C ITY OF A RROYO G RANDE G UIDELINES & S TANDARDS FOR H ISTORIC D ISTRICTS
CONSTRUCTION MATERIALS
This section provides examples of the most
commonly found building materials used in
the Village area of Arroyo Grande. There
are also examples of construction materials
under the Village Core and the Residential
sections specific to those areas.
All new projects shall use materials that fit
within the character of the Village (see
following examples). Using similar
materials or replicating these materials on
all projects and restorations will extend the
existing character extended throughout the
Village.
All restorations shall use materials that
match or complement the original structure
facilitating compatibility and preservation of
its character.
WEATHERBOARD OR CLAPBOARD
WOOD SIDING
Most of the original housing and a few of
the commercial buildings used horizontal
wood siding or vertical board and batten for
the exterior walls and trim of the buildings.
Wood siding gives the buildings a sense of
historic character, adding detail and texture.
CEMENT PLASTER
Cement plaster (including stucco) is not as
common as wood or brick, however some of
the commercial and residential buildings
within the Village have plaster exteriors.
Cement plaster buildings require detailing
that gives them a historic “Village” feel.
Buildings with plain plaster walls and no
ornamentation are not appropriate for The
Village.
YELLOW INDIGENOUS SANDSTONE
This type of stone is used on the old
I.O.O.F. Hall on Bridge Street and the Old
Brisco Hotel on East Branch Street. It is a
golden stone that is shaped in large irregular
chunks. The color of this natural stone adds
a warm variety and individuality to the area.
20 ATTACHMENT 8
C ITY OF A RROYO G RANDE G UIDELINES & S TANDARDS FOR H ISTORIC D ISTRICTS
BRICK AND STONE BLOCK
Brick and stone blocks are most common on
commercial buildings in the Village. Brick
is an old construction material that was used
in the late 1800s and early 1900s when the
bulk of the historic commercial buildings in
Arroyo Grande Village were built. The use
of exposed plain concrete block is not
permitted in the Historic Village Core
District.
WINDOW SASHES AND DOOR FRAMES
Doors should be made of wood or a material
that resembles an older style wooden door.
For commercial areas, large industrial style
glass doors and windows with metal frames
are not appropriate. Doors with wood trim
and windows with wood framing should be
used. Aluminum and other frames that have
a modern metal look are not appropriate for
the Village.
21
C ITY OF A RROYO G RANDE G UIDELINES & S TANDARDS FOR H ISTORIC D ISTRICTS
VILLAGE CORE DOWNTOWN
(VCD)
This section of the Guidelines and Standards
applies to all parcels in the Village Core
Downtown area and may also be applicable
within Community Facilities (including
Public Facilities and Parks), and Mixed Use
districts as shown on the Design Overlay
District Map.
An objective of the Village Core Downtown
area is to enhance and maintain a compact,
active street frontage with commercial uses
that attract pedestrians. A visual continuity
should be maintained through site design
and compatibility of scale and materials.
MIXED USES WITHIN THE DISTRICT
There are properties within the Village Core,
Mixed Use and Community Facilities
overlay districts that have residential
architectural styles, and are currently being
used as stores, shops, residences, or offices.
In order to preserve and enhance mixed use,
the character of any new building or
renovation shall be consistent with the
surrounding area.
EXISTING CHARACTER
Many of the Downtown district historic
commercial buildings were erected in the
period from 1885 to 1910, and represent a
variety of architectural styles. Although
building material and detail differ, there are
definite patterns that should be respected
and incorporated into new development and
renovation. Common elements of design
include façade height and structure, strong
pedestrian orientation, and attention to
ornamentation.
Similarity in Height, Mass and Scale
Most buildings are one or two stories high
and range from about eighteen to thirty feet
in height. The majority of the buildings in
the Village on Branch Street between Traffic
Way and Mason Street are also narrow as
well, which emphasizes their vertical
character.
The most common façade design is two
stories high, although some buildings use a
“false front” to achieve the impression of
height. This façade treatment, when used on
a relatively narrow building, stresses the
strong vertical elements in the structure and
creates an impressive image.
Buildings are also made to appear larger by
creating a series of attached facades, linking
several smaller structures to create the
appearance of one large building. These
techniques lead to a more impressive
appearance without losing pedestrian scale
or blocking views and light.
28
C ITY OF A RROYO G RANDE G UIDELINES & S TANDARDS FOR H ISTORIC D ISTRICTS Similarity of Material
Brick and stone masonry construction is
common, especially along Branch and
Bridge Streets. Although some exteriors
have been painted, such as the Olohan
Building, the buildings retain many
architectural details of “brick front”
construction. This was one of the most
popular storefront types of vernacular
design, and incorporated commercial
establishments on the ground floor with
storage, offices or living quarters on the
second level. An unusual vernacular style
that uses locally quarried yellow stone is
also found in the Village Downtown
district. The unifying element is the stone
itself, which calls for simplicity of
construction and ornamentation, but the
buildings using this material vary
significantly in design. Another common
material is wood siding, especially
clapboard or weatherboard.
Sense of Experimentation
Although similar architectural styles are
evident, and many elements are common,
there is no one predominant architectural
style, and elements are often combined in
creative ways. The historic character,
however, is maintained.
Pedestrian Orientation
Most commercial buildings have large
display windows and a main entrance that
faces the street, oriented to pedestrian
traffic. There is no setback from the
sidewalk, and buildings are generally
designed and detailed to human scale,
contributing to an atmosphere where
pedestrians feel comfortable.
Variety in Building Form
There is sufficient variety in height, mass,
scale and proportion to create visual interest
in the Village Core Downtown Area. There
is also a mixture of uses that includes retail
establishments, cafes, restaurants and
offices, often within the same block.
DESIGN GUIDELINES AND STANDARDS
Mixed Use Projects Within the Village
Core Downtown
Mixed use projects within the Village Core
Downtown shall be predominantly
commercial in character. Upper story
residential and office uses designed to be
compatible with ground floor retail uses are
appropriate. Design of mixed use projects
shall not impede pedestrian flow or disrupt
concentration of retail, cultural and
entertainment uses.
The following building elements shall
NEITHER overpower the project or
detract from the visual continuity of the
streetscape or neighborhood NOR
produce redundancy in feature or pattern
that is discordant with the historic
character of the district:
• Building scale
• Building form
• Building façade
• Building entrance
• Roofline
• Fencing, rails or trellis
• Archways, columns or towers
• Doors and windows
• Signage or feature designed for sign
placement
• Colors
29
C ITY OF A RROYO G RANDE G UIDELINES & S TANDARDS FOR H ISTORIC D ISTRICTS Site Design
1. All new projects or renovations shall
adhere to the site development standards
of the Development Code.
2. The existing front setbacks of zero to
fifteen feet (0’ to 15’) shall be required
with main entries facing the street. A
majority of the building frontage shall
face the street and incorporate design
features oriented to the pedestrian.
3. Streetscape improvements shall
complement the existing design
sidewalk paving, lighting schemes and
street furniture within the district.
4. All enclosures for service areas, trash or
recycling containers shall be designed as
part of the overall project or building.
Materials, textures and colors should be
consistent with those of the proposed
project and compatible with adjacent
buildings.
5. Landscaping shall retain existing trees
and plants as much as possible. Street
trees and sidewalk planters shall be
incorporated where feasible and
pedestrian circulation will not be
obstructed. (Streetscape elements
within the public right-of-way, require
an Encroachment Permit from the Public
Works Department.) Landscaping in
parking areas shall conform to the
requirements of Title 16 of the
Municipal Code (Development Code).
Building Design
1. The height of new buildings shall not
exceed development standards allowed
in Title 16 of the Municipal Code. Scale
and massing of any building within this
area shall be consistent with that of the
neighboring buildings, as described
above in “Similarity in Height, Scale
and Massing”.
2. The existing pattern of building façades
shall be incorporated into new
development projects. Dominant façade
designs incorporate either brick front
elements or parapet features. Roof
patterns generally associated with
residential buildings such as gable, hip
or gambrel are generally not appropriate
for commercial building frontages in the
Village Core Downtown District.
3. For retail commercial buildings, display
windows should complement the design
of surrounding historic buildings and
shall be oriented to pedestrian traffic.
4. Transoms are common over display
windows, and were used for light and
ventilation. When possible, transoms
should be incorporated into new
building design, and existing transoms
should be used in building renovations.
5. New construction should include
elements such as cladding, roof structure
and ornamentation common to the
district. All new projects shall use
materials – including roof materials –
that fit within the character of the
Village Core Downtown district. By
using similar materials or replicating
these materials on all projects and
restorations, the existing character will
be reinforced and extended.
