Cities Index.
ATT 5 - Project Descriptions List

Atherton City Council
May 1, 2024

Document
ATT 5 - Project Descriptions List
Meeting
May 1, 2024
Body
Atherton City Council
Original file
701 KB
Text extracted from the city's file for reading and search. Open the original on atherton.primegov.com. That file is the official record.

FY 2024/25 Projects
Bike|Ped Master Plan (Line 29) Project # Amount Description (CIP Program pg.15) 1-A $ 250,000 Selby Bike Lane Improvements/Construction 1-B $ 250,000 Bicycle & Pedestrian Master Plan Update
$ 500,000
Drainage Master Plan (Line 30) Project # Amount Description (CIP Program pg. 22) 2-A $ 2,750,000
El Camino Real Long Term Drainage/additional
design and construction
2-B $ 725,000 Drainage Town Match Eschoo
2-C $ 10,000 Drainage Inlet Markers
$ 3,485,000
Federal Funding Grant (Line 32) 4 $ 1,380,000
Eschoo- Atherton Channel Culvert & Detention
System Drainage Grant (CIP Program pg. 22)
Green Infrastructure Plan (Line 37) 2-D $ 350,000 Green Infrastructure (Selby & ADLP) $ 5,215,000 Drainage Total
Park Master Plan (Line 31) Project # Amount Description (CIP Program pg. 27) 3-A $ 1,000,000 New Playground construction at HPP
3-B $ 800,000 Playground Restroom Replacement/Construction 3-C $ 150,000
Jennings Pavilion Flooring, Cosmetic Improvements;
Main House Flooring
$ 1,950,000
Road Maintenance Improvement (Line 33) Project # Amount Description (CIP Program pg. 17) 5 $ 840,000 Road Maintenance Program
Traffic Safety Improvement Plan (Line 38) Project # Amount Description (CIP Program pg. 13) 6 $ 450,000 Additional Funding for ADLP
Facility Replace/Improvements (Line 40) Project # Amount Description (CIP Program pg. 26) 7-A $ 100,000 HPP General Assessment & Miscellaneous Repairs 7-B $ 150,000 Town Center Potential Improvements
7-C $ 250,000 Facility Replacements
$ 500,000
$ 9,455,000 Total Amount
ATTACHMENT 5
FY 2025/26 Projects
Bike|Ped Master Plan (Line 29) Project # Amount Description (CIP Program pg.16) 8-A $ 250,000 Atherton Avenue Bicycle Lanes Design
8-B $ 100,000 Watkins Avenue Pedestrian Improvement Study 8-C $ 150,000
ECR Complete Streets/Project Approval &
Environmental
$ 500,000
Park Master Plan (Line 31) Project # Amount Description (CIP Program pg. 27) 9-A $ 200,000 Master Plan Refresh
9-B $ 150,000 Solar and Energy Resilient Improvements
$ 350,000
Road Maintenance Improvement (Line 33) Project # Amount Description (CIP Program pg. 22) 10 $ 840,000 Road Maintenance Program
Green Infrastructure Plan (Line 37) Project # Amount Description 11-A $ 200,000 Green Infrastructure To Be Determined
11-B $ 10,000 Drainage Inlet Markers
$ 210,000
(CIP Program pg. 26)
Facility Replace/Improvements (Line 40) Project # Amount Description 12-A $ 100,000 HPP General Assessment & Miscellaneous Repairs 12-B $ 100,000 Town Center Potential Improvements
12-C $ 300,000 Facility Replacements
$ 500,000
$ 2,400,000 Total Amount
ATTACHMENT 5
FY 2026/27 Projects
Bike|Ped Master Plan (Line 29) Project # Amount Description 13-A $ 1,500,000 Atherton Avennue Bicycle Lanes Construction 13-B $ 250,000
ECR Complete Streets/Project Approval &
Environmental
$ 1,750,000
Project # Amount Description
Drainage Master Plan (Line 30) 14 $ 250,000 Drainage Master Plan Project to be determined Green Infrastructure Plan (Line 37) 17 $ 200,000 Green Infrastructure To Be Determined $ 450,000
Park Master Plan (Line 31) Project # Amount Description 15 $ 250,000 Master Plan Improvements To Be Determined
Road Maintenance Improvement (Line 33) Project # Amount Description 16 $ 840,000 Road Maintenance Program
Facility Replace/Improvements (Line 40) Project # Amount Description 18-A $ 100,000 HPP General Assessment & Miscellaneous Repairs 18-B $ 100,000 Town Center Potential Improvements
18-C $ 300,000 Facility Replacements
$ 500,000
$ 3,790,000 Total Amount
ATTACHMENT 5
FY 2027/28 Projects
Bike|Ped Master Plan (Line 29) Project # Amount Description 19-A $ 1,000,000 Atherton Avennue Bicycle Lanes Construction 19-B $ 500,000 To Be Determined Projects
$ 1,500,000
Project # Amount Description
Drainage Master Plan (Line 30) 20 $ 2,500,000 Drainage Master Plan Project To Be Determined Green Infrastructure Plan (Line 37) 23 $ 250,000 Green Infrastructure To Be Determined $ 2,750,000
Park Master Plan (Line 31) Project # Amount Description 21 $ 250,000 Master Plan Improvements To Be Determined
Road Maintenance Improvement (Line 33) Project # Amount Description 22 $ 840,000 Road Maintenance Program
Facility Replace/Improvements (Line 40) Project # Amount Description 24-A $ 100,000 HPP General Assessment & Miscellaneous Repairs 24-B $ 400,000 Facility Replacements
$ 500,000
$ 5,840,000 Total Amount
ATTACHMENT 5
FY 2028/29 Projects
Bike|Ped Master Plan (Line 29) Project # Amount Description 25 $ 1,000,000 To Be Determined Projects
Project # Amount Description
Drainage Master Plan (Line 30) 26 $ 2,500,000 Drainage Master Plan Project To Be Determined Green Infrastructure Plan (Line 37) 29 $ 250,000 Green Infrastructure To Be Determined $ 2,750,000
Park Master Plan (Line 31) Project # Amount Description 27 $ 250,000 Master Plan Improvements To Be Determined
Road Maintenance Improvement (Line 33) Project # Amount Description 28 $ 840,000 Road Maintenance Program
Facility Replace/Improvements (Line 40) Project # Amount Description 30-A $ 100,000 HPP General Assessment & Miscellaneous Repairs 30-B $ 400,000 Facility Replacements
$ 500,000
$ 5,340,000 Total Amount
ATTACHMENT 5

← All documents from this meeting