PREPARED FOR:

Town of Atherton
July 20, 2026
Proposal

EL CAMINO REAL/SELBY LANE

INTERSECTION IMPROVEMENTS PROJECT
(RFP No. 56096)
(408) 453-5373
2833 JUNCTION AVENUE, SUITE 110
SAN JOSE, CA 95134 MARKTHOMAS.COM
July 20, 2026
Town of Atherton
Attn: Douglas Kim, Consultant Project Manager
80 Fair Oaks Lane
Atherton, CA 94027
RE: Professional Engineering Services for El Camino Real/Selby Lane Intersection Improvements Project (56096) Dear Mr. Kim:

This project presents an important opportunity to improve safety, accessibility, and operations at a key crossing along El Camino Real. We understand that the Town of Atherton (Town) is seeking a team that can evaluate feasible alternatives, coordinate effectively with Caltrans and partner agencies, and advance the project through final design with a thorough understanding of the corridor context, multimodal needs, and implementation requirements.

Mark Thomas & Company, Inc. (Mark Thomas) brings extensive experience delivering intersection and corridor improvement projects on Caltrans-owned facilities and local roadways throughout California. Our team has successfully delivered projects involving multimodal safety enhancements, traffic analysis, environmental documentation, Caltrans coordination and approvals, and final design. We understand the technical and coordination challenges associated with improving facilities along El Camino Real and similar corridors, and we bring a practical, responsive approach that keeps projects moving efficiently while maintaining clear communication among stakeholders.

For Atherton, our team will focus on developing context-sensitive solutions that improve bicycle and pedestrian access, enhance traffic operations, and align with ongoing and planned improvements along the corridor. We take a disciplined approach to project management and agency coordination that supports timely decision-making and steady progress throughout each phase of the project. Our team recognizes that the project’s success depends on seamless coordination among Caltrans, San Mateo County, Redwood City, and the Town while integrating ongoing drainage and corridor improvement initiatives. This coordinated approach will help minimize conflicts, streamline agency reviews, and position the project for timely delivery.

Alex Lee, PE, QSD, will serve as Project Manager and will be supported by a team with extensive experience in multimodal design, traffic operations, corridor planning, and Caltrans project delivery from concept through final design. As Principalin-Charge, I will serve as the primary point of contact for this project. We appreciate your consideration and look forward to the opportunity to partner with the Town of Atherton. If you have any questions, please contact me at (925) 858-8581 or [email protected].

Sincerely,
MARK THOMAS & COMPANY, INC.

Shawn O’Keefe, PE, QSD
Executive Vice President + Principal

COVER LETTER

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 2 ends

TABLE OF CONTENTS
Cover Letter 1
Firm Introduction 3
About Mark Thomas 3
Approach 5
Management Approach 11
Project Experience 12
Work Plan 18
Key Staff 27
References 33
Project Schedule 35
Litigation 36
Disclosure 37
Professional Services Agreement 38
Fee Information Submitted separate
Appendices
Resumes

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 3 ends

FIRM INTRODUCTION

ABOUT MARK THOMAS
Mark Thomas provides civil and traffic engineering, structures engineering, transportation planning, grant/funding support, environmental compliance, construction management,
landscape architecture, and surveying services to clients throughout California. As a California corporation, our stability throughout the years is founded on our client service focus and delivering projects through a tailored approach to meet clients’ goals. This reputation is realized through the efforts of more than 500 full-time professionals within offices that are strategically located to support the communities that we live and do business in. Originating in San Jose (corporate headquarters), the firm has grown to establish additional offices in Sacramento, Fresno, Cupertino, Walnut Creek, Roseville, Oakland, Los Angeles, Long Beach, Ontario, and Irvine.

The Mark Thomas team will be led by Shawn O’Keefe,
PE, QSD, who brings extensive experience overseeing
transportation and intersection improvement projects on State highway corridors throughout California. Alex Lee, PE, QSD will be responsible for the day-to-day management of the project, serving as the primary point of contact with Town staff and driving the project to meet its schedule and budgetary goals, with PS&E completion targeted for early 2027 and construction planned to begin summer 2027.

Active Transportation
Through our work with multiple cities, counties, regional transportation agencies, and Caltrans, we have accumulated an expansive knowledge base specifically geared toward
balancing motorized and active transportation travel safety, connectivity, and access. We have delivered hundreds of complete streets and active transportation facilities throughout the state. Our projects have included Class I trails and paths, Class IV protected bikeways, Class II buffered bike lanes, ADA upgrades and road diets. We have also woven bicycle and pedestrian accessibility in our highway and interchange projects.

The projects we complete become lively community plazas, connect major bicycle and pedestrian corridors to key destinations, and enhance mobility, connectivity, transit reliability, and safety. We emphasize the importance of community engagement to understand local resident and business owner concerns and user preferences.

Familiarity with Local, State, and Federal Standards
Mark Thomas works closely with agencies on implementing transportation projects both on and off the state highway systems. We are familiar with the applicable design standards and guidelines that may be applied to this project, including the Caltrans Highway Design Manual, NACTO Urban Bikeway Design Guide, Caltrans Design Information Bulletin DIB-89 Class IV Bikeway Guidance, Caltrans Highway Safety Manual (HSM), California Transportation Plan 2040, California State Bicycle and Pedestrian Plan, Caltrans District 4 Bicycle Plan, San Mateo County Comprehensive Bicycle and Pedestrian Master Plan, as well as nationwide best practices and innovations.

MARK THOMAS AT A GLANCE
» California Corporation
» 99 years in business
» >500 employees
» 11 offices statewide
- San Jose (HQ)
- Fresno
- Cupertino
- Sacramento
- Walnut Creek
- Roseville

SERVICES PROVIDED
» Civil Engineering
» Construction Management
» District Management
» Grant Assistance
» Environmental Compliance
» Land Surveying
» Landscape Architecture & Urban Design
» Planning
» Structures Engineering

CONTACT
Shawn O’Keefe
Principal-in-Charge
[email protected]
(925) 858-8581
- Oakland
- Los Angeles
- Long Beach
- Ontario
- Irvine

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 4 ends

We Know Caltrans
Mark Thomas has an unmatched understanding of the Caltrans delivery process and their design standards and manuals. Why is this important to a complete streets project? We have the experience to support municipal agencies as they navigate the complex and often frustrating Caltrans process. Our experience as a premier interchange and highway/corridor design firm means we have the ability to develop creative geometric concepts, and deliver the planning and final design of projects governed by Caltrans. As a result, we have developed strong working relationships with Caltrans Headquarters and District 4 staff and are knowledgeable of the Caltrans HDM and the Caltrans Project Development Procedures Manual (PDPM). Further, our interchange and highway/corridor designs consider multi-modal needs, including the connectivity and safety of transit users, bicyclists, pedestrians, and the driving public. A partial list of projects that adhered to the Caltrans Project Development Process follows on the next page. We put our experience to work to help our clients deliver projects with Caltrans involvement.

We understand how to address key challenges to develop designs that meet local goals and can be approved by Caltrans staff. We work proactively with Caltrans staff to develop win-win solutions that work for both parties.

Mark Thomas has planned and delivered more than 100 Caltrans-related projects in Caltrans District 4 as shown on the map above. We were the first consultant allowed to plan and design improvements to the State Highway System, with the US 101 Widening project in Santa Clara County in 1986. Since then, we have planned and/or delivered more than 200 locally-sponsored projects on Caltrans facilities across the state, totaling more than $15 billion in improvements.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 5 ends

APPROACH

PROJECT UNDERSTANDING
The Town of Atherton (Town) is seeking a consultant team to advance safety and mobility improvements at the intersection of El Camino Real (ECR) and Selby Lane, with work that moves from feasibility refinement into final design, permitting, environmental documentation, and bidding support. The Town is considering two primary traffic control alternatives for evaluation at this location, a full traffic signal or a high-intensity activated crosswalk (HAWK)/Pedestrian Hybrid Beacon (PHB), along with supporting pedestrian, bicycle, lighting, curb ramp, and geometric improvements. Both alternatives identified will be studied and analyzed to understand how each affects pedestrian safety improvements (refuge areas, curb ramps, ADA access), lighting, signing and striping, and proposed bicycle improvements. The analysis of both alternatives will be supported by traffic analysis that builds on prior corridor study work and focuses on reducing conflicts between different modes of travel. The documented history of incidents (including the recent pedestrian hit and run that was noted in the RFP) at and near this intersection make safety improvements for pedestrian, bicycle and other vulnerable users extremely important to the Town and the traveling public. The two alternatives will also be coordinated with existing planned corridor work, future projects (including a concurrent Town drainage improvement effort) and Caltrans requirements.

El Camino Real is a Caltrans owned, operated and maintained facility. Any improvements on this corridor requires Caltrans review, coordination and approval. The proposed improvements make this intersection a perfect candidate to acquire Caltrans approval through the Design Engineering Evaluation Report (DEER) process. Along with the required DEER application and checklist, the DEER process specifically requires coordination with Caltrans Traffic Safety and completion of the Intersection Safety and Operational Assessment Process (ISOAP) analysis. Mark Thomas has had success gaining project approval from Caltrans District 4 using multiple approval processes, including the DEER process. Utilizing monthly meetings with Caltrans, We have successfully gained approval from Caltrans while maintaining an aggressive delivery schedule. We would develop a project schedule around submitting technical studies and environmental documents at regular intervals and use monthly meetings to keep Caltrans focused and on track with their review periods. This strategy keeps project momentum while gaining Caltrans approval on technical documents and reports “along the way”. When the final DEER is submitted, the supporting documents have already been approved by the Caltrans reviewing parties.