6. Decorative fixtures, including awnings,
signs, and lighting, shall be integrated
with other design elements of the
structures.
Construction Materials
1. Brick and stone masonry are the most
common façade materials used on
historic character structures in the
Village Core Downtown district, and are
acceptable façade materials. Some
brickwork has been painted, and this is
consistent with design style of the 1870-
1939 period.
30
C ITY OF A RROYO G RANDE G UIDELINES & S TANDARDS FOR H ISTORIC D ISTRICTS Other acceptable façade materials
include yellow sandstone (such as that
on the I.O.O.F. building), and wood
cladding. Wood cladding shall be of
painted clapboard, painted
weatherboard, or board and batten
styles.
Materials of similar design, color and
texture may be considered. Smooth
plywood panels are not appropriate
unless detailed for the historic period.
2. Window sashes shall be of wood or
painted steel, and consistent with the
historic period. Materials that
approximate the appearance of original
materials may be substituted subject to
the approval of the Architectural Review
Committee, but unfinished aluminum is
not allowed.
3. Door materials were traditionally wood
panel and glass, either single or double.
New or replacement doors shall be
wood or an approved substitute material
that approximates the appearance of
original materials. Aluminum entry
doors with large glass panels are
inappropriate for the Village Core
Downtown District.
4. Original decorative details should be
retained during renovation. If the
original materials have deteriorated and
must be removed, they shall be replaced
with materials that match as closely as
possible the original in design, color,
and texture.
5. Reflective glass is not appropriate in the
Village Core Downtown District.
Stained glass may be used as an accent
material if it is consistent with the
historic period of the building.
Building colors
1. The number of colors used on a building
should be kept to a minimum.
2. While bright colors may be used for
limited accent, their use is subject to
review by the Architectural Review
Committee (ARC).
3. Color samples shall be submitted as part
of Plot Plan Review or Conditional Use
Permit process.
4. The use of fluorescent, “neon” or “dayglo” colors on building facades is not appropriate, historic base colors should
be used instead.
5. Accent colors used for ornamentation,
awnings, dentils, friezes or other details
shall harmonize with the predominant
building color.
6. Color palettes shall complement the
majority of the neighboring buildings
and be consistent with the historic
period.
31
ATTACHMENT 9
Planning Commission-Recommended Alternative Ordinance
ORDINANCE NO.
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF ARROYO
GRANDE AMENDING TITLE 16 OF THE ARROYO GRANDE
MUNICIPAL CODE REGARDING THE ESTABLISHMENT OF A
PERMANENT PARKLET PROGRAM
WHEREAS, the City of Arroyo Grande (“City”) currently does not allow the placement of permanent parklets within the right of way; and
WHEREAS, the purpose of these regulations is to ensure that parklets within the right of way conform to the existing character of the area in which they are located and do not create an adverse impact on adjacent properties; and
WHEREAS, the Planning Commission finds that, unless properly regulated, parklets can result in similar adverse impacts to adjacent properties; and WHEREAS, the Planning Commission has considered the proposed Ordinance approving Development Code Amendment 22-003 at a duly noticed public hearing on September 6, 2022; and
WHEREAS, it is the purpose of the proposed Ordinance to protect the public health, safety, and welfare of residents within the City by establishing regulations for a permanent parklet program; and
NOW, THEREFORE, BE IT ORDAINED by the City Council of the City of Arroyo Grande as follows:
SECTION 1: The above recitals and findings are true and correct and incorporated herein by this reference.
SECTION 2: Arroyo Grande Municipal Code Section 16.52.250 is hereby added as follows:
SECTION 16.52.250 – PARKLETS
A. Purpose and Intent. The purpose and intent of these regulations is to ensure that parklets located in the City conform to the existing character of the area in which they are located and do not create an adverse impact on adjacent properties.
B. Application and Approval.
1. Operators of parklets within the right of way are required to obtain a Minor Use Permit - Plot Plan Review pursuant to AGMC 16.16.080, and an Encroachment Permit pursuant to AGMC Section 13.26.
2. Operators of parklets shall pay a parking space rental fee of 5% of the parking in-lieu fee for each space annually.
3. Operators of parklets shall pay a rental fee for City-owned safety barriers.
4. Upon vacation by a parklet operator of the premises adjoining the parklet, the Minor Use Permit - Plot Plan will terminate.
ORDINANCE NO.
PAGE 2
5. Existing operators of temporary parklets shall have 90 days from the date of ordinance adoption (______) to submit an application for a permanent parklet and removal of an existing temporary parklet. All temporary parklets shall be removed within six months of the ordinance adoption date of ______.
C. Performance Standards and Conditions.
Location
1. A parklet shall only be located in designated on-street parking areas.
2. A parklet shall not block sight distance at intersections or driveways.
Accordingly, a parklet shall not be located less than twenty-five feet (25’) from a roadway intersection, adjacent driveway, or other points of off-street access which require line of sight standards as required by the City’s Engineering Standards. The final location of a parklet will vary based on the proposed parklet design, and shall be subject to review and approval by the Community Development Director.
3. Parklets are prohibited in disabled parking zones, parking areas of thirty minutes or less, and no-parking zones.
4. A parklet may not cover or impede access to any utility equipment, utility pole, fire hydrant, parking permit kiosk, or utility access such as manhole covers, drainage inlets, stormwater drainage flow lines and equipment shelters, subject to review by the City Public Works Director and Fire Chief.
5. The parklet shall not extend beyond the building frontage of the business utilizing the parklet without written consent from the adjacent business.
Parklet Design
6. Parklets shall consist of no more than two adjoining parking spaces, or fortyfeet (40’) in length. When a parklet is shared by two or more businesses, the parklet length may be extended up to eighty (80) feet in length and no more than four adjoining parking spaces.
7. A parklet’s walls or railing shall not have a continuous height that exceeds fortytwo inches (42”) and shall not block views in or out of the parklet. Columns or other vertical framing for overhead elements are permitted. All elements of a parklet shall have a maximum height limit no higher than the first floor of the adjacent building. All parklets shall maintain a vertical walkway clearance height of at least eight feet (8’).
8. The depth (dimension measured perpendicular to curb) of a parklet shall be no less than the minimum dimension required to meet ADA accessibility requirements. Portions of the required parklet depth may be located within an existing sidewalk area as long as the sidewalk encroachment does not reduce the pedestrian path of travel to a width of less than four and a half feet (4.5’) in the public right of way.
9. A parklet shall include an element that ensures public safety by providing a barrier or fortified railing between moving vehicles and parklet users. These barriers shall either be well articulated or allow for plants or vegetation for screening.
ORDINANCE NO.
PAGE 3
10.Parklets shall have a flush transition at the sidewalk and curb to permit easy access and avoid tripping hazards.
11.A parklet shall comply with applicable Americans with Disabilities Act (ADA) accessibility standards. Compliance with ADA standards is required with respect to design elements of the parklet, as well as for adjacent areas that may be impacted by the parklet. Parklets shall use a slip-resistant flooring material to minimize hazards and shall be accessible to wheel-chair users.
12.The four corners of a parklet shall have a reflective element or other clearly visible design feature, such as a soft-hit post, bollard, or raised pavement marker, to illuminate the parklet at night and signify the parklet envelope.
13.Parklets shall be consistent with the Village Design Guidelines
14.The primary materials shall be stone, brick, wood, decorative concrete or composite wood. Wood materials such as lattice and T1-11 plywood siding, are prohibited.
15.Color schemes shall consist of one primary color and one secondary color unless natural wood is used.
16.Areas for the storage of trash, recycling, and green waste receptacles shall not be visible from the public right of way and all waste receptacles shall be emptied and maintained by the applicant in a neat and sanitary order.
SECTION 3: Arroyo Grande Municipal Code Section 16.04.070 is hereby amended as follows:
16.04.070 Definitions
“Parklet” means a small seating area created as a public amenity in a former roadside parking space utilized by a food service business for outdoor dining.
SECTION 4: If any section, subsection, subdivision, paragraph, sentence, or clause of this Ordinance or any part thereof is for any reason held to be unlawful, such decision shall not affect the validity of the remaining portion of this Ordinance or any part thereof.
The City Council hereby declares that it would have passed each section, subsection, subdivision, paragraph, sentence, or clause thereof, irrespective of the fact that any one or more section, subsection, subdivision, paragraph, sentence, or clause be declared unconstitutional.
SECTION 5: Upon adoption of this Ordinance, the City Clerk shall file a Notice of Exemption pursuant to 14 CCR § 15062.
