Project: Catch Basin Screen Installation Project – Phase 5 The work consists of retrofitting approximately 498 storm water catch basins citywide with Connector Pipe Screens (CPS), full capture trash baskets (baskets), and Automatic Retractable Screens (ARS). The project includes, but is not limited to, survey and measurements of all catch basin locations, fabrication of the CPS trash capture devices, traffic control and installation of the CPS devices.
Account No. 274-412-J747-7893
RCP2025-23306
LOWEST RESPONSIBLE BIDDER: G2 Construction, Inc.
1352 E. Borchard Ave. Santa Ana, CA 92875
License #: 801253
PUBLICATION DATES: 9/18/2025 & 9/25/2025
BID OPENING DATE: 10/9/2025
PREVAILING WAGE RATE RESOLUTION NO: Per Current D.I.R. Publication AWARD DATE: 11/18/2025
CONTRACT PRICE: Six Hundred Eighty-One Thousand Seven
Hundred Thirty-Six and No Cents
(681,736.00)
CONTRACT COMPLETION DAYS: Seventy-five (75) Working Days LIQUIDATED DAMAGES: Eight Hundred Dollars ($800.00)
Per Day