Our understanding is that this is not simply an isolated intersection improvement project. It is a safety-sensitive, multi-jurisdictional, Caltrans-facing assignment that must balance immediate pedestrian and operational needs with future corridor improvements already in motion along El Camino Real. While on the surface, the proposed intersection improvements do not seem complex, the multi-jurisdictional nature of this project requires diligent coordination.

The Town has previously identified that the project will have to integrate and coordinate an existing Caltrans Project (SHOPP Project), a Town stormwater and drainage project (ECR Stormwater and Drainage Project Phase 1), the Town ECR Complete Streets Planning Study and the ECR Grand Boulevard Initiative (GBI) Action Plan. Diligent coordination with Caltrans, County of San Mateo, the City of Redwood City, the San Mateo County Transportation Authority, and related corridor initiatives will ensure that this project is developed in a manner that does not preclude future planned improvements and minimizes “throwaway” improvements and costs.

Our approach is focused on three key drivers that will influence the success of this project: enhancing safety and mobility, integrating drainage and corridor improvements, and efficiently navigating Caltrans approvals and project delivery.

Safety & Mobility Corridor Coordination & Future-Proofing Caltrans Approval & Delivery Through our review of the project requirements, existing conditions, corridor plans, and ongoing initiatives, we have identified the opportunities, constraints, and critical considerations that will shape the project. The following pages illustrate these project drivers and our approach to addressing each one.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 6 ends

PROJECT APPROACH

DELIVERING SAFE, CONTEXT-SENSITIVE MULTIMODAL INTERSECTION

SOLUTION
We will perform detailed traffic analysis and operational evaluation to compare traffic signal and PHB
alternatives, including safety performance, operations, and corridor consistency. Both alternatives will be
advanced to a level that supports confident decisionmaking.

Pedestrian Safety
As noted in the Town’s RFP, this intersection and
surrounding area has a history of incidents. With
the recent report of a hit and run incident at this
intersection, pedestrian and bicycle safety is one
of the primary focuses of the proposed intersection
improvements. We will design and incorporate
pedestrian safety improvements, including ADAcompliant curb ramps, bulbouts to shorten crossing distances, median refuges at crosswalks, improved
crosswalk visibility, and lighting upgrades.

Two of the four corners at this intersection do not
include any pedestrian facilities. ADA-compliant curb
ramps that fit within existing Town right-of-way will be constructed at these corners. Although the northeast
corner currently has an existing curb ramp, it will be
reconstructed to meet current ADA standards. This
particular corner is also a candidate for a bulbout
to shorten crossing distance across Selby Lane to
reduce the amount of time a pedestrian interacts with
motorized vehicles.

Coordination with the Complete Streets
Vision
The ECR Complete Streets Study advanced two
different corridor design concepts that will be
studied further, shown to the right. Although both
design concepts feature different configurations for
pedestrian, bicycle and vehicular cross-sections, they
both have in common that the limits of the pedestrian
improvements (back of sidewalk) locations are intended
to remain within existing right-of-way. The proposed
curb ramps and sidewalk improvements with the Selby
Lane Intersection project will be designed with the
Complete Street Study in mind. No improvements
will be proposed that preclude potential future
improvements. As shown in the images, thoughtful
placement of intersection improvements (ADA
curb ramps, sidewalk locations, traffic signal/PHB
pole locations) within existing right-of-way can
accommodate both Complete Street design concepts. ECR Complete Streets Study:

Design Concept 1
ECR Complete Streets Study:

Design Concept 2

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 7 ends

Integration with Adjacent Projects
Our team has experience coordinating with concurrent Caltrans and local agency projects along shared corridors, including maintaining alignment with evolving designs and avoiding conflicts. In addition to the ECR Complete Streets Study, the Town has identified that there are other adjacent projects which will influence the design of the intersection improvements project. The Caltrans SHOPP Project (1W130 – 82 Bicycle Improvement Project), the El Camino Real Stormwater and Drainage Improvements Project – Phase 1 and the El Camino Real Grand Boulevard Initiative Action Plan either include the intersection with their improvements or are in very close proximity to the intersection. Similar to the Town’s Complete Streets Study, there will be overlapping elements or conflicting elements. Frequent and diligent coordination with these other projects is necessary to reduce the amount of project conflicts/throwaway and ensure smooth implementation and construction relative to adjacent improvements by others.

Caltrans State Highway Operation and Protection Program (SHOPP) Project Caltrans is developing a SHOPP Project that is approximately 1.9 miles long. Improvements include ADA-compliant pedestrian facilities (curb ramps, sidewalks), intersection crossing improvements (crosswalks, traffic signals, PHBs) and bicycle facility improvements (bicycle lanes of various classes) with the intention of improving safety for all users. Mark Thomas has experienced planning and design local agency projects and coordinating improvements with Caltrans SHOPP projects. One important strategy we have utilized is to attend Caltrans SHOPP PDT meetings. This allows Mark Thomas and the Town the ability to stay informed of SHOPP project progress and changes while simultaneously keep Caltrans informed of local agency project progress. This has assured limited project overlap, conflicts and throwaway costs.

El Camino Real Stormwater and Drainage Improvements Project The Town has identified that they have an existing design for drainage improvements at the project location. They intended to remedy the flooding issue by installing a concrete line ditch/gutter that will direct drainage to a new inlet connecting to an existing drainage system. They will also demo an existing curb and construct a new curb that will help direct drainage to an existing inlet. To the extent practical, the intersection will attempt to reuse as much of the installed infrastructure as possible. Inlets will be considered when developing the new curb lines. If possible, existing inlet can be converted to manholes to preserve drainage junctions within the existing Town drainage system.

El Camino Real Grand Boulevard Initiative (GBI) Action Plan SamTrans is planning for improvements along 25 miles of the ECR corridor.

The Town of Atherton and the project intersection is located within the project footprint. This project involves pedestrian, ADA, bicycle and transit improvements with the overall vision of a safer corridor for all users. Mark Thomas is currently under contract with SamTrans as the lead designer for this planning effort. As the lead designer for the GBI project and potentially the designer of the Town’s intersection improvements, Mark Thomas would be able to ensure that the Town is kept informed of project updates and that the GBI project receives Town intersection project updates.

Stormwater Treatment
New projects, when installing new impervious surfaces, are typically required to install stormwater treatment facilities (bioswales, bioretention areas etc). The amount of impervious surfaces being replaced with this project is very small and falls under the threshold for required stormwater treatment.

Future-Proofing
In addition to maintaining awareness of surrounding projects, our design approach is to incorporate strategies such as adaptable infrastructure and location-sensitive improvements. Forward thinking that brings high-value solutions for relatively low up front cost. As an example, constructing a traffic signal mast arm that could accommodate future signal heads. Or designing a traffic signal foundation that is capable of accommodating a future longer mast arm if the intersection were to be expanded with a future project.

Mark Thomas will
have the ability to
coordinate internally
about any potential
changes along the
ECR corridor as
they are happening
within SamTrans and
Caltrans. Instead of
reacting to decisions
that are being made
externally, concerns
that the Town can be
raised proactively to
other jurisdictions with
adjacent projects and
discussed/considered
sooner.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 8 ends

Project Initiation
(PID)
Project Approval
& Environmental
Document (PA&ED)
Final Plans
Specifications &
Estimate (PS&E)
DEER Application Encroachment Permit

DESIGN ENGINEERING EVALUATION REPORT (DEER) PROCESS
Funding: Local | Schedule 1-2 years

ENCROACHMENT PERMIT PROCESS
Funding: Local | Construction Cost < $1m | Schedule 3-6 months after design completion

STANDARD PROCESS
Funding: Any | Schedule 3-5 years For project over $3 million. Caltrans Project Manager is assigned to process oversight and
reviews.

For non-complex projects that do not require
structures. Caltrans Project Manager is
assigned to process oversight and reviews.

For project under $1 million within the State
right-of-way. Over-the-counter reviews
through the Caltrans Permit Office.

PSR or PSR/PDS Project Report,
Env. Document Encroachment Permit
Encroachment Permit

NAVIGATING CALTRANS APPROVALS THROUGH THE DEER PROCESS
Caltrans Processing
Caltrans approval is critical because the project is located at the intersection of Selby Lane and El Camino Real. They will be the oversight agency for project improvements in their right-of-way; and if federal funds are included, Caltrans is the acting Federal Lead Agency for processing and approving the National Environmental Policy Act (NEPA) Categorical Exclusion. Based on Caltrans policy, there are three ways to obtain Caltrans approval: their Standard Process for oversight projects, a streamlined Design Engineering Evaluation Report (DEER) process, and the Encroachment Permit process. The process selected will be based on project complexity and/or the cost of construction within the State right-of-way. These are summarized in the graphic as follows:

We recommend meeting with Caltrans early in the process to define the Caltrans approval process. Getting confirmation from Caltrans as one of the first orders of work sets expectations with Caltrans for the technical studies and reports required to gain project approval. This project meets all the requirements for the Caltrans DEER process.

In order to use the DEER process, we recommend the following:

1. Hold a meeting to discuss the project with appropriate Caltrans staff.

2. Submit a letter to Caltrans District 4 Director, Dave Ambuehl, requesting authorization to use the process. The letter must address how the project meets the
qualifications for the process as outlined
in Chapter 9 of the Caltrans Project
Development Procedures Manual.