SECTION 6: A summary of this Ordinance shall be published in a newspaper published and circulated in the City of Arroyo Grande at least five (5) days prior to the City Council meeting at which the proposed Ordinance is to be adopted. A certified copy of the full text of the proposed Ordinance shall be posted in the office of the City Clerk. Within fifteen (15) days after adoption of the Ordinance, the summary with the names of those City Council Members voting for and against the Ordinance shall be published again, and the City Clerk shall post a certified copy of the full text of such adopted Ordinance.
ORDINANCE NO.
PAGE 4
SECTION 7: This Ordinance shall take effect thirty (30) days from the date of adoption.
On motion of Council Member , seconded by Council Member , and on the following roll call vote to wit:
AYES:
NOES:
ABSENT:
The foregoing Ordinance was adopted this 6
th day of September 2022.
ORDINANCE NO.
PAGE 5
___________________________________
CAREN RAY RUSSOM, MAYOR
ATTEST:
___________________________________
JESSICA MATSON, CITY CLERK
APPROVED AS TO CONTENT:
___________________________________
WHITNEY McDONALD, CITY MANAGER
APPROVED AS TO FORM:
___________________________________
TIMOTHY J. CARMEL, CITY ATTORNEY
ATTACHMENT 10
DRAFT RESOLUTION NO.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
ARROYO GRANDE AMENDING THE MASTER FEE
SCHEDULE FOR THE COMMUNITY DEVELOPMENT
DEPARTMENT BY ESTABLISHING A NEW FEE FOR
PARKLETS
WHEREAS, on December 7, 2007 the City Council adopted Resolution No. 4060 approving a Citywide Master Fee Schedule; and
WHEREAS, on October , 2022 the City Council adopted an Ordinance to establish a permanent parklet program; and
WHEREAS, the purpose of these regulations is to ensure that parklets within the right of way conform to the existing character of the area and are secured by protective barriers to provide safety for its users; and
WHEREAS, the ordinance requires parklets to be located within the City right of way in off-street parking stalls and rental of City-owned barriers to secure the parklet; and WHEREAS, the costs of utilizing City right of way to establish a parklet and renting City owned protective barriers are to be offset by the operators of the parklet; and WHEREAS, the Master Fee Schedule does not include fees for use of City right-of-way or rental of City-owned barriers that are required by adopted permanent parklet program; and
WHEREAS, the City Council has considered the proposed fee structure for the permanent parklet program; and
WHEREAS, at a duly noted public meeting, the City Council considered all oral and written presentations that were made regarding the fees associated with permanent parklet program.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Arroyo Grande does hereby amend the Master Fee Schedule to update the fees and fee structure for the Community Development Department by adding fees related to the Permanent Parklet Program for Parking Space Rental and Protective Barrier Rental, as set forth in Exhibit “A” attached hereto and incorporated herein by this reference as though set forth in full.
On motion by Council Member _________, seconded by Council Member _______, and on the following roll call vote, to wit:
AYES:
NOES:
ABSENT:
The foregoing Resolution was passed and adopted this day of October, 2022.
RESOLUTION NO.
PAGE 2
__________________________________
CAREN RAY RUSSOM, MAYOR
ATTEST:
JESSICA MATSON, CITY CLERK
APPROVED AS TO CONTENT:
_________________________________
WHITNEY MCDONALD, CITY MANAGER
APPROVED AS TO FORM:
_________________________________
TIMOTHY J. CARMEL, CITY ATTORNEY
RESOLUTION NO.
PAGE 3
EXHIBIT ‘A’
City of Arroyo Grande
MASTER FEE SCHEDULE
COMMUNITY DEVELOPMENT DEPARTMENT
Fee Description
Parking Space Rental for Parklets (per space) per month $ 100.00 Protective Barrier Rental for Parklets (per barrier) per month $ 25.00
Item 11.a.
MEMORANDUM
TO: City Council
FROM: Whitney McDonald, City Manager
Timothy J. Carmel, City Attorney
SUBJECT: Discussion and Consideration of Approval of a Joint Exercise of Powers Agreement Creating the Central Coast Blue Regional Recycled Water Authority and Appointment of a Representative to the Authority Board of Directors
DATE: September 27, 2022
SUMMARY OF ACTION:
Approval of the proposed Joint Exercise of Powers Agreement Creating the Central Coast Blue Regional Recycled Water Authority (CCB JPA Agreement) (Attachment 1) with the cities of Grover Beach and Pismo Beach for the Central Coast Blue Project (Project).
Appointment of a Council representative to the CCB JPA Board of Directors will enable the JPA Board to meet before the City Council ordinarily makes committee appointments in December if necessary to address needs of granting or loaning agencies.
IMPACT ON FINANCIAL AND PERSONNEL RESOURCES:
The City’s Biennial Budget for Fiscal Years 2021-23 includes a total of $1,420,000 in the Water Availability Fund for the Central Coast Blue Project, $720,000 for Fiscal Year 2021- 22 and $700,000 for Fiscal Year 2022-23. The CCB JPA Agreement obligates the City to pay for 25% of the total costs of the Project consistent with the Cost Sharing Agreement approved by the City Council on January 25, 2022. The City of Pismo Beach will pay 39% of the costs and the City of Grover Beach will pay 36% of the costs. Total costs for the Project are currently estimated to be $92,595,000. To date, $17,120,000 in federal and State grants have been awarded to fund the Project. It is anticipated that the Project could receive an estimated $29,178,000 of additional federal and State grants, which would reduce these costs. The City’s portion of the estimated remaining $46,297,000 in Project costs is $11,574,250. It is anticipated that this amount would be financed through low interest loans provided by federal or State programs such as the Water Infrastructure Finance and Innovation Act (WIFIA) and/or the State Revolving Fund. In addition to the pre-construction and construction costs of the project, the three Cities will also support their share of operating and maintenance costs of the Central Coast Blue facility, which is currently projected to begin in 2026. The Water and Sewer Rate Study approved by
Item 11.a.
City Council
Discussion and Consideration of Approval of a Joint Exercise of Powers Agreement Creating the Central Coast Blue Regional Recycled Water Authority and Appointment of a Representative to the Authority Board of Directors September 27, 2022
Council on January 11, 2022 (Attachment 3), provides recommended water rates necessary to fund the City’s share of costs for the Project.
RECOMMENDATION:
1) Authorize the Mayor to execute a Joint Exercise of Powers Agreement Creating the Central Coast Blue Regional Recycled Water Authority (Authority); and 2) appoint a member of the City Council to the Authority Board of Directors BACKGROUND:
The City of Pismo Beach has been the lead agency for the Central Coast Blue Project.
The Project has been a multi-agency effort between three of the four Northern Cities Management Area agencies (the Cities of Arroyo Grande, Grover Beach, and Pismo Beach) and the South San Luis Obispo County Sanitation District1to construct a regional recycled water project that will enhance supply reliability by injecting advanced purified water into the Santa Maria Groundwater Basin. The Project will reduce vulnerability to drought and seawater intrusion by creating a seawater intrusion barrier and supplementing the naturally occurring groundwater.
At its January 25, 2022 meeting, the City Council authorized entering into a Cost Sharing Agreement with the cities of Grover Beach and Pismo Beach for the Project, as well as a Resolution that authorized the City Manager to apply for financial assistance from Clean Water State Revolving Fund administered by the State Water Resources Control Board for the City’s share of anticipated construction costs for the Project. A copy of the January 25, 2022 staff report related to the Cost Sharing Agreement is attached for reference (Attachment 2) and contains additional information regarding the process leading up to approval of that agreement, as well as information related to the financing for the Project.
The Cost Sharing Agreement also contained provisions related to the contemplated creation of a joint powers authority, which will be a separate legal public entity, pursuant to Government Code section 6500 et seq., that will own and operate the Project and have the power to issue debt and enter into loans or financing agreements to finance the construction costs for Phase 1 of the Project. As set forth in the Cost Sharing Agreement, the Joint Powers Agreement is to contain provisions addressing acquisition of the facility site from Pismo Beach by the Authority, ownership of the facility, and financing of construction costs, including repayment obligations of the parties consistent with the Water Purveyor Contribution percentages identified in the Cost Sharing Agreement. The CCB JPA Agreement has been negotiated by staff for the cities of Arroyo Grande, Pismo
1 Although it has contributed to the overall Project effort, the South San Luis Obispo County Sanitation District is not a party to the JPA during Phase I and will not be involved in the construction or initial operation of the Project.
Item 11.a.
City Council
Discussion and Consideration of Approval of a Joint Exercise of Powers Agreement Creating the Central Coast Blue Regional Recycled Water Authority and Appointment of a Representative to the Authority Board of Directors September 27, 2022
Beach and Grover Beach and is now being presented to the City Council for its consideration and approval.
