RESOLUTION NO. 2026-

A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF ANAHEIM ADOPTING THE FY 2026-27

PROJECT LIST FOR THE ROAD REPAIR AND
ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1 ), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 to address the significant multi-modal transportation funding shortfalls statewid e; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of our City are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and
WHEREAS, the City must adopt a list of all projects proposed to receive funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, in the City budget, which must include a description and the location of each project, a proposed schedule for the project's completion, and the estimated useful life of the improvement; and WHEREAS, the City will receive an estimated $9,718,323.00 in RMRA funding in FY 2026-27 from SB 1; and
WHEREAS, this is the tenth year in which the City is receiving SB 1 funding and will enable the City to continue essential road maintenance and rehabilitation projects for the public; and
WHEREAS, the City has obtained and considered public input into the City's project list; and
WHEREAS, the City used a Pavement Management System to develop the SB 1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the City's priorities for transportation investment; and WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate streets at four neighborhoods and fifteen arterial streets throughout the City in FY 2026-27; and WHEREAS, the SB 1 project list and overall investment in City's local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete street infrastructure, and using cutting-edge technology, materials and practices, will have significant positive benefits citywide.

NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of Anaheim does hereby resolve as follows:

1. The foregoing recitals are true and correct.

2. The City of Anaheim is adopting the list of projects attached hereto as Exhibit "A" planned to be funded with Fiscal Year 2026-27 with Road Maintenance and Rehabilitation Account Act revenues, which includes new and relisted projects.

3. The City of Anaheim hereby adopts the Fiscal Year 2026-27 project list in Exhibit "A." THE FOREGOING RESOLUTION is approved and adopted by the City Council of the City of Anaheim this ___ day of ________ , 2026, by the following roll-call vote:

AYES:

NOES:

ABSENT:

ABSTAIN:

CITY OF ANAHEIM
BY: ------------

MAYOR OF THE CITY OF ANAHEIM
ATTEST:

CITY CLERK OF THE CITY OF ANAHEIM
158145
Unit No.

Project
Tracker
ID#
PROJECT TITLE Estimated
Useful Life Project Description Project Location
Estimated Start
Date (Mo-Yr)
Estimated
Completion
Date (Mo-Yr)
Estimated Start
Date (Mo-Yr)
Estimated
Completion
Date (Mo-Yr)
L318 1313 Monterrey Neighborhood Street
Rehabilitation N/A N/A Jul-26 Dec-26 7-20 years
The project improvements include removing and reconstructing the pavement in the roadway, applying slurry seal, replacing damaged areas of concrete (sidewalk, curb and gutter, and access ramps), replacing signs, pavement striping and pavement markings. (District 2) - bordered by the I-5 Freeway to the north, Euclid Way to the east, Lincoln Avenue to the south, and Belinda Circle to the west
L319 1619 Baker Neighborhood Street
Rehabilitation N/A N/A Jul-26 Dec-26 7-20 years
The project improvements include removing and reconstructing the pavement in the roadway, applying slurry seal, replacing damaged areas of concrete (sidewalk, curb and gutter, and access ramps), replacing signs, pavement striping and pavement markings. (District 2) - bordered by Lincoln Avenue to the north, Gilbert Street to the east, Orange Avenue to the south, and Magnolia Avenue to the west
L266 4237 Harbor Boulevard Rehabilitation Jun-24 Apr-26 Sep-26 Nov-26 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 3) - Harbor Boulevard from Lincoln Avenue to North Street L298 5568 Ball Road Rehabilitation Apr-24 Aug-26 Apr-27 Sep-27 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings. (Partnership with Sewer)
(District 2) - Ball Road from Magnolia Avenue to Gilbert Street L302 5771 Magnolia Avenue Rehabilitation Nov-24 Jul-26 Dec-26 May-27 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 1) - Magnolia Avenue from Lincoln Avenue to La Palma Avenue
L303 5772 Orange Avenue Rehabilitation Nov-24 Jul-26 Dec-26 May-27 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 2) - Orange Avenue from Magnolia Avenue to Euclid Street L304 5768 Broadway Rehabilitation Nov-24 Jul-26 Jan-27 May-27 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 3) - Broadway from Euclid Street to Harbor Boulevard L305 5769 Manchester Avenue Rehabilitation Nov-24 Jul-26 Jan-27 May-27 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 4) - Manchester Avenue from City Limit (South) to Anaheim Boulevard
L306 5773 La Palma Avenue Rehabilitation Nov-24 May-26 Oct-26 Jan-27 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 5) - La Palma Avenue from White Star Avenue to Miller Street
L307 5774 Santa Ana Canyon Road
Rehabilitation Nov-24 May-26 Oct-26 Jan-27 10-20 years
Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 6) - Santa Ana Canyon Road from Imperial Highway to Fairmont Boulevard
L312 5794 Western Avenue Rehabilitation Feb-26 Sep-26 Mar-27 Jul-27 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 1) - Western Ave from City Limit (North) to City Limit (South)
EXHIBIT "A"
City of Anaheim
FISCAL YEAR 2026-27 PROJECT LIST FOR THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017 Pre-Construction Schedule Construction Schedule
PROJECTS ADOPTED IN FY 2025-26 AND CARRIED OVER (RELISTED) FOR FY 2026-27