3. Once Caltrans has approved the use
of the DEER process, a DEER with
supporting documentation must be
prepared and submitted to Caltrans.

The DEER document is a streamlined
version of the Standard Process. The
DEER is submitted to Caltrans and will be
conditionally approved to provide Project
Initiation Document and Project Approval
Document clearance. Final DEER
approval will be granted upon approval of
the final PS&E documents. Once all final
approvals are in place, Caltrans will sign
the approved DEER, which authorizes
the Caltrans office of Permits to issue a
construction Encroachment Permit.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 9 ends

Design Engineering Evaluation Report
It is expected that Caltrans will require the following supplemental studies to be included with the project
DEER application:
» Vicinity and Location Map
» Project Plans
» Right-of-Way Data Sheet (assumes no ROW acquisition)
» Initial Site Assessment
» Storm Water Data Report
» Environmental Document
In addition to the above required attachments, the
following attachments may also be applicable:
» Geotechnical Report
» Design Standard Decision Document
– While possible that this may be required, we do not
see any potential design features that would require
this document, and anticipate designing the project
to be in compliance with all applicable Caltrans
Design Standards, thus eliminating the need for this
document/process
» Complete Streets Checklist
» Transportation Management Plan (TMP)
» Traffic Impact Report
» Intersection Safety and Operational Assessment
Process (ISOAP)
» Cost Estimate
Traffic
We will coordinate early with Caltrans traffic safety staff and prepare supporting documentation that aligns with Caltrans expectations, reducing rework. The ISOAP consists of two stages. This project will be required to complete Stage 1 Screening but may be exempted from Stage 2 Detailed
Assessment. The two stages are described below:
» Stage 1 Screening applies to this project because the Town proposes to change the existing intersection
traffic control from minor approach STOP control to
a signal or pedestrian hybrid beacon (PHB). Stage 1
is to be completed and is submitted as a technical
report attachment to the DEER. The Stage 1 ISOAP
stage and uses an assessment methodology focusing
on multimodal safety, e.g., Safety Performance
for Intersection Control Evaluation (SPICE) or Safe
System Intersection Methodology.
» Stage 2 Detailed Assessment may be undertaken if
there is more than one strategy identified out of Stage 1 Screening, e.g., full traffic signal, PHB and roundabout.

If required, Stage 2 is to be completed and requires
quantification of the project’s benefit / cost ratio. Our proposed budget limits our effort to mesoscopic traffic model software, i.e., Synchro / SimTraffic.

Stage 2 may be deleted if Caltrans accepts the findings of the Stage 1 Screening process to proceed with a traffic signal or PHB without further analysis of a roundabout or other intersection reconfiguration.

The Stage 1 assessment includes:
» Identification of desired project outcomes
» Assessment of non-motorized travel including crash
records and conformance with SSA principles of
modal separation
» Assessment of transit and freight access.
» Assessment of available right-of-way
» Estimated multimodal safety and delay under
proposed traffic control proposals
» Summary of the overall intersection measures of
effectiveness (MOE), e.g., daily person hours of delay
(DPHD), volume/capacity ratio, queuing, or another
measure as directed by the District Traffic Operations
Engineer
» Completed Stage 1 ISOAP form and supporting
documentation
The Stage 2 assessment includes:
» Identification of whether there is more than one
feasible improvement strategy (signal, PHB,
roundabout, or access change)
» Completion of a detailed safety analysis using
Highway Safety Manual methodologies and
supplemented by SPICE and SSA
» Operational analysis using traffic models
» Plan sketch diagrams of viable improvement strategies » Calculations of improvement costs and ROW impacts
» Calculations of the benefit to cost ratio (B/C) based on HSIP or other benefit calculation methodologies
» Completed Stage 2 ISOAP form and supporting
documentation
Maintain Momentum Through Proactive
Coordination
In order to keep the approval process on schedule, we
will establish regular coordination with Caltrans reviewers, track review timelines, and maintain communication
to keep approvals progressing. An effective strategy
for doing this that we have used with multiple Caltrans approvals is to establish a monthly PDT meeting with
the Caltrans PM and their functional unit reviewers. This consistent touchpoint allows the design team to monitor Caltrans’ progress on document reviews, and have an
open dialogue for any questions/comments, with the
intention of streamlining document reviews. This monthly touchpoint allows for a consistent event for conflict
resolution (if any), and allows for the Town and the design team to stress the importance of schedule and timely
reviews. While the Town and the design team cannot
dictate Caltrans’ timeline for reviews, this proactive
coordination and communication strategy allows for
consistent discussion with Caltrans reviewers.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 10 ends

MANAGING MULTI-JURISDICTION COORDINATION AND PUBLIC

ENGAGEMENT
The project requires coordination with multiple agencies and includes public outreach, stakeholder meetings, and environmental documentation. The Town will lead outreach, with consultant support.

Multi-Agency Coordination
The west side of El Camino Real is within the Town of
Atherton’s right-of-way while the east side of El Camino Real is within the County of San Mateo’s right-of-way.

The intersection being partially within two jurisdictions requires that the project team establish and maintain a protocol for multi-agency coordination. Mark Thomas
will facilitate and host regular coordination meetings with the Town and the County to ensure that both parties are consistently aligned with project decisions and informed of status within the Caltrans approval process.

Effective Public Engagement
One of the main elements to ensure the success of a
project is for the community to continue to support the project. Public outreach will be a critical component to inform members of the community about the project
and to receive feedback. The community is socioeconomically diverse and therefore so are their wants, needs, and opinions. Mark Thomas will support the
Town’s public outreach efforts by preparing clear, concise materials and support public meetings to communicate
project benefits, describe alternatives to stakeholders and note public comments and concerns.

Environmental Clearance
We will prepare the necessary CEQA/NEPA documentation and will seamlessly integrate the environmental and design processes to ensure consistency and efficiency. We anticipate the environmental clearance document will be a Categorical Exemption / Categorical Exclusion (CE/CE), and the environmental team will work closely with the design team to proactively identify design elements that may require a higher level of clearance, so the project design can be optimized to minimize environmental clearance requirements wherever possible.

Balance Design Advancement with Approval
Progress
Submitting technical documents and forms to Caltrans
as they are completed allows for the Caltrans review
team to review, comment and approve documents as
the schedule progresses. Waiting until the entire DEER
Application and supporting technical documents are
complete may create avoidable delays to the approval
schedule. Acquiring approvals of technical reports as
they are completed, streamlines the approval of the
final document. Instead of reviewing all documents at
once, the supporting technical documents to the overall DEER are already approved by the time the DEER is
submitted to Caltrans, significantly reducing the amount of time needed to approve the final document.

Drainage Constraints
The south west side of the intersection exhibits flooding issues in its current condition. As acknowledged above, the Town has an existing project in design that intends to address this drainage issue. The curb ramps and sidewalk in this area will be designed to maintain the existing
drainage pattern to reuse and preserve as much of the
drainage facilities installed with the Town Stormwater and Drainage Improvements project practical. The locations of the existing inlets will be considered when developing the new curb return alignments in the attempt to preserve the newly installed infrastructure.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 11 ends

MANAGEMENT APPROACH
In addition to a sound technical approach, we have found that the cornerstone of a successful project delivery is for Mark Thomas and our team members to operate as a true extension of Town staff. Mark Thomas implements a proactive, collaborative approach to managing projects, with close attention to meeting design goals, budget constraints and schedule targets. We have developed a proven and effective management approach that will be utilized for this project, which includes:

Active Project Schedule Management. Maintaining an accurate, up-to-date project schedule is critical to the overall success of a project and has a direct correlation to maintaining project budgets. Our project manager, Alex Lee, will be responsible for controlling project design efforts and deliverables by developing a comprehensive critical path method (CPM) schedule that identifies all necessary tasks and interrelationships required for a project. To keep us on track and provide transparency across the project team we will be updating the schedule regularly to track progress closely.

Enhanced Communication with Team Members. Our clients can attest to our responsiveness, our proactive approach, and our ability to work collaboratively with agency staff. Establishing open channels of communication and building a strong working relationship between Town staff and Mark Thomas will enhance communication throughout the project. We will hold regular PDT meetings to report on and monitor progress. These meetings will include Mark Thomas, key Town staff, and other stakeholders. Progress and coordination meetings will follow a set agenda and will review action items and key milestones. Meeting summaries and action item lists will be distributed soon after the meeting. Mark Thomas will also be available to hold executive briefings (as needed) to inform the Public Works Director, the Town council, or other critical Town staff of project status and issues.

Effective Cost Control. Engineering design costs will be controlled through active management of design team activities, frequent monitoring of time spent and early identification of any design issue affecting project costs. Control of project costs and unnecessary design changes are also important elements of any project. It is our duty to inform the Town as soon as possible of any potential or proposed design revisions that will affect the established scope, schedule, or budget. Keeping all parties informed of any potential issues/changes in a timely and continuous manner through regular communication is vital to controlling cost and schedule. We intend to minimize impacts by identifying issues early in the process by conducting weekly budget reports so we can track costs against our progress in real-time and adjust before issues arise. This approach has been effective on many recent projects.

Auditable QA/QC Documentation. Mark Thomas believes that QA/QC is a company-wide effort. A QA/QC person will develop and oversee our QA/QC program for this project. All team members will adhere to this Plan and each of our team members supports the idea that it is our responsibility to produce high-quality products that will result in developing a clearly-defined and cost-effective project. We will operate under a Total Quality Management system of which a specific QC Plan is only a part of the overall system. The Total Quality Management program is a continuous process, used not just at project milestones, but on a regular basis.