On September 14, 2022, the first joint City Council meeting called for in the Cost Sharing Agreement was held with the City Councils of the cities of Arroyo Grande, Grover Beach, and Pismo Beach. At that meeting, the City Councils and the public received an update from the Project’s design and engineering consultant, Water Systems Consulting (WSC), regarding the Project components and purpose, preliminary design of the Advanced Treatment Facility, updated cost estimates, grant funding opportunities and awards, and permitting requirements. The City Manager for Arroyo Grande also provided information regarding the Cost Sharing Agreement and the anticipated CCB JPA. Total costs to construct the Project are now estimated to reach approximately $93 million. With anticipated federal and state grants, the City’s share of the remaining, non-grant funded costs is anticipated to be approximately $11.6 million. The City’s current water rates will be sufficient to cover these anticipated construction costs.
ANALYSIS OF ISSUES:
As previously explained in the January 25, 2022 staff report, the Project will help address the threat of seawater intrusion by injecting recycled water into the basin at key locations near the seawater interface. Phase 1 of the Project proposes to treat wastewater from the City of Pismo Beach to an advanced purification level to create approximately 900 acrefeet of additional water per year. This new developed water will be injected into the basin at key locations to help to ensure that a sufficient barrier exists within the basin to keep seawater from flooding into the aquifer and contaminating the wells used by the NCMA parties. As a result, the Project will support the City’s ability to rely on groundwater to supply water to its residents and businesses into the future. Approval of the CCB JPA Agreement and completion of the Project will secure an estimated 225 acre-feet per year of reliable groundwater for the City.
Proposed CCB JPA Agreement
The CCB JPA Agreement contains provisions to provide for the ongoing operation of the Project. It provides that the new Central Cost Blue Regional Recycled Water Authority will have the responsibility for the operation and maintenance of the Project and will own the Facility Sites, Facilities, Ancillary Facility Sites and Ancillary Facilities, which are defined in the Agreement. It references and incorporates the Cost Sharing Agreement, and contains provisions to be consistent with it. It has also been reviewed and revised by bond counsel, to address and facilitate anticipated future financing for the Project. The Agreement contains provisions relating to:
Item 11.a.
City Council
Discussion and Consideration of Approval of a Joint Exercise of Powers Agreement Creating the Central Coast Blue Regional Recycled Water Authority and Appointment of a Representative to the Authority Board of Directors September 27, 2022
o The powers of the Authority (e.g., to make contracts, employ staff and consultants, acquire and dispose of property, issue bonds and incur debts and liabilities, apply for grants, etc.).
o The governance of the Authority. There will be a Board of Directors, which will have a Chair and Vice Chair, will meet at least quarterly, and which will consist of one representative of each city, as well as one alternate. Except for reimbursement for actual costs and expenses, the Board will serve without compensation from the Authority.
o An annual budget process. In March of each year, the Board is to adopt a preliminary budget and an allocation of contributions from the Member Agencies for presentation to each Member Agencies' governing body. The governing body of each Member Agency is to then review and comment on the preliminary budget and allocation of contributions. The Board is to adopt a final budget prior to July 1 of each year and adopt an allocation of contributions from the Member Agencies to be consistent with the percentages agreed to for Pre-Construction and Construction costs for Phase 1 of the Project (i.e., Arroyo Grande 25%, Grover Beach 36%, and Pismo Beach 39%). Each annual budget is to be adopted by an affirmative unanimous vote of the Directors, except that the first annual budget may be adopted by a majority vote.
o Construction financing, operations and maintenance costs, capital improvement costs, and debt service. In connection with the issuance of debt, each party will enter into a Financing Agreement with the Authority securing the obligation of such party to make payments on its share of debt service. The Financing Agreements will stipulate that payment to the Authority is a special limited obligation payable solely from system net revenues of each party’s Enterprise Fund.
Termination, withdrawal of Member Agencies and the effect of withdrawal, including continuing liability (the Agreement makes it clear that the debts, liabilities, and obligations of the Authority are not the debts, liabilities and obligations of any of the Member Agencies) and indemnification.
Appointment to the Authority Board of Directors
In addition to consideration and approval of the CCB JPA, it is recommended that the City Council appoint a representative to the Authority Board of Directors. While appointments to regional and local boards and committees are typically considered by Council in December of each year, selection of a representative to the Authority Board at this time will enable the Board to meet sooner, if necessary for purposes of applying for funding or financing.
Item 11.a.
City Council
Discussion and Consideration of Approval of a Joint Exercise of Powers Agreement Creating the Central Coast Blue Regional Recycled Water Authority and Appointment of a Representative to the Authority Board of Directors September 27, 2022
ALTERNATIVES:
1. Approve staff’s recommendation to authorize the Mayor to execute the proposed Joint Exercise of Powers Agreement Creating the Central Coast Blue Regional Recycled Water Authority with the cities of Grover Beach and Pismo Beach for the Central Coast Blue Project; and appoint a member of the City Council to the Authority Board of Directors;
2. Do not approve staff’s recommendation to authorize the Mayor to execute the proposed Joint Exercise of Powers Agreement and provide direction to staff related to any changes that the City Council wants the City Manager to negotiate with the other parties; and/or do not appoint a member of the City Council to the Authority Board of Directors at this time;
3. Provide other direction to staff.
ADVANTAGES:
The City Council has already approved the City’s participation in the Project and the City has executed the Cost Sharing Agreement, which contemplates that the parties will create a Joint Powers Authority to own and operate the Project. Approval of the CCB JPA Agreement will provide a framework for operating, managing and administering the Project. The Project is important for the ongoing resiliency of groundwater resources relied upon by the City, as well as all residents, businesses, agricultural operations, and visitors to the Five Cities area.
DISADVANTAGES:
Since the City has already approved participation in the Project and entered into the Cost Sharing Agreement, no disadvantages to entering into the CCB JPA Agreement have been identified, as it will provide the needed framework for operating, managing and administering the Project.
ENVIRONMENTAL REVIEW:
The City of Pismo Beach is the Lead Agency under the California Environmental Quality Act (CEQA) for the Project and previously prepared, circulated, and approved an Environmental Impact Report (EIR), and adopted findings and a Statement of Overriding Considerations on February 16, 2021. The City of Arroyo Grande is a Responsible Agency for the Project under CEQA. On March 23, 2021, the City Council adopted findings and a Statement of Overriding Considerations for the Project relying on the EIR in compliance with CEQA. No additional CEQA findings are required at this time.
PUBLIC NOTIFICATION AND COMMENTS:
The Agenda was posted at City Hall and on the City’s website in accordance with Government Code Section 54954.2.
Item 11.a.
City Council
Discussion and Consideration of Approval of a Joint Exercise of Powers Agreement Creating the Central Coast Blue Regional Recycled Water Authority and Appointment of a Representative to the Authority Board of Directors September 27, 2022
Attachments:
1. Proposed Joint Exercise of Powers Agreement Creating the Central Cost Blue Regional Recycled Water Authority
2. January 25, 2022 Staff Report relating to Cost Sharing Agreement
3. January 11, 2022 Staff Report and attachments
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
1 A JOINT EXERCISE OF POWERS AGREEMENT
CREATING THE CENTRAL COAST BLUE REGIONAL
RECYCLED WATER AUTHORITY
THIS JOINT EXERCISE OF POWERS AGREEMENT ("Agreement") is made and entered into by and between the City of Arroyo Grande, a California municipal corporation (“Arroyo Grande”), the City of Grover Beach, a California municipal corporation (“Grover Beach”), and the City of Pismo Beach, a California municipal corporation (“Pismo Beach”). The cities may be individually referred to herein as a “Party” or collectively as the “Parties.”
