Project: Resort Area Sanitary Sewer and Roadway Widening Improvements Project The sanitary sewer improvements consist of constructing a new 21-inch VCP sewer line along Katella Avenue between Disneyland Drive and Harbor Boulevard. In addition, the existing 21-inch and 24-inch sewer will be replaced with a new 30-inch VCP sewer along Katella Avenue between Walnut Street and Harbor Boulevard. The project also includes roadway widening improvements between Disneyland Drive and Harbor Boulevard with a new fourth westbound traffic lane and a pedestrian sidewalk. Lastly, the project provides street rehabilitation with a 2-inch and 3-inch asphalt concrete pavement cold mill and overlay.
Account No. 592-412-ID00-7895, 270-412-KD08-7892, 541-412-3105-7701, 211-412-ID00-7895, 502- 521-3743-7865-260301301, 270-412-ID00-7895, 528-521-6767-7865-2600557-02, 283-412-L344-7892 RCP 2025-23000
LOWEST AND BEST RESPONSIBLE BIDDER: Boudreau Pipeline Corporation 436 N. Smith Ave.
Corona, CA 92878
PUBLICATION DATES: 7/2/2026, 7/9/2026, 7/16/2026, &
7/23/2026
BID OPENING DATE: 7/30/2026
PREVAILING WAGE RATES: Per current D.I.R. Publication
AWARD DATE: 8/11/2026
CONTRACT PRICE: $20,088,888.00
CONTRACT COMPLETION DAYS: Three Hundred and Twenty (320) Working Days
LIQUIDATED DAMAGES: Ten Thousand Dollars ($10,000)