DISCIPLINE

REVIEWS
PERFORMED BY:

Technical Leaders
GOAL:

To validate all
components within a
discipline, including
specifications, plans,
studies, reports,
standards conformance,
quantities, estimates,
and other documents

INTER-DISCIPLINE

REVIEWS
PERFORMED BY:

Technical Leaders
Project Managers
GOAL:

To provide consistency
among disciplines by
eliminating conflicts and
promoting collaboration
in the production of all
engineering documents
related to the project

INDEPENDENT

REVIEWS
PERFORMED BY:

Technical Experts
Constructibility Team
GOAL:

To use independent peer
review teams to evaluate
project components
for thoroughness,
completeness and
adherence to project
goals and schedules

QUALITY

ASSURANCE
PERFORMED BY:

Quality Manager
GOAL:

To verify that the quality
control process conforms
with procedures prior to
client submittal, including
QA documentation,
closeout checklists,
signatures and audits

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 12 ends

PROJECT EXPERIENCE
At Mark Thomas, we are proud of our success delivering thoughtful, context-sensitive transportation improvements in communities with high expectations for design quality, safety, and minimal disruption such as Atherton. Our experience includes multimodal corridor enhancements, bike/pedestrian improvements, and multi-jursidictional projects that require careful coordination with agencies, stakeholders, and the public. The following projects reflect work similar in scale and complexity to the Atherton effort and demonstrate our ability to develop solutions that enhance mobility while respecting community character and environmental constraints.

Grand Boulevard Initiative (GBI)
San Mateo and Santa Clara Counties
The Grand Boulevard Initiative (GBI) is a coalition of 14 cities, San Mateo and Santa Clara counties, two transit agencies, two congestion management agencies, Caltrans, and regional and local stakeholders. Mark Thomas has been very involved with SamTrans, Caltrans and multiple cities in implementing the GBI vision, which is to help El Camino Real (SR 82) achieve its full potential as a place for residents to work, live, shop and play by creating links between communities and providing facilities that promote walking, bicycling, and transit use. Mark Thomas has designed several GBI projects to revitalize the ECR corridor, providing conceptual design, environmental clearance, PS&E, and construction support. Design goals include complete street concepts, expanded bike lane and pedestrian facilities, green infrastructure design, and aesthetic improvements. Each project required extensive coordination with Caltrans, host, and adjacent cities.

Grand Boulevard Initiative Phases I, II, and III, City of South San Francisco - As part of the GBI, Mark Thomas provided PID and PA&ED approval, PS&E, and design support during construction for the improvements to El Camino Real at the Arroyo Drive intersection to Chestnut Avenue (Phase I), from McLellan Drive to Kaiser Way (Phase II), and Arroyo Drive to Kaiser Way (Phase III) in South San Francisco. The projects include providing shorter, more direct and visually enhanced crosswalks with sidewalk bulbouts, median refuge areas, landscaped medians, new vegetated bioretention area, ADA curb ramp improvements, and upgraded traffic signals with pedestrian countdown features. The bus stops were replaced with wider bus bulbs for

PROJECT STAFF
Alex Lee (Project Manager)
Shawn O’Keefe
Jason Fong
Aaron Seitz
Christopher Ko
Brianna Bohonok
Danielle Keith
Christine Anderson
Deanna Gibson

SUBSONSULTANTS
Crawford & Associates, Inc.
- geotechnical engineering
services and hazardous materials
assessment support
Associated Right of Way Services,
Inc. (AR/WS) - right-of-way support
and real estate services

REFERENCE
South San Francisco
Matthew Ruble
Principal Engineer
400 Grand Ave
South San Francisco, CA 94080
[email protected]
(650) 829-6671

PROJECT ELEMENTS
Multi-Agency Coordination
Complete Streets Planning
Concept Development
Initial Design
Preliminary Engineering
Bicycle/Pedestrian Updates
Transit-Oriented Improvements
Public Outreach
Green Infrastructure
Stormwater Management
Median Improvements
Landscaping Enhancements
Urban Design / Streetscape
Improvements
Sustainability & Climate Resiliency
Caltrans Corridor Coordination
Context-Sensitive Solutions
Corridor Revitalization

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 13 ends

improved access and gathering areas. Bicycle access was accommodated with striped shoulders and bike pockets extending down to the Chestnut/Westborough intersection. Mark Thomas prepared a DEER to secure Caltrans’ approval of the proposed design for the Phase III improvements. Phase I, II, and III are all constructed.

El Camino Real/28th to 31st Avenue Streetscape (ECR Master Plan), City of San Mateo - As part of the GBI to revitalize the ECR corridor, Mark Thomas prepared the PS&E for enhancements along ECR between 28th and 31st Avenue including: a new curbed median with trees and low-growth landscaping, a new irrigation system, sidewalks, median refuge areas, pedestrian-scale lighting, and traffic signal modifications. The new decorative pedestrian lighting and landscaped median along the length of the project helped to create a new identity for the area, inviting increased bicycle activity with a fresh pavement overlay and new striped shoulder. The project transformed both 31st and 28th Avenues into “themed” intersections with enhanced crosswalk paving treatments, streetscape features and furniture that compliment and further the vision and goals to upgrade ECR into a Grand Boulevard. Mark Thomas assisted the City in obtaining the federal E-76 approval for construction funding including approval of fact sheets, right-of-way certification and encroachment permit. Construction was completed in summer 2013.

El Camino Real/Arroyo Avenue Intersection, City of San Carlos - Mark Thomas provided final PS&E for complete streets and multimodal streetscape enhancements at the ECR/Arroyo Avenue intersection funded through a One Bay Area Grant (OBAG). Improvements included high-visibility crosswalks, widening sidewalks with bulbouts and new curb ramps, roadway restriping, a new plaza area, and replacing the ECR southbound left-turn lane with median trees/landscaping and a median pedestrian refuge. Accessible pedestrian push buttons and countdown features are incorporated for the traffic signal, new pedestrian scale lighting, new streetscape furniture, and a plaza gathering area will also be added. A new bus bulb and shelter will enhance transit facilities while striped shoulders will better accommodate bicyclists along ECR. This project will also serve as a model for incorporating the vision of the GBI into future projects along the ECR corridor. Mark Thomas assisted the City with the E-76 funding application, public meeting, and construction support, and worked collaboratively with Caltrans to get environmental clearance and approval of fact sheets, PEER, right-of-way certifications, and encroachment permit.

El Camino Real/Stanford Avenue Intersection Streetscape, City of Palo Alto - Mark Thomas worked collaboratively with the City of Palo Alto, Stanford University, Caltrans, and local businesses to redesign a multimodal, pedestrianand bike-friendly intersection that meets Caltrans safety standards while enhancing aesthetics. We secured federal E-76 approval for construction funding and managed all civil design, including street geometry, sidewalk bulb-outs, utility relocations, decorative signals and lighting, drainage improvements, and landscaping. Key features include a landscaped median, plaza seating, and traffic-calming measures such as narrowed lanes and ornamental streetscape elements. Traffic calming measures were designed to offer visual cues to drivers that they are entering an area of increased pedestrian activity and are encouraged to drive more carefully. The intersection improvements provide more safety for pedestrian and bicycle crossings. Mark Thomas managed the environmental consultant in preparation of CEQA/NEPA compliance documents. NEPA memos were required by Caltrans Local Assistance for equipment staging, traffic, tree removal, water quality, and hazardous materials.

Crawford & Associates: Geotechnical investigations, hazardous materials screening, pavement assessment, and preliminary geologic/seismic evaluation.

AR/WS: Right-of-way impact analysis, acquisition planning, property ownership research, utility coordination support, and planning-level ROW cost estimating.

El Camino Real/Stanford Avenue El Camino Real/28th to 31st Avenue

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 14 ends

Treat Boulevard Corridor Improvements
Walnut Creek
Mark Thomas is providing civil, traffic, and geotechnical engineering design services to the Contra Costa County Public Works Department (CCCPWD) for improvements along Treat Boulevard from North Main Street in Walnut Creek to Jones Road in unincorporated Contra Costa County, spanning approximately 2,400 feet. This project is focused on advancing multimodal safety, connectivity, and corridor efficiency by reconfiguring the roadway to reduce vehicle weaving conflicts associated with free right-turn lanes while enhancing access between the Contra Costa Centre Transit-Oriented Development (TOD) and the existing Class II bicycle network.

Treat Boulevard currently operates as a high-volume regional arterial providing direct access to I-680, but its auto-oriented design presents significant safety and mobility challenges for non-motorized users. With a posted speed limit of 35 mph, heavy peak-hour traffic, and roadway segments ranging from eight to nine lanes, pedestrians and bicyclists face substantial barriers. Wide intersections requiring crossings of 60 to 145 feet increase exposure and delay, while existing Class III bicycle facilities require cyclists to share lanes with highspeed traffic, resulting in reduced comfort and elevated collision risk.

The proposed improvements will address these deficiencies by implementing a Class I shared use path and Class IV buffered bicycle lanes, achieved through lane reconfiguration, removal of free rightturns, curb reconstruction, and restriping. Additional elements include ADA-compliant curb ramp upgrades, modification and relocation of three traffic signals, and signal timing optimization to improve corridor operations in both directions. The project will also require significant utility coordination and relocation. Coordination with the City of Walnut Creek and Caltrans will be critical, as the project will be delivered in accordance with the Design Engineering Evaluation Report (DEER) process, supporting streamlined approvals and successful project implementation.

