CITY COUNCIL AGENDA REPORT
City of Anaheim

DEPARTMENT OF PUBLIC WORKS
DATE: MAY 5, 2026
FROM: DEPARTMENT OF PUBLIC WORKS
SUBJECT: AWARD OF CONTRACT TO GUY F. ATKINSON

CONSTRUCTION, LLC FOR THE ORANGEWOOD AVENUE

BRIDGE WIDENING OVER THE SANTA ANA RIVER PROJECT
ATTACHMENT (Y/N): YES ITEM # 04
GOVERNMENT CODE § 84308 APPLIES: NO
RECOMMENDATION:

That the City Council, by Motion, award the contract to the lowest responsible bidder, Guy F. Atkinson Construction, LLC, of Costa Mesa, CA, Contractor’s License No. 1004388, Classification A, in the amount of $23,743,815, for the Orangewood Avenue Bridge Widening over the Santa Ana River Project (Project); authorize and direct the Director of Public Works, on behalf of the City, to execute the Contract and any other related documents, and to take such actions as are necessary to implement and administer the Contract; and authorize and direct the Finance Director to execute the Escrow Agreement pertaining to contract retentions.

DISCUSSION:

The bids are summarized as follows:

1. Guy F. Atkinson Construction, LLC, Costa Mesa, CA 92626................$23,743,815.00

2. Reyes Construction, Pomona, CA 91766.................................................$26,307,334.65

3. Beador Construction Company, Inc., Costa Mesa, CA 92626................$26,700,700.00

4. Steve P. Rados, Inc., Santa Ana, CA 92705 ...........................................$59,610,469.00 The Orangewood Bridge Widening Project is part of the City of Anaheim’s Platinum Triangle Implementation Plan (PTIP), Update #4 for Public Works Backbone Facilities Improvements, identified as a portion of Project 3D. The Project consists of construction of improvements to widen the existing Orangewood Avenue bridge over the Santa Ana River to the SR-57 Freeway to improve regional traffic circulation and multimodal access.

The work includes adding an additional westbound travel lane, constructing an improved sidewalk along the north side of the bridge, and completing bridge seismic retrofit improvements, along with reconstruction of roadway approaches to provide a consistent cross-section through the corridor.

Additional construction activities include drainage improvements, retaining walls, utility relocations, and work within the Santa Ana River channel, including bank stabilization, riprap placement, and restoration of disturbed areas. The Project also includes installation Award of Contract for the Orangewood Avenue Bridge Widening over the Santa Ana River Project May 5, 2026

Page 2 of 3 ends

of a new City of Orange water transmission main within the bridge extending to Eckhoff Street.

Traffic control and construction staging will be implemented to maintain access and minimize impacts during construction, and all work will be performed in compliance with applicable permits and regulatory requirements.

The City Council previously approved a Cooperative Agreement (AGR-10938) between the City of Anaheim and the City of Orange for the funding, design, right-of-way acquisition, permitting, and construction of the Orangewood Avenue Bridge Widening Project and the City of Orange water transmission main. Pursuant to the Cooperative Agreement, the City of Anaheim serves as the lead agency responsible for design, right-of-way acquisition, and construction. Upon completion of construction, the City of Orange will retain ownership and maintenance responsibility for the bridge structure and associated facilities.

The City of Orange is responsible for all costs associated with the design, construction, maintenance, and operation of its water transmission main from State College Boulevard to Eckhoff Street. This segment of water main will close a loop in the City of Orange’s public water system, thereby improving the overall reliability of their system.

The bid price was $23,743,815, reflects the current bidding environment, appears to be reasonable, and is within the available funding. Liquidated damages for this Project shall be $7,100 per calendar day.

Construction is scheduled to begin in the 2nd quarter of 2026 and should be completed by the 1st quarter of 2030.

This Project supports Anaheim’s Strategic Plan Goal C - Invest in Infrastructure and Amenities, Strategy No. 4 – “Improve, enhance, beautify and maintain major street corridors.” ENVIRONMENTAL DETERMINATION:

The Project is consistent with the previously certified Final Subsequent Environmental Impact Report (SEIR) No. 339 for the Revised Platinum Triangle Expansion Project. Addendum No. 9 to SEIR No. 339 evaluated the Project improvements, including the bridge widening and related infrastructure improvements. No further environmental review is required pursuant to CEQA Guidelines Section 15164.

COMMUNITY WORKFORCE AGREEMENT (CWA):

This Project is covered “Project Work” as defined in the CWA the City entered into with the Los Angeles/Orange Counties Building and Construction Trades Council and the Signatory Craft Councils and Local Unions.

IMPACT ON BUDGET:

Adequate funding is available from the Platinum Triangle Mello Roos Projects Fund in the department’s Fiscal Year 2025/26 budget. The City of Orange will fund its portion of the water main work.

Award of Contract for the Orangewood Avenue Bridge Widening over the Santa Ana River Project May 5, 2026

Page 3 of 3 ends

Respectfully submitted,
Rudy Emami
Director of Public Works