RECITALS
WHEREAS, each Party to this Agreement is a public agency authorized and empowered to contract for the joint exercise of powers under Articles 1 through 4, Chapter 5, Division 7, Title 1 (commencing with Section 6500) of the Government Code of the State of California; and WHEREAS, in 1983, the Parties hereto entered into a voluntary groundwater management plan to manage the safe yield of the Arroyo Grande Groundwater Basin, which agreement was updated by the Parties through approval of the 2002 Agreement Regarding Management of the Arroyo Grande Groundwater Basin (the “Management Agreement”); and
WHEREAS, on April 30, 2002, the Parties hereto, among others, entered into a settlement agreement (the “Settlement Agreement”) related to a 1997 groundwater adjudication litigation filed by the Santa Maria Valley Water Conservation District, which reaffirmed the Management Agreement, established separate water management areas (the “Original Management Areas”) to be independently managed by the Parties and others, and requiring the Parties and others to develop an equitable cost sharing agreement for any newly constructed water resource and water production facilities within the Original Management Areas; and
WHEREAS, on June 30, 2005, the Parties hereto entered into a stipulation imposing a physical solution for ensuring the Arroyo Grande Groundwater Basin’s long-term stability (the “Stipulation”). The Stipulation adopted a local management approach, establishing three management areas (the “Current Management Areas”) and requiring a monitoring program to be established in each of the Current Management Areas; and
WHEREAS, on January 25, 2008, the Santa Clara Superior Court entered Judgment in the Santa Maria Groundwater Adjudication litigation approving the Stipulation, without qualification (the “Adjudication Decree”); and
WHEREAS, the Parties are participating in the Central Coast Blue Project to construct a regional recycled water project that will enhance supply reliability by injecting advanced purified water into the Northern Cities Management Area of the Santa Maria Groundwater Basin (“Project”). The Project will reduce vulnerability to drought and seawater intrusion by creating a seawater intrusion barrier and supplementing the naturally occurring groundwater; and
WHEREAS, Phase 1 of the Project includes construction of an Advanced Treatment Facility (“ATF”), treatment of secondary treated flows from Pismo Beach’s Wastewater Treatment Plant (“WWTP”), construction of approximately five injection wells and associated transmission lines, and injection of flows from the WWTP (“Phase 1”). Phase 1 proposes to treat wastewater from Pismo Beach to an advanced purification level to create between nine hundred (900) and one thousand (1,000) acre-feet of additional water per year; and
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
2 WHEREAS, Phase 2 of the Project will include upgrades to the ATF to increase capacity, construction of approximately two additional injection wells and associated transmission lines, and injection of flows from the South San Luis Obispo County Sanitation District Wastewater Treatment Plant (“Phase 2”); and WHEREAS, Arroyo Grande, Grover Beach and Pismo Beach believe that the best way to achieve their joint goals in a way that is mutually beneficial is to form a joint powers agency under Articles 1 through 4, Chapter 5, Division 7, Title 1 (commencing with Section 6500) of the Government Code of the State of California ("Joint Exercise of Powers Act"); and
WHEREAS, by forming a joint powers agency ("JPA") under the Joint Exercise of Powers Act, the Parties believe they will be better able to, through a separate JPA, oversee and manage the planning and implementation, including but not limited to construction, operation and administration of, the Project.
NOW THEREFORE, in consideration of the above Recitals and of the mutual promises and agreements contained herein, the Parties agree as follows:
ARTICLE 1
GENERAL PROVISIONS
1.1 Definitions. Unless the context otherwise requires, the words and terms defined in this Section
1.1 shall, for the purposes of this Agreement, have the meanings herein specified.
1.1.1. Act means Articles 1 through 4, Chapter 5, Division 7, Title 1 of the Government Code of the State of California (commencing with Section 6500) relating to the joint exercise of powers common to public agencies.
1.1.2. Agreement means this Joint Exercise of Powers Agreement.
1.1.3. Ancillary Facilities means injection wells, storage tanks, pump stations, associated piping, and any other equipment located on an Ancillary Facilities Site.
1.1.4. Ancillary Facilities Sites means any real property or real property interest held by the Authority for purposes of the Project, excluding the Facility Site.
1.1.5. Annual Budget means the budget adopted pursuant to Section 6.2.2 of this Agreement.
1.1.6. Authority means the Central Coast Blue Regional Recycled Water Authority, which is created by this Agreement.
1.1.7. Board or Board of Directors means the Board of Directors referred to in Article 2 of this Agreement, which is the governing body of the Authority.
1.1.8. Bonds means bonds, notes, commercial paper, and any other evidence of indebtedness of the Authority authorized and issued pursuant to the Act, any indebtedness issued or incurred by the Authority pursuant to any act supplementary to the Act, including, but not limited to, refunding bonds authorized and issued pursuant to Article 11 of Chapter 3 of Part 1 of Division 2 of Title 5 of the Government Code of the State of California.
1.1.9. Cost Sharing Agreement means the Cost Sharing Agreement for the Parties’ Participation in the Central Coast Blue Project dated March 14, 2022, a copy of which is attached hereto as Exhibit A and incorporated herein.
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
3 1.1.10. Director means a member of the Board appointed to the Board pursuant to Section 2.2 of this Agreement.
1.1.11. Effective Date means the last date on which all Parties to this Agreement have executed the Agreement.
1.1.12. Facility or Facilities means the advanced water treatment facility that will receive and further treat wastewater influent from Pismo Beach’s WWTP, in Phase 1, which as of the date of this Agreement is proposed to be constructed on Assessor’s Parcel Number 060- 543-016 in the City of Grover Beach, including the Facility’s equalization basin, injection wells, storage tanks, pump station and associated piping and equipment from the Pismo Beach.WWTP, but excluding the joint outfall shared by the South San Luis Obispo County Sanitation District and the City of Pismo Beach which both agencies use to discharge their municipal waste.
1.1.13. Facility Site means Assessor’s Parcel Number 060-543-016 in the City of Grover Beach, California.
1.1.14. Financing Agreement means any agreement between the Authority and a Member Agency securing the obligation of the Member Agency to make payments relating to Bonds or other obligations issued or incurred by the Authority in connection with the financing of the Facilities or the improvement, use or acquisition of real or personal property that is or will be owned or operated by the Authority, or to refinancing of such previously issued or incurred Bonds or other obligations.
1.1.15. Manager means the manager of the Authority.
1.1.16. Member Agency(ies) means Arroyo Grande, Grover Beach and Pismo Beach and any other entity added to this Agreement by a subsequent amendment.
1.1.17. Member of the Board or Board Member means and includes any duly appointed Director, Chair and/or Vice-Chair of the Board.
1.1.18. Party(ies) means those entities who have executed this Agreement or any Amendment to this Agreement and who have not withdrawn from the Authority.
1.2 Purpose. This Agreement is made pursuant to the Act by Arroyo Grande, Grover Beach and Pismo Beach, each of which is authorized to contract with the other pursuant hereto. The purposes of this Agreement are to create the Authority, provide for the administration of the Authority and to enable the Authority to: (1) take all actions necessary to operate, and maintain Phases 1 and 2 of the Project. Phase 1 includes construction of an ATF, treatment of all secondary treated flows from Pismo Beach’s WWTP, construction of approximately five injection wells and associated transmission lines, and injection of flows from the WWTP; and (2) pursue grant funding and financing options for the Project and future projects; and (3) collectively interact with regulatory agencies with oversight over the Parties and the Project.
1.3 Creation of Authority. Pursuant to the Act, there is hereby created a public entity known as the “Central Coast Blue Regional Recycled Water Authority." The Authority shall be a public entity separate and apart from the Member Agencies and shall administer this Agreement.
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
4 1.4 Term. The term of this Agreement shall commence on the Effective Date and shall continue until terminated by the Parties as provided in Article 7 of this Agreement.
1.5 Phase 1, Project Facility Site Ownership, Construction Financing, and Operation
1.5.1. Phase 1 of Project. As set forth in Article III, Section 1 – Lead Agency Duties of the Cost Sharing Agreement, Pismo Beach will be Lead Agency and act as project developer through final completion of Phase 1 of the Project. As the Lead Agency, Pismo Beach will act as the construction manager for Phase 1 and will provide administration of construction and start-up of Phase 1 on behalf of the Member Agencies. The Parties shall pay their pro rata shares of Pre-Construction costs for any professional service expenses incurred by Pismo Beach in connection with obtaining such Phase 1 approvals, in accordance with Section 6.3.2 below.
1.5.2. Ownership of Facility Sites and Facilities. Pismo Beach has previously purchased the Facility Site, which is located in Grover Beach and identified as Assessor’s Parcel Number 060-543-016 (“Facility Site”). Within sixty (60) days of the Effective Date of this Agreement, Pismo Beach shall transfer the Facility Site to the Authority. The Authority shall own all Facilities located at the Facility Sites, including, but not limited to, the real property, buildings, water and treatment facilities, and support infrastructure and assets, injection wells and related transmission lines.
1.5.3. Ownership of Ancillary Facilities Sites and Ancillary Facilities. The Authority shall own all Ancillary Facilities Sites and Ancillary Facilities located thereon.
1.5.4. Financing of Construction Costs. To finance Construction Costs, as defined in the Cost Sharing Agreement, the Authority shall apply for and obtain financing for such costs through the issuance of Bonds, entering into loans or Financing Agreements or any other financing mechanisms not otherwise covered by grant funding awarded to the Project.
Any loans entered into and secured for construction of the Project may consist of separate installment sale agreements based on the respective share of each Member Agency, and any prepayment may be paid either directly to the Authority by each Party consistent with the Water Purveyor Contribution percentages identified in Section 6.3.2 hereof or directly to the grant funding agency or bond trustee, depending on the funding mechanism. In the event that the Authority is not able to finance the Construction Costs as described in this Section 1.5.4, the Parties will seek financing consistent with the financing plan described in Article III, Section 1.c of the Cost Sharing Agreement for its respective share of Construction Costs.