REFERENCE
Contra Costa County Public Works
Department (CCCPWD)
Jenna Caldwell
Senior Civil Engineer
1025 Escobar Street
Martinez, CA 94553
[email protected]
(925) 313-2020

PROJECT ELEMENTS
DEER Process
Feasibility Study
Initial Design
PID Development
Data Collection & Analysis
Concept Alternative Evaluation
Bicycle/Pedestrian Improvements
Multimodal Connectivity
Pedestrian Safety Enhancements
Interchange Area Improvements
Funding Strategy Development
Caltrans Coordination & Approval

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 15 ends

Windsor Downtown Bicycle and Pedestrian
Crossing
Windsor
Mark Thomas completed the 30% design for the Old Redwood Highway Bike/ Pedestrian Crossing project for the Town of Windsor (Town). The existing condition of the Old Redwood Highway consists a of one-way bike lane (Class II) in both directions. The existing pedestrian facilities are sidewalks within the underpass separated from the road by grade, structural columns and a chain link fence. On the north side of Old Redwood Highway, there are existing retaining walls under the structure that vary from three to six feet in height. The south side of the underpass has a concrete curb that separates the sidewalk from a slope paving. This project proposes to construct new retaining walls to widen the sidewalk area to accommodate a two-way protected bicycle path and separate pedestrian area. Other improvements include a planted buffer between the existing roadway and the proposed bicycle facility. Mark Thomas also reviewed whether a two-way protected bicycle path is needed on both sides of the roadway or on the northside only. The project includes coordination with Caltrans and submitting a DEER Process confirmation letter. Ultimately, Caltrans determined the project to be more appropriately processed through the PSR-PR process.

PROJECT STAFF
Alex Lee (Project Manager)
Aaron Seitz
Christopher Ko

REFERENCE
Town of Windsor
Carl Euphrat
Deputy Director Of Engineering
9291 Old Redwood Hwy #400
Windsor, CA 95492
[email protected]
(707) 838-1195

PROJECT ELEMENTS
Caltrans Approval Process (PSR-PR)
Initial Design
30% Concept Development
Bicycle/Pedestrian Improvements
Protected Two-Way Bicycle Path
Pedestrian Safety Enhancements
Underpass Widening
Retaining Wall Design
ADA/Curb Ramp Improvements
CEQA/NEPA Clearance
Final PS&E Development
I-280/Westborough Interchange
South San Francisco
Mark Thomas is currently supporting the Project Initiation Document (PID) phase for the Junipero Serra Boulevard and I-280 Westborough Boulevard Pedestrian and Bicycle Connectivity and Safety Project. This phase builds on the foundation established during the feasibility study, which focused on enhancing multimodal transportation access and improving safety for cyclists and pedestrians along Junipero Serra Boulevard, Westborough Boulevard, and the I-280 interchange. The project is divided into four segments: Junipero Serra Boulevard, Westborough Boulevard (East and West), and the I-280/Westborough Boulevard Interchange, each designed to incorporate Complete Streets principles and minimize environmental impacts.

During the feasibility study, Mark Thomas led efforts in data collection and analysis, developed a comprehensive project base map, and identified conceptual alternatives for corridor improvements. Our team prepared refined geometric designs, conducted constructability assessments, and developed cost estimates for selected alternatives. We also analyzed regional, state, and federal funding opportunities for highway, safety, and active transportation improvements, evaluating the project’s competitiveness for these programs.

Building on this work, Mark Thomas is now advancing the PID phase by refining concepts, coordinating with Caltrans and local stakeholders, and preparing documentation for PSR-PDS to help advance to the PA&ED phase. Our approach combines technical expertise, environmental compliance, and strategic planning to deliver safer, more connected corridors for all users while positioning the project for successful funding and implementation.

PROJECT STAFF
Ryan Bissegger
Deanna Gibson
Brianna Bohonok

REFERENCE
South San Francisco
Lawrence Henriquez
Senior Engineer
400 Grand Ave
South San Francisco, CA 94080
[email protected]
(650) 829-6668

PROJECT ELEMENTS
DEER Process
Feasibility Study
Initial Design
PID Development
Data Collection & Analysis
Concept Alternative Evaluation
Bicycle/Pedestrian Improvements
Multimodal Connectivity
Pedestrian Safety Enhancements
Interchange Area Improvements
Funding Strategy Development
Caltrans Coordination & Approval

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 16 ends

Bolinas Lagoon Wye Wetlands
Marin County
Mark Thomas provided professional engineering services for the Bolinas Lagoon Wye Wetlands project in Marin County, which included the redesign of a critical bridge structure and roadway improvements at the intersection of SR 1 and Olema Bolinas Road. The project supported the restoration of Bolinas Lagoon’s wetland and riparian habitat, improved fish and amphibian passage, and raised the roadway and bridge to accommodate nearly six feet of anticipated sea-level rise. As one of only 37 ramsar-designated wetlands in the U.S., Bolinas Lagoon provides over 1,100 acres of critical habitat for migratory birds, Central California Coast Steelhead trout, black rail, and the California red-legged frog. Coordination with Caltrans, Marin County Parks, County Public Works, and resource agencies has been essential to the project’s success.

The redesigned bridge consisted of a three-span post-tensioned concrete slab with a thicker superstructure, discontinuous catcher bent caps, and vertical restraining pins to address seismic and tsunami hazards. It is designed to accommodate up to five meters of fault rupture and tsunami wave loading associated with a 5% probability in 50 years event. The abutments are short diaphragm types without foundations, with spans 1 and 3 cantilevered from Piers 2 and 3. Foundations for these piers use largediameter cast-in-drilled-hole piles designed for tsunami-induced scour.

Mark Thomas conducted an Intersection Control Evaluation (ICE) at the SR 1 and Olema Bolinas Road junction, developed preliminary construction phasing and cost estimates, and prepared 30% and 60% PS&E packages for roadway improvements. The team also participated in progress meetings with Caltrans, Marin County, and other stakeholders to support project development and coordination. The roadway design was closely integrated with the environmental goals of the project, balancing transportation safety, sea-level rise adaptation, and ecological restoration.

Crawford & Associates: provided geotechnical and hazardous materials services, including site assessments, subsurface and soil investigations, engineering geology evaluations, and analysis of settlement, liquefaction, contamination, and other project constraints to support design and permitting.

The project received Caltrans approval through the DEER process.

PROJECT STAFF
Marshall Moore

SUBSONSULTANTS
Crawford & Associates, Inc.
- hazardous materials and
geotechnical

REFERENCE
Marin County
Tara McIntire
Projects & Design Manager
1600 Los Gamos Drive, Suite 275
San Rafael, CA 94903
[email protected]
(415) 521-8059

PROJECT ELEMENTS
DEER Process
Initial Design & Alternative Evaluation
Intersection Control Evaluation (ICE)
Roadway Improvements
Bridge Replacement
Environmental Restoration
Fish & Amphibian Passage
Improvements
Sea-Level Rise Adaptation
Multi-Agency Coordination
30% and 60% PS&E Development

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 17 ends

SR 116/West Cotati Avenue Reconfiguration
Project
Cotati
Mark Thomas is providing preliminary engineering services to assist the City of Cotati (City) in developing a vision for a safer, connected, cohesive SR 116 corridor from Alder Avenue to Redwood Drive.

Scope of work includes the development of a conceptual plan and preliminary engineering to help the City set expectations with adjacent developments and share with other stakeholder groups and processes in such a way to anticipate the upcoming countywide active transportation plan.

Mark Thomas subsequently developed the 35% plans and accompanying construction cost estimate and initiated the Caltrans DEER approval process. The project will widen Highway 116 on both sides of the proposed intersection to create new turn pockets to increase safety and reduce backup along the mainline due to vehicle queuing. The improvements also include the installation of bicycle and pedestrian features to improve community connectivity and safety as Highway 116 is a busy regional highway with no pedestrian or bicycle crossings west of Redwood Drive.

PROJECT STAFF
Shawn O’Keefe

REFERENCE
City of Cotati
Damien O’Bid
City Manager
201 West Sierra Avenue
Cotati, California 94931
[email protected]
(707) 792-4685

PROJECT ELEMENTS
DEER Process
Conceptual Design
Initial Engineering
Intersection Reconfiguration
Roundabout Design
Bicycle/Pedestrian Improvements
Community Connectivity
Safety Improvements
Turn Pocket Improvements
Highway Widening
Caltrans Permitting & Coordination
Corridor Visioning and Multimodal
Planning

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 18 ends

WORK PLAN
TASK 1. PROJECT

MANAGEMENT AND

MEETINGS
Task 1.1. Project Management and
Support
Mark Thomas will provide ongoing general project
management for this project, including coordinating
subconsultant activities and submittals. General project management will also include organizing and maintaining files and records to track correspondence, contractual
matters, data requests, transmittals and other pertinent data.

Mark Thomas will prepare monthly status spreadsheets
with each invoice submitted for payment. The
spreadsheet will show the original budget, reallocated
budget, amount spent-to-date, amount spent this
period, and percentage spent-to-date for each task.

Accompanying the spreadsheet will be a brief written
summary of work (typically one page long) that has been accomplished in the previous month, anticipated work for the next month.

