EXHIBIT A
Project: Residential Street Improvement Project – Monterey & Baker – Group 19 The work consists of rehabilitating the roadway by removing and reconstructing asphalt concrete, sidewalks, driveway approaches, curb & gutters, and ADA access ramps; application of slurry seal; installation of striping, pavement markings, and repainting curbs as well as the adjustments and/or replacement of public utilities (Water Valve Boxes, Sewer Manholes, Gas Valves, Etc.); distributing public notification; providing traffic control, and all appurtenant work as shown on the plans and delineated in the specifications.
Account Number(s): 282-412-L318-7710, 271-412-L318-7710, 282-412-L319-7710, 271-412- L319-7710, 101-412-3256-7710, 101-412-3258-7710, 592-412-3233-7710-Group19, 502-521- 3743-7865-260238301, 528-521-6768-7865-2300688-01, 202-213-1114-7710, 101-213-4171- 7710, 675-412-8255-7705-Hardscape, 283-412-3237-7710-Group19 LOWEST AND BEST RESPONSIBLE BIDDER: R.J. Noble Company
15505 E. Lincoln Ave.
Orange, CA 92865
PUBLICATION DATES: 4/2/2026 & 4/9/2026
BID DUE DATE: 4/30/2026
PREVAILING WAGE RATES: Per Current D.I.R. Publication
AWARD DATE: 6/9/2026
CONTRACT COST ESTIMATE: $8,123,983
(Eight Million One Hundred Twenty
Three Thousand Nine Hundred
Eighty Three Dollars)
CONTRACT COMPLETION DAYS: One Hundred Sixty (160) Working Days
LIQUIDATED DAMAGES: $11,000 Per Day