood Street to Euclid Street, and on
Nutwood, from Ball Road to Katella Avenue
2 $17.5M May 2024 – May 2026
Wildfire Mitigation Undergrounding in
Fire Threat Zone (FTZ): Martella Lane, Del
Giorgio Road, Timken Road, Cooks Corner,
Country Hill Road, Oak Canyon Nature
Center Park near Walnut Canyon Road, and
the wilderness area north of Nohl Ranch Road
from Royal Oak to Anaheim Hills Road
6 $18.4M(2) June 2025 – November 2026
Olive / Vermont: Olive Street from South
Street to Vermont Avenue; Vermont Avenue
from Anaheim Boulevard to State College
Boulevard; and South Street from Anaheim
Boulevard to Olive Street
3, 4 $16M March 2026 – February 2028
La Palma / East: La Palma Avenue from
East Street to State College Boulevard 3, 5 $13.5M May 2027 – December 2028 Ball / Brookhurst: Ball Road from
Brookhurst Street to Euclid Street
2 $13.3M February 2028 – October 2029
Santa Ana / State College: Santa Ana Street
from Vine Street to State College Boulevard 3, 4 & 5 $10.2M August 2028 – December 2029 Attachment 1
(1) SCE undergrounding costs reimbursed from General Fund (2) Awarded partial funding through Federal Emergency Management Agency (FEMA) Projects Council
District
Constr.

Cost
($M)
Construction Schedule
La Palma / Sunkist: La Palma Avenue from
State College Boulevard to 57 Freeway;
Sunkist Street from La Palma Avenue to
Lincoln Avenue and on Miraloma Avenue;
and Sunkist Way to Romneya
5 $18.8M June 2029 – May 2031
La Palma / Anaheim: La Palma Avenue
from Harbor Boulevard to Olive Street, and
on Anaheim Boulevard from La Palma
Avenue to Carl Karcher Way
3 $9.0M June 2030 – August 2031
Broadway: Broadway from Magnolia
Avenue to Dale Avenue
1 $5.3M February 2031 – January 2032
Nutwood / Ball: Nutwood Street from Ball
Road to Orange Avenue 2 $5.3M July 2031 – June 2032
Nohl Ranch / Nohl Canyon (Proposed):

Nohl Ranch Road from Black Oak Road to
Villa Real Drive, and on Nohl Canyon Road
from Santa Ana Canyon Road to Nohl Ranch
Road
6 $7.7M December 2031 – February 2033