1.5.5. Operation and Maintenance of the Facilities. The Authority will have total responsibility for the operation and maintenance of the Facilities.
1.5.6. Procurement Methods. The Board may adopt such policies relating to procurement of services, equipment, supplies and other materials needed to accomplish the purposes of this Agreement.
1.6 Powers of Authority
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
5 1.6.1. General Powers. The Authority shall exercise, in the manner herein provided, the powers which are common to each of the Member Agencies, powers otherwise permitted under the Act, and powers necessary to accomplish the purposes of this Agreement.
1.6.2. Specific Powers. Subject to the limitations set out in Section 1.6.1, the Authority is hereby authorized, in its own name, to do all acts necessary, convenient and appropriate for the exercise of the foregoing powers for the purposes set forth in this Agreement and to do any or all of the following:
i. To make and enter contracts, including contracts with its Member Agencies; ii. To employ agents, attorneys, consultants and employees or to contract for personnel to fulfill its mission and purpose. The Authority shall not contact employees of the Member Agencies at their current places of employment about employment opportunities with the Authority;
iii. To lease, acquire, construct, manage, maintain or operate any building, works or improvements;
iv. To lease, acquire, hold or dispose of real or personal property; v. To acquire and hold property, including funds, Project agreements and other obligations of any kind, and pledge, encumber or assign the same, or the revenues therefrom or any portion of such revenues, or other rights, whether then owned or possessed, or thereafter acquired, for the benefit of the bondholders, and as security or additional security for any bonds or the performance of obligations under an indenture;
vi. To provide for the advance of bond proceeds and other funds pursuant to Project agreements as necessary to pay or reimburse for Project costs; vii. To borrow money and issue Bonds and incur debts, liabilities or obligations for the purpose of paying all or any part of the costs of the Project or for any other authorized purpose, which do not constitute a debt, liability or obligation of any Member Agency;
viii. To receive gifts, contributions and donations of property, funds, services and other forms of assistance from persons, firms, corporations, and governmental entities, provided that the Authority consents to such gifts, contributions and donations;
ix. To fix the compensation, if any, paid to the Board of Directors, Secretary, Treasurer, Controller and Attorney, in compliance with all applicable laws; x. To prescribe the duties, compensation and other terms and conditions of employment of other agents, officers and employees;
xi. To adopt reasonable rules and regulations for the conduct of the day-to-day operations of the Authority;
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
6 xii. To apply for, accept, receive and disburse grants, loans and other aid from any agency of the United States of America or of the State of California; xiii. To sue and be sued in its own name;
xiv. To enter into Financing Agreements, state funding agreements and federal funding agreements relating to the Project, and assume rights and obligations pursuant to these agreements;
xv. To invest money in the treasury, pursuant to Government Code Section 6505.5, that is not required for the immediate necessities of the Authority, as the Authority determines advisable, in the same manner and on the same conditions as local agencies, pursuant to Section 53601 of the Government Code; xvi. To contract and pay compensation for professional, financial, and other services; xvii. To carry out and enforce all provisions of this Agreement; xviii. To exercise any and all powers which are provided for in the Act and in Government Code section 6584 et seq., including, without limitation, Government Code section 6588, as they exist on the Effective Date of this Agreement or may hereafter be amended;
xix. To exercise any power necessary or incidental to the foregoing powers.
ARTICLE 2
BOARD OF DIRECTORS
2.1. Creation. The Authority shall be governed by a board of three (3) members, which is hereby established and which shall be composed of one (1) representative appointed from each Member Agency.
The governing board shall be known as the "Board of Directors of the Central Coast Blue Regional Recycled Water Authority." All voting power shall reside in the Board.
2.2. Members of the Board of Directors.
2.2.1. Directors Appointed. Upon the Effective Date of this Agreement, each Member Agency which has not already done so shall designate and appoint, by resolution or minute order of its governing body, one (1) member of its governing body to act as its representative on the Board of Directors, and one individual to act as an alternate to each Director so appointed. The alternate appointed by each Member Agency shall have the authority to attend, participate in and vote at any meeting of the Board when the regular member is absent.
2.2.2. Membership. Each Director and alternate of the Board of Directors shall serve until a successor is appointed; provided, however, each Director and alternate serves at the pleasure of the appointing Member Agency's governing body and may be removed at any time, with or without cause, at the sole discretion of the appointing Member Agency governing body. If a Director or alternate's membership on the appointing Member Agency's governing body ceases, his or her membership on the Board shall also cease.
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
7 2.2.3. Chair. The Board of Directors shall elect one of its members as Chair of the Board. The term of office for the Chair of the Board shall be one (1) year. The Chair of the Board shall preside at all meetings and shall perform such other duties as are specified by the Board of Directors.
2.2.4. Vice-Chair. The Board of Directors shall elect one of its members as Vice-Chair. The term of office for the Vice-Chair shall be one (1) year. The Vice-Chair shall perform all the duties of the Chair of the Board in the absence of the Chair of the Board or in the event the Chair of the Board is unable to perform such duties, and shall perform such other duties as are specified by the Board of Directors.
2.2.5. Board Compensation. Except for reimbursement for actual costs and expenses, the Board shall serve without compensation from the Authority. Compensation may be provided as approved by the Member Agencies appointing each Director and alternate, and any such compensation will be the responsibility of the Member Agency.
2.2.6. Reimbursement of Costs. Each Board Member is entitled to reimbursement for their travel, meals, lodging and other actual and necessary expenses incurred in the performance of the duties required or authorized by the Board pursuant to Government Code Section 53232.2.
2.3. Powers of the Board. All the power and authority of the Authority shall be exercised by the Board of Directors.
2.4. Provision for Bylaws. The Board may cause to be developed and may adopt, from time to time, such bylaws for the Authority to govern its day-to-day operations. Each Member Agency shall receive a copy of any bylaws developed and adopted under this Section.
ARTICLE 3
MEETINGS OF THE BOARD
3.1 Meetings. The Board shall provide for its regular meetings by resolution; provided, however, that at least one regular meeting shall be held each fiscal quarter. The date, hour and place of the regular meetings shall be fixed by resolution of the Board and filed with the governing body of each of the Member Agencies. The Board may meet in joint session with other public agencies and advisory bodies in accordance with State law.
3.2 Ralph M. Brown Act. All meetings of the Board, including, without limitation, regular, adjourned regular, special, adjourned special, and emergency meetings, shall be called, noticed, held, and conducted in accordance with the provisions of the Ralph M. Brown Act, commencing with section 54950 of the Government Code.
3.3 Voting. Each Board Member shall have one vote. Except as otherwise provided by law or by this Agreement, all actions of the Board shall be approved on the affirmative vote of a majority of the Members of the Board.
3.4 Quorum. A majority of the Members of the Board shall constitute a quorum for the transaction of business, except that less than a quorum may adjourn from time to time.
3.5 Minutes. The Secretary of the Authority shall cause minutes of regular, adjourned regular, special, adjourned special, and emergency meetings to be kept and shall, as soon as possible after each
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
8 meeting, cause a copy of the minutes to be forwarded to each Member of the Board and to each Member Agency.
3.6 Rules. The Board may adopt from time to time such rules and regulations for the conduct of its affairs as may be required.
ARTICLE 4
OFFICERS AND EMPLOYEES OF THE AUTHORITY
4.1 Secretary. The Board of Directors shall appoint a Secretary who shall serve at the pleasure of the Board. The Secretary may, but need not, be a member of the Board of Directors. The Secretary shall be responsible for the minutes and other records of the proceedings of the Board of Directors and shall perform such other duties as the Board of Directors specifies.
4.2 Treasurer and Auditor Controller. Pursuant to Government Code Sections 6505.5 and 6505.6, the Authority's Treasurer and Auditor/Controller shall be the Manager's senior financial officer (such as its chief financial officer, director of finance, or finance manager as designated by the Manager. The Treasurer shall be the depository and have custody of all money of the Authority, from whatever source, and shall have all of the duties and obligations set forth in Sections 6505 and 6505.5 of the Government Code. The offices of Treasurer and Auditor/Controller may be held by separate individuals, or combined and held by one individual as the Board may elect. The Treasurer and Auditor/Controller shall serve at the pleasure of the Manager and may be removed at any time, with or without cause, in the sole discretion of the Manager.