Mark Thomas will coordinate design activities with
consultant team members and stakeholders through
regular communication via telephone calls, emails and
other correspondence. We will also prepare, update,
maintain and distribute a CPM schedule for task order
activities. Schedule updates will be distributed on a
monthly basis. The initial schedule will be prepared
for and approved by The Town at the outset of the
task order. It is assumed the duration of this project is approximately twelve (12) months.

DELIVERABLE(S):
» Monthly progress reports and invoices (up to 12)
» Monthly CPM schedule updates (up to 12)
» All deliverables to be submitted in pdf format unless specifically stated otherwise
Task 1.2. Client Meetings
Mark Thomas will attend a project kick-off meeting and
bi-weekly “check-in” meetings via conference call with
the Town. This task includes preparation of agendas,
an email summary of meeting notes and a log of action
items. The project Critical Path Method (CPM) schedule
note above will discussed reviewed during client
meetings.

DELIVERABLE(S):
» Client Meeting Attendance (bi-weekly, up to 24
meetings)
» All deliverables to be submitted in pdf format unless specifically stated otherwise
Task 1.3. Caltrans PDT Meetings
As a part of the Caltrans DEER process, Mark Thomas
will schedule and attend monthly PDT meetings.

Caltrans PDT meetings will include representatives
from the Mark Thomas team, The Town, Caltrans and
other stakeholders as directed by The Town. Technical
document progress and review progress will be
discussed during this monthly PDT meeting. This task
includes preparation of agendas, an email summary of
meeting notes and a log of action items. The project
Critical Path Method (CPM) schedule identified below will be distributed and reviewed during PDT meetings.

DELIVERABLE(S):
» Caltrans PDT Meetings (monthly, up to 8 meetings)
Task 1.4. Quality Assurance/Quality
Control
Mark Thomas will conform to our Quality Management
Manual (QMM) while performing QA/QC for the project.

All deliverables, as appropriate, will go through an
independent QA/QC review before delivery to the Town.

DELIVERABLES
» Deliverable 1
– Deliverable 2
» Deliverables 3
TASK 2. REVIEW/COLLECT

EXISTING CONDITIONS,

DOCUMENTATION AND

INFORMATION
Task 2.1 Data Collection and Review
Mark Thomas will request, collect, assemble, and
review all pertinent and available project information, including, but not limited to, prior reports, environmental documents, environmental technical reports, CAD files
and drawings, and other relevant correspondence.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 19 ends

Mark Thomas will send “A Letters” on Town letterhead to utility companies with facilities in the project area project, requesting updated copies of their existing facility maps.

Mark Thomas will prepare updated existing base utility
mapping.

Encroachment permit applications will be prepared on
Town letterhead for submittal to Caltrans and San Mateo County for field work that will include visual observations of the project area.

Task 2.2 Right-of-Way Survey
Mark Thomas will perform a field survey to locate the
necessary monumentation to establish the right-ofway lines of El Camino and Selby Lane in Atherton. Our research indicates that Parcel Maps (PM), Records of
Survey (RS) & Tract Maps (TM) are publicly available from the San Mateo County Surveyors office will be sufficient to complete this survey. It is our understanding that no other monument ties to other maps will be necessary to
complete this project other than those publicly available.

Should a material discrepancy be found or evidence of a dispute with adjoiners be discovered, Mark Thomas will
stop work under the current scope and discuss options
with the Town to move forward. Once the locations of
the right-of-way lines are established based on the field evidence collected, Mark Thomas will plot this boundary in a CAD file that will serve as the basis for design. Mark Thomas assumes current title reports will be required
to show the locations of easements. Mark Thomas has
included the acquisition of 4 preliminary title reports at a cost of $750 per report. Only easements shown in the
title reports will be mapped. It is assumed that boundary evidence necessary to define the boundary will be readily available. This Boundary Survey scope is limited to one (1) days of fieldwork.

It is assumed no right-of-way or easement acquisitions
will be required for the project.

Task 2.3 Topographic Survey
Mark Thomas will perform a field survey to establish
control to facilitate topographic surveys of the site.

Inter-visible local project horizontal control (NAD83) and vertical control (NAVD88) will be established within each segment based on existing monument networks and
benchmarks. Control point coordinates, basis of bearings and coordinates, and benchmark notes will be provided
to show on final plans.

In addition, Mark Thomas will collect pertinent
accessible above ground features that will be located
and documented using conventional ground survey
techniques. Ground visible features to be captured
include, but are not limited to sidewalks, curb and gutter, driveways, curb ramps, fences, private utilities, storm and sewer facilities, trees, street lighting, signing, striping, and markings within the project limits. Storm and sewer will be dipped to determine invert elevations and pipe diameters within the streets around the site. Field crews will rely upon markings on utility feature lids. No utilities will be dipped other than sewer and storm. Detailed topographic surveys are limited to two (2) days of field work for a 2 person crew.

DELIVERABLES
» Field survey
– CADD file with topographic data drafted for use by
engineering team
» CADD file depicting retraced ROW
TASK 3. FINALIZE

CONCEPTUAL DESIGN

DOCUMENTS
Task 3.1. Finalize Conceptual Design
Documents (Geometric Approval
Drawings)
Working with the Town and our Design Team, we
will review and refine develop potential intersection
configurations for the Selby and ECR Intersection.

We will explore different combinations of geometric
configurations (sidewalk, crosswalk, median refuge, curb ramp) and both intersection traffic control devices. We will provide a qualitative assessment of the feasibility and appropriateness of the various combinations of
inputs. Conceptual designs will be presented as technical geometric approval drawings (GADs).

Based on the feedback in response to the presented
conceptual design alternatives, we will refine up to two alternatives. For each alternative, we will conduct an
operational and safety assessment and summarize
results (e.g. LOS summary, queueing reports, conflict
analysis, etc.) in a graphic or table for Town review. The results of this analysis will be used to inform a selection of a preferred alternative and inform the Caltrans ISOAP Report to the extent feasible. We will also prepare a rough order of magnitude cost estimate for each alternative to understand relative costs between alternatives.

Ahead of beginning the DEER process, the preferred
alternative will be selected and featured as the single alternative for the DEER application.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 20 ends

DELIVERABLES
» Draft and Final Conceptual Design Exhibits
TASK 4. PUBLIC OUTREACH

AND COMMUNITY

ENGAGEMENT SUPPORT
This task includes outreach to key stakeholders and the broader community.

Task 4.1. Public Outreach and
Community Engagement
Mark Thomas will support the Town for Public Outreach
for the project. Tasks will include attending two, in
person stakeholder/community meetings and providing
supporting documents for the meeting. Documents may
include exhibits, poster boards, fact sheets, PowerPoint presentations. It is assumed that the Town will lead
developing the outreach plan. Developing the public
outreach plan is excluded from this scope of services. If developing the public outreach plan is needed, it can be provided as an additional service.

DELIVERABLES
» Meeting Attendance (Up to two in person meetings)
» Support Materials
TASK 5. PROJECT DESIGN

AND PERMITTING
This task also includes preparing and obtaining Caltrans Permitting and supporting technical documents. This task includes preparation of construction documents, (plans, specifications, and estimate, or PS&E) of the selected
alternative. For the purposes of this proposal, this scope assumes that a traffic signal will be designed.

Task 5.1. Technical Reports
Task 5.1.1. Geotechnical Reports
Task 5.1.1.1. Phase 1 Initial Site Assessment
Crawford will prepare an ISA to evaluate the project
alignment and adjacent properties for evidence of
recognized environmental conditions (RECs) and/
or potential RECs that may significantly impact the
project. The ISA will be prepared in accordance with
ASTM E1527-21 and Caltrans’ Standard Environmental
Reference, Chapter 10, and will include the following
elements.
» Physical Setting Review: The ISA review will include a summary of geologic conditions underlying the project
alignment based on readily available geologic mapping
from the US Geological Survey and the California
Geological Survey (including an evaluation for naturally occurring asbestos); a summary of hydrogeologic
conditions (including depth to groundwater and
regional groundwater flow, if readily available) based on information from websites maintained by the State of
California; and a summary of soil conditions based on
readily available soil mapping from the US Department
of Agriculture Natural Resource Conservation Service.
» Historical Land Use Review: Environmental Risk
Information Service (ERIS) will provide historical
aerial photographs, USGS topographic maps, Town
directories, and Sanborn fire insurance maps (where
available) for the project alignment and vicinity.

Crawford will review these data to develop a history
of general property uses for the subject property and
surrounding parcels back to the subject property’s first development, or 1940, whichever is earlier.
» Records review: ERIS will also conduct a
computerized search of reasonably ascertainable
federal, state, local, and tribal environmental agency
database records. These database records will be
reviewed for information pertaining to the project site and properties within ASTM standard search radii
applicable to each database. The databases searched
will include, at a minimum, all databases specified in
ASTM E1527-21.
» Interviews: Crawford will contact San Mateo County
Environmental Health Division personnel to inquire
about departmental knowledge of the project site and
vicinity. Where warranted by the findings Crawford will attempt to contact owners or managers of adjacent
properties to inquire about past property uses and
conditions.
» Site Reconnaissance: Crawford will perform a
reconnaissance of the project site and vicinity to
evaluate current site conditions.
» Report of Findings: An ISA report documenting our
assessment will be prepared for the project alignment.

