Attachment 1
EXHIBIT A
Project: Park Substation Line Extension Project
Scope of Work: The work consists of installing 12,000 Volt substructures and associated electrical equipment along Santa Ana Canyon Road from Woodcreek Road to Gypsum Canyon Road in coordination with the Gypsum Canyon Memorial Park Development.
Account No(s). 528-521-6761-7865-2600461-01; 528-521-6761-7865-2600462-01; 525-521-2776- 7865-2500794-01
RCP2024-21762
Project Funding Source: Restricted Electric Utility Enterprise Funds. Project expenditures will be reimbursed by the developer.
LOWEST RESPONSIBLE BIDDER: Outsource Utility Contractor, LLC 17115 Alburtis Avenue
Artesia, CA 90701
PUBLICATION DATES: 2/5/2026 & 2/12/2026
PRE-BID MEETING 2/17/2026
BID OPENING DATE: 3/12/2026
PREVAILING WAGE RATE RESOLUTION NO: Per Current D.I.R. Publication AWARD DATE: April 7, 2026
CONTRACT PRICE: Four Million, Eight Hundred Seventy-Seven Thousand, Nine Hundred Thirty-Four
Dollars and Sixty Cents
($4,877,934.60)
CONTRACT COMPLETION DAYS: Two Hundred Forty (240) Working Days LIQUIDATED DAMAGES: One Thousand Dollars ($1,000.00)
Per Calendar Day