4.3 Authority Attorney. The Attorney for the Authority, who may not be counsel to one of the Member Agencies, shall be engaged by the Board of Directors. The Attorney for the Authority or a designated deputy shall attend or participate in meetings of the Board of Directors; provided, however, that the absence of the Authority Attorney shall not affect the validity of any meeting. The Attorney shall perform such other duties the Board of Directors specifies.
4.4 Official Bond. Pursuant to Government Code section 6505.1, the public officer, officers or persons who have charge of, handle or have access to any property of the Authority shall file an official bond in an amount to be fixed by the Parties to this Agreement.
4.5 Additional Officers and Employees. The Board shall have the power to appoint such additional officers and to employ such employees, assistants, contractors, consultants and others as may be appropriate. Such power shall include, but not be limited to, the power to appoint a Manager for the purposes of managing and administering the Authority, and an Operator for the purposes of providing operations, maintenance, and similar services to the Authority. A Member Agency may be appointed as the Authority's Manager and/or Operator pursuant to a written agreement with the Authority.
ARTICLE 5
COMMITTEES
5.1 Committees. The Board of Directors, by a majority vote, may form committees for any purpose.
Such vote shall designate the method for appointing committee members, the scope of the duties and responsibility of the committee, whether the committee is a standing or ad hoc committee, and such other matters as the Board may deem appropriate.
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
9 ARTICLE 6
FINANCES
Fiscal year. The Fiscal Year of the Authority shall be the period commencing on July 1 of each year and ending on and including the following June 30.
6.2 Annual Budget.
6.2.1 Interim Budget. The Board shall, within one hundred and twenty days (120) days of the Effective Date of this Agreement, approve an interim budget, which shall constitute the operating budget until the Annual Budget is adopted.
6.2.2 Annual Budget. Except for costs related to construction of Phase I, which shall be subject to the Cost Sharing Agreement, annually, in March of each year, the Board shall adopt a preliminary budget and an allocation of contributions from Member Agencies for presentation to each Member Agencies' governing body. The governing body of each Member Agency shall, no later than May 31 of each year, review and comment on the preliminary budget and allocation of contributions. Thereafter, annually, prior to July 1 of each year, the Board shall adopt a final budget for all expenses to be made by the Authority during the ensuing Fiscal Year and adopt an allocation of contributions from Member Agencies consistent with Section 6.3.2. Each annual budget shall be adopted and shall be effective on the affirmative unanimous vote of the Directors, except that the first Annual Budget may be adopted by an affirmative vote of a majority of the Directors.
Contributions for each Member Agency shall be due and payable to the Authority on a monthly basis with the first payment being made within thirty (30) days of approval of the budget.
6.2.3 Failure to Obtain Budget Approval. In the event the Board does not adopt a budget prior to the beginning of a fiscal year, the budgeted amounts of all expenses and allocation of contributions from Member Agencies shall remain the same as the amounts last approved by the Board in its most recently adopted budget; provided, however, that the amounts shall be increased by the Consumer Price Index ("CPI") with a minimum increase of no less than two percent (2%). The CPI shall mean the Consumer Price Index, Bureau of Labor Statistics, U.S. Department of Labor Consumer Price Index-All Urban Consumers, All Items, Los Angeles-Long Beach-Anaheim CA for the twelve (12) month period ending the February prior to the beginning of the fiscal year, or if this index no longer exists, an index approved by a majority of the Board. This factor shall be applied to the budget until such time as a new budget is adopted by the Board. Any shortfall in revenues shall be made up from available reserves dedicated by the Board for such purpose and, if insufficient to cover the shortfall, any available reserve funds which have not been designated by the Board for a particular purpose or otherwise legally restricted for other purposes. Reserves shall mean any available cash or investments.
6.3 Funds, Accounts and Reports. There shall be strict accountability of all funds and reporting of all receipts and disbursements.
6.3.1 Sources of Funds. The sources of funds available to the Authority may include, but are not limited to, the following:
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
10 i. Grants, donations, and loans received by the Authority from local, State, or Federal agencies or from individuals or businesses.
ii. Funds collected as user charges or user fees by Member Agencies. iii. Funds collected from Members pursuant to this Agreement. iv. Funds received from State and Federal disaster relief agencies. v. Funds obtained by issuing Bonds.
vi. Funds collected pursuant to a Financing Agreement.
vii. "In kind" contributions from Member Agencies.
viii. Funds from any other source derived.
The Authority shall arrange for the receipt of such funds from the above sources as are available to the Authority and as are necessary for the conduct of the Authority's activities. Member Agencies may, in the appropriate circumstances: (a) make contributions from their treasuries for the purposes set forth in this Agreement; (b) make payments of public funds to defray the cost of such purposes; and (c) make advances of public funds for such purposes. The provisions of Government Code section 6513 are incorporated into this Agreement.
6.3.2 Water Purveyor Contributions. The Parties shall pay their pro rata share of all PreConstruction and Construction Costs incurred by Pismo Beach in connection with Phase 1 of the Project.
The Parties agree to the following cost allocation of the total Pre-Construction and Construction costs for Phase 1 for each Party:
i. Arroyo Grande shall contribute 25%.
ii. Grover Beach shall contribute 36%.
iii. Pismo Beach shall contribute 39%.
. As provided in Section 6.2.2, annual contributions by Member Agencies for ongoing operations shall be consistent with the above percentages.
6.3.3 Accounts. Revenues or funds received or made available to the Authority from any source whatsoever, shall be deposited into accounts that may be established by the Authority and may be expended by the Authority in any legal manner, subject to such reservations as may be imposed by the Authority from time to time.
6.3.4 Reports. The Treasurer shall, within one hundred and eighty days (180) days after the close of each Fiscal Year, give a complete written report of all financial activities for such fiscal year to the Board of Directors and to each Member Agency. The Authority's books and records shall be open to inspection at all reasonable times by representatives of each Member Agency.
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
11 6.4 Payments and Advances. No expenditures in excess of those budgeted shall be made without approval of a revised or amended budget, which may from time to time be submitted to and approved by the Board of Directors.
6.5 Audit. The Treasurer and Auditor/Controller shall cause an annual audit of the accounts and records of the Authority to be made and reported in accordance with Sections 6505 through 6505.6 of the Government Code. The audit shall be conducted by an independent certified public accountant. The audit shall conform to generally accepted auditing standards. Such report shall be filed within twelve (12) months of the end of the Fiscal Year under examination.
ARTICLE 7
COST ALLOCATION
7.1 Operations and Maintenance Costs. Each Party shall pay its allocated share of all expenses incurred by the Authority for administration, operation, and maintenance of its Facilities and Ancillary Facilities based on the Water Purveyor Contribution percentages.
7.2. Capital Improvement Costs. Capital improvement costs to acquire, construct, or improve Facilities and Ancillary Facilities shall be subject to allocation between the Parties based on the Water Purveyor Contribution percentages.
7.3 Debt Service. In connection with the issuance of Bonds or the incurrence of other obligations by the Authority to finance or refinance Construction Costs or capital improvement costs to acquire, construct or improve Facilities and Ancillary Facilities, each Party shall negotiate a Financing Agreement with the Authority that includes provisions by which each Party shall make payments with respect to such Party’s share of debt service on the Bonds or other obligations incurred by the Authority, consistent with any pre-existing contractual obligations of each Party.
Each Financing Agreement will stipulate that the debt service payments made by a Party to the Authority will be subject to the payment limitations set forth in Article IV, Section 5 of the Cost Sharing Agreement. For purposes of this Section 7.3, the provisions of Article IV, Section 5 of the Cost Sharing Agreement shall continue in full force and effect in the event that the Cost Sharing Agreement shall terminate.
At the time of a Bond issuance or the entering into of any other obligation by the Authority, if a Party elects to pay its share of the capital improvement costs in full with cash, it will not be allocated any share of the debt service on such Bonds or other obligations incurred by the Authority, and will not be required to enter into a Financing Agreement with the Authority, for that Bond issuance or obligation.
ARTICLE 8
TERMINATION/WITHDRAWAL/AMENDMENT
8.1 Duration and Termination. This Agreement shall become effective as of the Effective Date and shall continue in full force and effect until terminated by the mutual written agreement of all Member Agencies, which agreement shall meet the requirements imposed by the terms and conditions of all outstanding bonds, notes, warrants, indentures and other evidences of indebtedness; provided, however, that this Agreement and the Authority shall continue to exist for the purpose of disposing of all claims, distribution of assets, and all other functions necessary to conclude the affairs of the Authority.
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
12 8.2 Withdrawal. Notwithstanding any other provision of this Agreement, any Member Agency may withdraw from the Authority by providing the Authority with one hundred eighty (180) days written notice of its intent to withdraw. A withdrawal from the Authority constitutes a withdrawal of that Member Agency's representatives from the Board of Directors.