This report will include, but not necessarily be limited to, the following:
– Description of the project alignment and vicinity;
– Summary of the physical setting, local geologic
conditions, and hydrogeologic conditions;
– Summary of the historical records review and
historical alignment usage;
– Findings from the records review;
– Site reconnaissance observations;
– Interview results;
– Photographs of significant items of environmental
concern observed during the site reconnaissance
(if any);

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 21 ends

– Findings, opinions, and conclusions on potential
impacts: including a summary of RECs, and a
discussion of significant data gaps and data
failures; and
– Recommendations, as warranted by the findings for
additional investigation and/or sampling and testing
for potentially hazardous materials.

DELIVERABLES
» Draft and Final Initial Site Assessment Report
Task 5.1.1.2. Materials Report
We assume minor pavement improvements will be
required at locations of the median reconfigurations
and the new paved corner areas. To collect subsurface
data at the pavement improvements and potential sign
locations, Crawford will complete the following for the field exploration preparation:
» Visit the site to mark our exploration locations for USA North 811;
» Obtain a Town encroachment permit;
» Obtain a Caltrans encroachment permit; and
» Coordinate/schedule field investigations.

Field exploration will consist of 2 to 3 hand auger borings (maximum depth of 3 to 5 feet) and 1 to 2 Dynamic Cone
Penetrometer (DCP) tests to a maximum depth of 15
feet at the proposed sign and new pavement areas. Soil
samples will be logged in general accordance with ASTM
standards and Caltrans practice. Crawford will complete laboratory testing, as appropriate, on representative
samples for R-value, sieve analysis, corrosivity, and
plasticity index testing.

Crawford will prepare a Materials Report to support
the PS&E phase for the proposed sign structures. The
Materials Report will be prepared in accordance with
Caltrans guidelines (Highway Design Manual) to support
the PS&E phase. The report will include a summary of
the field exploration; laboratory testing results; pavement structural section recommendations for both traditional and full-depth HMA sections utilizing CalME; grading;
and foundation recommendations for the signal/light
poles, assuming standard plan foundations. Crawford will include a vicinity map, geologic map, exploration map,
and DCP logs.

DELIVERABLES
» Draft and Final Materials Report
Task 5.1.1.3. Hazardous Materials Report (Optional)
During the geotechnical exploration in PS&E, Crawford
would collect samples for hazardous waste testing. The
following scope can be adjusted up or down based on
the current project configuration. Prior to collecting the samplings, Crawford will submit the sampling plan to
Caltrans for review.

Crawford will collect soil samples to screen for lead
content in soil along the shoulder areas and median of El Camino Real, concrete samples to screen for asbestos,
and traffic striping samples to assess the metals content.

Aerially Deposited Lead (ADL)
Crawford will mark sample locations for USA/811
clearance during Task 2. A Crawford field technician
will return to the site to collect soil samples from up to 7 locations along El Camino Real, at depths of 0‑6”, 12”- 18”, and 24”-30” below ground surface (total of 21 soil samples). Samples will be collected with a hand auger.

All samples will be analyzed for total lead by EPA Method 6010, and eight samples will be analyzed for pH by EPA
Method 9045. Samples with total lead concentrations
that exceed 50 milligrams/kilogram will be further
analyzed for soluble lead using the WET and TCLP
methods. For budgeting purposes, we assume that 10
samples will require analysis for soluble lead.

Concrete
Crawford will collect up to three samples of concrete for asbestos testing.

Traffic Striping
Crawford will collect three samples of both white and
yellow thermoplastic traffic striping material. All samples will be analyzed for lead, and the yellow striping samples will also be analyzed for chromium (EPA Method 6010).

The ADL, concrete, and traffic striping sampling results will be included in a Hazardous Materials Report.

DELIVERABLES
» Draft and Final Hazardous Materials Report
Task 5.1.2. Right-of-Way Data Sheet
As a part of the Mark Thomas Team, AR/WS will prepare
a Rightof-Way Data Sheet. It is anticipated that the
improvements at the intersection will not impact buildings or other major improvements. Any acquisitions required
(TCE’s) will not result in damages to the remainder
parcels.
» The right-of-way estimate will include the following:
» Research of subject properties including land use
designations.
» An analysis of the probable highest and best use of
the properties.
» Classification of properties into land use categories to establish land value ranges.
» Analysis of right-of-way acquisitions and impacts to
improvements, if applicable (assumes none).

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 22 ends

» Consideration of severance damages and benefits
(assumes none).
» Estimated relocation assistance costs, if applicable
(assumes none).
» Estimated right-of-way support costs.

The right-of-way estimate is not an appraisal. It utilizes resources such as information available in the mark or
from past relevant assignments, sales data, listings, field inspections, and Assessor’s information.

DELIVERABLES
» Right-of-way Data Sheet
Task 5.1.3. Drainage Report
Mark Thomas will prepare a roadway drainage report in
the form of a technical memo containing the required
drainage report elements as required by Caltrans District 4 and submit it to the Town and Caltrans for review. The report will include a delineation of existing and proposed drainage shed areas, calculations for proposed drainage conditions (based upon the Rational Method), and
calculations for proposed pipe sizes, inlet locations, and outfall areas based upon proposed modifications to the
existing drainage system within the project limits along SR-116 and within Caltrans operating right-of-way. This scope assumes that design storm tailwater Hydraulic
Grade Line (HGL) information will be available from
either Caltrans or the Town for the purpose of calculating required changes to the drainage system.

Draft drainage calculations will be included with the
65% submittal and the draft and final drainage report
will be submitted with the 95% and 100% submittals
respectively. Mark Thomas will address and respond
to comments received on each submittal. This scope
assumes no trunk line drainage system modification will be required.

DELIVERABLES
» Drainage Report
Task 5.1.4. Stormwater Data Report
Mark Thomas will prepare a Storm Water Data Report
(SWDR) in conformance with Caltrans SWDR guidelines
to address post-construction storm water quantity
and quality. This scope assumes a “long form” will be
needed for the project. Mark Thomas will prepare a
draft and final SWDR. The SWDR will include a project
risk level determination, storm water treatment sizing
calculations including consideration of hydromodification, determination of disturbed soil area, impervious area
calculation, and design checklists. The development of
the SWDR and the permanent storm water treatment
measures will be coordinated with the development
of the project drainage design concept. Storm water
treatment measure calculations will be provided at 65%, and the draft and final SWDR will be submitted with the 95% and 100% submittals respectively.

DELIVERABLES
» Stormwater Data Report
Task 5.1.5. Transportation Management Plan
Mark Thomas will prepare a Transportation Management
Plan (TMP) Checklist for the project, including the
requirements set forth in the Caltrans Transportation
Management Guidelines dated November 2015.

DELIVERABLES
» TMP Checklist
Task 5.1.6. Intersection Safety and Operational
Assessment Process (ISOAP)
Parametrix, as part of the Mark Thomas team, will
coordinate with the Caltrans District 4 Division of
Traffic Safety and complete a required ISOAP analysis.

The ISOAP will be undertaken as an early action
item; it will include traffic analysis and will inform the PS&E development tasks. Parametrix will prepare the
supporting technical analyses and documentation
materials required by Caltrans. We will evaluate the
proposed intersection improvements and respond to
feedback received from the Town and Caltrans District 4 staff.

The ISOAP consists of two stages. This project will be
required to complete Stage 1 Screening but may be
exempted from Stage 2 Detailed Assessment. The two
stages are described below:
» Stage 1 Screening applies to this project because the Town proposes to change the existing intersection
traffic control from minor approach STOP control to
a signal or pedestrian hybrid beacon (PHB). Stage
1 is to be completed at the current Project Initiation
Document (PID) stage and uses an assessment
methodology focusing on multimodal safety, e.g.,
Safety Performance for Intersection Control Evaluation
(SPICE) or Safe System Intersection Methodology.
» Stage 2 Detailed Assessment may be undertaken
if there is more than one strategy identified out of
Stage 1 Screening, e.g., full traffic signal, PHB and
roundabout. Stage 2 is to be completed at the Project
Approval and Environmental Document (PA&ED)
phase and requires quantification of the project’s
benefit / cost ratio. Our proposed budget limits our
effort to mesoscopic traffic model software, i.e.,
Synchro / SimTraffic.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 23 ends

» Stage 2 may be deleted if Caltrans accepts the
findings of the Stage 1 Screening process to proceed
with a traffic signal or PHB without further analysis of a roundabout or other intersection reconfiguration.

The Stage 1 assessment includes:
– Identification of desired project outcomes.
– Assessment of nonmotorized travel including crash
records and conformance with SSA principles of
modal separation.
– Assessment of Town and freight access
– Assessment of available right-of-way
– Estimated multimodal safety and delay under
proposed traffic control proposals.
– Summary of the overall intersection measures of
effectiveness (MOE), e.g., daily person hours of
delay (DPHD), volume/capacity ratio, queuing, or
another measure as directed by the District Traffic
Operations Engineer.
– Completed Stage 1 ISOAP form and supporting
documentation.

The Stage 2 (optional task) assessment includes:
– Identification of whether there is more than one
feasible improvement strategy (signal, PHB,
roundabout, or access change)
– Completion of a detailed safety analysis using
Highway Safety Manual methodologies and
supplemented by SPICE and SSA
– Operational analysis using mesoscopic traffic
models, e.g., Synchro software.
– Plan sketch diagrams of viable improvement
strategies
– Calculations of improvement costs and right-ofway impacts – Calculations of the benefit to cost ratio (B/C) based on HSIP or other benefit calculation methodologies.
– Completed Stage 2 ISOAP form and supporting
documentation.