Page 1 ends

Unit No.

Project
Tracker
ID#
PROJECT TITLE Estimated
Useful Life Project Description Project Location
Estimated Start
Date (Mo-Yr)
Estimated
Completion
Date (Mo-Yr)
Estimated Start
Date (Mo-Yr)
Estimated
Completion
Date (Mo-Yr)
Pre-Construction Schedule Construction Schedule

L313 5796 Anaheim Shores Drive Rehabilitation Nov-25 Oct-26 Mar-27 Jul-27 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 3) - Anaheim Shores Drive from La Palma Avenue to Euclid Street
L314 5799 Harbor Boulevard Rehabilitation Nov-25 Oct-26 Mar-27 Jul-27 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 3) - Harbor Boulevard from South Street to Lincoln Avenue & from North Street to City Limit (North)
L315 5805 Harbor Boulevard Rehabilitation Sep-25 May-26 Sep-26 Dec-26 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 4) - Harbor Boulevard from Chapman Avenue to Convention Way
L316 5807 Placentia Avenue Rehabilitation Sep-25 May-26 Sep-26 Dec-26 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 5) - Placentia Avenue from State College Boulevard to the SR-91 Bridge
L317 5809
Miraloma Avenue,Van Buren Street;
Coronado Street; Jefferson Street
Rehabilitation
Sep-25 May-26 Sep-26 Dec-26 10-20 years
Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings.
(District 6) - Miraloma Avenue (Miller Street to Van Buren Street); Van Buren Street (Miraloma Avenue to La Palma Avenue);
Coronado Street (Jefferson Street to Van Buren Street); Jefferson Street (Tustin Avenue to Miraloma Avenue)
L320 5848 Hilda Neighborhood Street
Rehabilitation N/A N/A May-27 Dec-27 7-20 years
The project improvements include removing and reconstructing the pavement in the roadway, applying slurry seal, replacing damaged areas of concrete (sidewalk, curb and gutter, and access ramps), replacing signs, pavement striping and pavement markings. (District 5) - bordered by Lincoln Avenue to the north, S Westgate Drive to the east, E Sugarwood Lane to the south, and State College Boulevard to the west
L321 5847 Tonia Neighborhood Street
Rehabilitation N/A N/A Jan-27 Jun-27 7-20 years
The project improvements include removing and reconstructing the pavement in the roadway, applying slurry seal, replacing damaged areas of concrete (sidewalk, curb and gutter, and access ramps), replacing signs, pavement striping and pavement markings. (District 2) - bordered by Katella Avenue to the north, S Ninth Street to the east, City limits to the south, and S Euclid Street to the west
L331 6016 Monte Vista Road and Roosevelt
Road Rehabilitation Nov-25 Jul-26 Dec-26 Mar-27 10-20 years Plans, Specifications, and Estimates are being prepared during the Pre-Construction period. The road rehabilitation work consists of cold planing, resurfacing the road with an asphalt concrete overlay, and the replacement of traffic striping, traffic signal loops, and pavement markings as well as damaged concrete improvements. (District 6) - Monte Vista Road from Weir Canyon Road to Roosevelt Street, Roosevelt Street from Monte Vista Road to Santa Ana Canyon Road, and Dream Street from Monte Vista Road to end of cul-de-sac
NEW PROPOSED PROJECTS LISTED FOR FY 2026-27

Page 2 ends