EXHIBIT A
Project: Groundwater Treatment Plant Phase C Well Rehabilitation Project
Scope of Work: The work consists of rehabilitation of four (4) groundwater production wells within the City of Anaheim, including but not limited to, mechanical and chemical cleaning, redevelopment, liner installation, and pump/motor removal.
Account No: 502-521-3779-7865-240089601
LOWEST AND BEST RESPONSIBLE BIDDER: General Pump Company 159 N. Acacia St
San Dimas, CA 91773
PUBLICATION DATES: 8/14/25, 8/21/2025
BID OPENING DATE: 9/11/2025
PREVAILING WAGE RATES: Per Current D.I.R. Publication
AWARD DATE: 11/4/2025
CONTRACT PRICE: $6,598,689.00
Six million five hundred ninety-eight
thousand six hundred eighty-nine
dollars and no cents
CONTRACT COMPLETION DAYS: Three Hundred (300) Working Days
LIQUIDATED DAMAGES: Eight Hundred Dollars and Zero
Cents ($800) Per Day