8.3 Effect of Withdrawal. The withdrawal of a Member Agency shall not terminate its responsibility to contribute its share of any obligation incurred by the Authority, including amounts determined by the Board for (1) liabilities and claims accrued during the time the agency was a Member Agency or (2) budgeted expenses for the Fiscal Year in which notice of intent to withdraw is given. Except as the withdrawing Member Agency may agree, in writing, with the Board, the withdrawing Member Agency shall automatically relinquish all rights as a Member Agency under this Agreement, on the effective date of the withdrawal. Upon termination of this Agreement, a Member Agency that has withdrawn will be treated like all other Member Agencies for purposes of disbursement of Authority assets, unless otherwise agreed in writing.
8.4 Disbursement. Upon termination of this Agreement and after payment of all liabilities, costs, expenses and charges validly incurred under this Agreement, all remaining assets of the Authority shall be disbursed among Member Agencies, including any Member Agencies which previously withdrew from the Authority. All assets shall be divided among the Member Agencies in accordance with and proportionate to the Water Purveyor Contribution amounts stated in Section 6.3.2, if it is feasible to do so.
8.5 Amendment. This Agreement may be amended at any time by the written approval of the governing body of each Member Agency upon recommendation of a majority of the Board of Directors of the Authority.
ARTICLE 9
SPECIAL PROVISIONS
9.1 Insurance. The Authority shall maintain types and levels of insurance coverage for the Authority as the Board of Directors determines to be reasonably adequate, provided, however, that each Member Agency shall be named as an additional insured on such policy of and/or agreement for insurance coverage.
9.2 Liability of Authority, Board, Officers, Employees. Pursuant to Government Code section 6508.1, the debts, liabilities, and obligations of the Authority shall not be the debts, liabilities and obligations of any of the Member Agencies or any of their respective members, officers, directors, employees or agents. The Authority, its Directors, officers, employees, staff and agents shall use ordinary care and reasonable diligence in the exercise of their powers and in the performance of their duties pursuant to this Agreement. No Member Agency, its officer, director or employee shall be responsible for any action taken or omitted by any other Member Agency, or its officers, or employees or the Authority, its officers, or employees.
9.3 Indemnity. The Authority shall indemnify, defend and hold harmless the Board of Directors, the individual Member Agencies, and their elected officials, members, officers, directors, employees and agents from and against any and all liability, loss, damages, expenses, costs (including, without limitations, costs and fees of litigation or arbitration) of every nature, arising out of any act or omission related to this Agreement, including, but not limited to those related to the use of any property and/or facility of any Member Agency, The Authority shall indemnify, defend and hold harmless the individual Member Agencies, and their elected officials, members, officers, directors, employees and agents from and against any and all liability, loss, damages, expenses, costs (including, without limitations, costs and
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
13 fees of litigation or arbitration) of every nature, arising out of any willful misconduct of the Authority Board of Directors or its Board Members, officers or employees. Further, the duty of the Authority to indemnify, defend and hold harmless shall not extend to the activities of the individual Member Agencies, and their members, officers, directors, employees and agents that are outside the scope of this Agreement.
The Authority's duty to indemnify each Member Agency pursuant to this Agreement shall survive that Member Agency's withdrawal from the Agency. This section shall not be deemed to supersede, extinguish, or modify the indemnification provisions in the Cost Sharing Agreement.
9.4 Conflict of Interest Code. The Authority shall, by resolution, adopt a conflict of interest code as required by law.
ARTICLE 10
MISCELLANEOUS PROVISIONS
10.1 Severability. If any section, clause or phrase of this Agreement or the application thereof to any Party or any other person or circumstance is for any reason held to be invalid by a court of competent jurisdiction, it shall be deemed severable, and the remainder of the Agreement or the application of such provisions to the other Party or to other persons or circumstances shall not be affected thereby. Each Party hereby declares that it would have entered into this Agreement, and each subsection, sentence, clause and phrase thereof, irrespective that one or more sections, subsections sentences, clauses or phrases or the application thereof might be held invalid.
10.2 Notices. Notices required or permitted hereunder shall be sufficiently given if made in writing and delivered either personally or by registered or certified mail, postage prepaid to the respective Parties, as follows:
City of Arroyo Grande
Attention: City Manager
300 E Branch Street
Arroyo Grande, CA 93420
City of Pismo Beach
Attention: City Manager
760 Mattie Road
Pismo Beach, CA 93449
City of Grover Beach
Attention: City Manager
154 S. Eighth Street
Grover Beach, CA 93433
10.3 Other Obligations. The responsibilities and obligations of each Party to this Agreement shall be solely as provided in this Agreement, or as may be provided for in other agreements to be executed by the Parties, including but not limited to the Cost Sharing Agreement. In the event there is any conflict between this Agreement and the Cost Sharing Agreement, the provisions of this Agreement shall be controlling.
10.4 Consent. Whenever in this Agreement or in any amendment thereto consent or approval is required, the same shall not be unreasonably withheld.
10.5 Other Agreements Not Prohibited. Other agreements by and between the Parties of this Agreement or any other entity are neither prohibited nor modified in any manner by execution of this Agreement.
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
14 10.6 Assignment. The rights, titles and interests of any Party to this Agreement shall not be assignable or transferable without the consent of the governing body of each Party hereto and the Board of Directors.
Any assignment of a membership in the Authority made under this Section 10.6 by the governing body of any Party hereto will not result in the novation of the assignor Member Agency’s obligations with respect to this Agreement, a Financing Agreement or any other agreement which may obligate the assignor Member Agency, unless such novation is agreed to in writing by such consenting Member Agency, the assignee and the assignor Member Agency.
10.7 Section Headings. The section headings herein are for convenience of the Parties only, and shall not be deemed to govern, limit, modify or in any manner affect the scope, meaning or intent of the provisions or language of this Agreement.
10.8 Laws of California. This Agreement is made in the State of California, under the Constitution and laws of such State, and shall be construed and enforced in accordance with the laws of such State.
10.9 Construction of Language. It is the intention of the Parties hereto that if any provision of this Agreement is capable of two constructions, one of which would render the provision void and the other of which would render the provision valid, then the provision shall have the meaning which renders it valid.
10.10 Cooperation. The Parties recognize the necessity and hereby agree to cooperate with each other in carrying out the purposes of this Agreement.
10.11 Successors. This Agreement shall be binding upon and shall inure to the benefit of the successors of the Parties hereto.
10.12 Enforcement. The Authority is hereby authorized to take any and all legal or equitable actions, including, but not limited to, an injunction and specific performance, necessary or permitted by law to enforce this Agreement.
10.13 Integration. This Agreement constitutes the full and complete Agreement of the Parties.
10.14 Counterparts. This Agreement may be executed in counterparts, each of which shall constitute an original and all of which together shall constitute one and the same agreement. [Signatures on following page.]
ATTACHMENT 1
A JOINT EXERCISE OF POWERS AGREEMENT CREATING THE
CENTRAL COAST BLUE REGIONAL RECYCLED WATER AUTHORITY
15 IN WITNESS WHEREOF, the Parties have caused this Joint Exercise of Powers Agreement to be executed and attested by their proper officers thereunto duly authorized on the day and year set forth below, making the same effective on the date signed by the last of all Parties hereto.
CITY OF ARROYO GRANDE: CITY OF PISMO BEACH:
By:
Caren Ray Russom, Mayor
Date:
By:
Ed Waage, Mayor
Date:
ATTEST:
By:
Jessica Matson, City Clerk
Date:
ATTEST:
By:
Erica Inderlied, City Clerk
Date:
APPROVED AS TO FORM:
By:
Timothy J. Carmel, City Attorney
Date:
APPROVED AS TO FORM:
By:
David M. Fleishman, City Attorney
Date:
CITY OF GROVER BEACH:
By:
Jeff Lee, Mayor
Date:
ATTEST:
By:
Wendi Sims, City Clerk
Date:
APPROVED AS TO FORM:
By:
David P. Hale, City Attorney
Date:
ATTACHMENT 2
Attachment 2 - January 25, 2022 Staff Report relating to Cost Sharing Agreement is available as a link: https://pub-arroyogrande.escribemeetings.com/Meeting.aspx?Id=1d8cd654- ed8d-45c4-bfc0-95d7b21fc210&Agenda=Merged&lang=English&Item=68&Tab=attachments
ATTACHMENT 3
Attachment 3 - January 11, 2022 Staff Report and attachments is available as a link:
https://pub-arroyogrande.escribemeetings.com/Meeting.aspx?Id=42d4e825-1f91-451a-af31- 6e17dfa546e0&Agenda=Agenda&lang=English&Item=41&Tab=attachments