Parametrix will provide the analysis to Caltrans District ISOAP Coordinator, District Traffic Ops Engineer,
and District Traffic Safety Engineer and respond to
their feedback to update the draft products to a final
assessment.

Parametrix has budgeted updated 12-hour multimodal
traffic counts across two days at the study intersection.

DELIVERABLES
» ISOAP Stage 1 and Stage 2 (optional task) forms with
sketches, cost estimates, and operational analysis
(model worksheets)
» Coordination with Public Outreach process

ASSUMPTIONS
» One draft and one final submittal of the ISOAP Stage 1 and Stage 2 forms resulting from up to two rounds of
Caltrans District 4 review
» Budgeted effort assumes traffic signal or PHB as a
near-term improvement with operational modeling
limited to Synchro / SimTtraffic modeling. Detailed
analysis using microsimulation (e.g., VISSIM), long
range travel demand forecasting, and detailed
roundabout modeling are subject to additional cost
Task 5.1.7. Traffic Operations Analysis Report
(TOAR)
Once up to two alternatives have been identified,
Parametrix will analyze each alternative for existing
conditions, the opening year and the design year
(20 years after the opening year), to help identify the preferred alternative and meeting the requires for
Caltrans approval and the need to demonstrate project
benefits through the life of the project.

Once the preferred alternative has been identified and
the Caltrans DEER process has been begun, Parametrix
will utilize the traffic data from the ISOAP process and prepare a Traffic Operation Analysis Report (TOAR)
satisfying typical Caltrans District 4 requirements. The operational analysis will consider existing conditions, opening year conditions, and the dear year conditions. A draft TOAR will be submitted to District 4 for review and comments. After receipt of comments on the Draft TOAR,
a response to comments matrix will be prepared and a
Final TOAR will be produced for Caltrans Approval.

DELIVERABLES
» Draft and Final TOAR
Task 5.2. Caltrans Permitting
Task 5.2.1. Pre-Permit Screening and Meeting
We anticipate this Project will be subject to a Design
Engineering Evaluation Report (DEER) process. This is
the applicable Caltrans process assuming the following
bullets are all met with the project:
» Project has approved environmental document
(Categorical Exemption/Categorical Exclusion,
Negative Declaration, EIR, EIS etc.) or project is
categorically exempted/excluded by CEQA and/or
NEPA and has completed studies or public outreach.
» Project only has a Single-Build Alternative
» Project does not require CTC action

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 24 ends

» Project doesn’t involve any ROW conveyances
from the Department to the local agencies (e.g.
dedications, relinquishments, modifications to State
ROW limits, etc.)
» Project doesn’t require FHWA approval for
Relinquishments or NPRCs involving a modification to
the access control
» Project doesn’t involve construction of new structures or bridge widenings
After the conceptual design is finalized (Task 3), the
Design Team will schedule and attend a meeting with
Caltrans to verify the project is subject to a DEER
process. At this meeting, we will present our approach to deliver the technical studies identified in Task 5.2 – 5.8, and clarify any scope of work and process related items necessary to secure Caltrans approval for the project
improvements.

Task 5.2.2. Design Engineering Evaluation
Report
The Design Team will prepare the draft DEER document
using the template provided by Caltrans on their website here: https://dot.ca.gov/-/media/dot-media/programs/
traffic-operations/documents/encroachment-permits/epqmap-attachment-4-a11y.pdf It is expected that this will require the following
supplemental studies to be included with our DEER:
» Vicinity and Location Map
» Geometric Approval Drawing – Task 3
» Right-of-Way Data Sheet (assumes no right-of-way
acquisition) – Task 5.1.2
» Initial Site Assessment – Task 5.1.1.1
» Storm Water Data Report – Task 5.1.4
» Environmental Document – Task 6
In addition to the above required attachments, the
following attachments may also be applicable:
» Geotechnical Report (including the Log of Test
Borings, or LOTB) – Task 5.1.1.2
» Design Standard Decision Document
» While possible that this may be required, we do not
see any potential design features that would require
this document, and anticipate designing the project
to be in compliance with all applicable Caltrans
Design Standards, thus eliminating the need for this
document/process
» Complete Street Checklist
» Transportation Management Plan (TMP) – Task 5.1.5
» Traffic Impact Report – Task 5.1.7
» Intersection Safety and Operational Assessment
Process (ISOAP) – Task 5.1.6
» Cost Estimate – Task 5.3

ASSUMPTIONS/EXCLUSIONS
It is assumed that no utility relocations or right-of-way acquisition will be needed as a part of the project.

We have also excluded the preparation of any utility
certification, right-of-way certification, Design Standard Decision Document (DSDD), Risk Management Plan or
maintenance agreement exhibits. These items can be
prepared as a supplemental service if needed.

Task 5.3. Final Design
Task 5.3.1. 65% Design Plans
After the approval and confirmation of the conceptual
design plan, Mark Thomas will prepare 65% construction
documents including plans and an engineer’s opinion of
probable cost using the Town of Atherton and Caltrans
standards. Technical specifications will be provided in Caltrans SSP format. 65% construction documents will
utilize the basemaps and Topographic Survey from Task

2. Layouts will be created at the scale of 1” = 20’. The plan will include all sheets shown below as well as an itemized opinion of probable construction cost. Submittal format will be electronic (PDF) of 11”x17” plans and letter-sized specifications and cost estimate.

Sheet Type # of Pages
Cover Sheet 1
General Notes 1
Demo Plans 1
Layout 1
Construction Details 3
Pavement Delineation and Sign Plans 1
Sign Plan 1
Drainage and Drainage Details 3
Temporary Erosion Control Plans 2
Staging Plans 2
Traffic Control Plans 2
Traffic Signal Plans 4
Total 22
We will prepare a construction cost estimate that will
identify construction work items, quantities, unit costs and summarize the estimate total project cost, including allowances supplemental work, owner-furnished
materials, expenses, mobilization and contingencies as
appropriate.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 25 ends

DELIVERABLE(S):
» 65% Plans
» 65% Technical Specifications (Caltrans SSP Format)
» 65% Engineer’s Opinion of Probable Cost
» Response to Conceptual Design Comments
» All deliverables to be submitted in pdf format
Task 5.3.2. 90% Design
Mark Thomas will review and respond to Town
comments from the 65% submittal. Mark Thomas
will update the 65% construction documents to 90%
(including plans and an engineer’s opinion of probable
cost). The 90% construction documents will incorporate
comments. Mark Thomas will submit responses in
writing with the 90% submittal. The 90% construction
documents will include a revised engineer’s estimate.

Mark Thomas will perform a constructability review on
the 90% plans, specs and opinion of probable cost. The
comments generated from the constructability review will be incorporated into the Final Design documents.

DELIVERABLE(S):
» 90% Plans
» 90% Technical Specifications (Caltrans SSP Format)
» 90% Engineer’s Opinion of Probable Cost
» Response to 65% Design Comments
» All deliverables to be submitted in pdf format
The plan set will include as sheets shown above as well as an itemized opinion of probable construction cost.

Submittal format will be electronic (PDF) of 11” x 17” plans and letter-sized cost estimate.

Task 5.3.3. Final Design Documents
Mark Thomas will review and respond to Town comments
from the 90% submittal. Mark Thomas will incorporate
constructability comments made on the 90% submittal.

Mark Thomas will update the 90% construction
documents to Final Design Documents (including plans,
technical specifications and an engineer’s opinion of
probable cost). The final documents will incorporate
comments received on the 90% design. Mark Thomas will
submit responses in writing with the bid submittal. The bid documents will include a revised engineer’s estimate.

DELIVERABLE(S):
» Final Plans
» Final Technical Specifications
» Final Engineer’s Opinion of Probable Cost
» Response to 90% Design Comments
» All deliverables to be submitted in pdf format
TASK 6. ENVIRONMENTAL

DOCUMENTATION
Task 6.1. Environmental Clearance
Mark Thomas will prepare a combined CEQA
Categorical Exemption/NEPA Categorical Exclusion
(CE/CE) using the most recently available form from
the Caltrans Standard Environmental Reference (SER).

We anticipate that the project, due to the limited nature of improvements which are assumed to be within the
existing right-of-way, will qualify for a Class 1 exemption under CEQA Guidelines Section 15301, Existing Facilities.

This section covers alterations to “existing highways
and streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities (this includes road grading for the purpose of public safety), and other alterations”.

We anticipate the project will qualify for a NEPA CE
under Section 177.117 of the CFR, subsection (c)(22),
which covers project within the existing right-of-way.

Because of the type and location of improvements,
and the proposed DEER process, we anticipate that no
detailed technical reports will be required, and that “no effect” memoranda will be prepared for biological and
cultural resources. A CHRIS and Sacred Lands search
will be completed to support the cultural resources
memorandum. Mark Thomas will prepare a draft CE
checklist and attachments and will respond to up to
three rounds of comments before finalizing. We will also provide a Notice of Exemption and summary form for
Caltrans to file with the State Clearinghouse.

DELIVERABLES
» Draft and Final CE Checklist
» Notice of Exemption and Summary Form
TASK 7. COORDINATE WITH

OTHER JURISDICTIONS
It has been identified that there are multiple projects by other jurisdictions within the direct proximity of the Selby and ECR Intersection. Mark Thomas will lead coordination and communication with other jurisdictions with adjacent projects and other identified stakeholders.

Task 7.1. Caltrans SHOPP Project
Coordination
Mark Thomas will participate in and attend Caltrans Monthly SHOPP Project PDT meetings. Mark Thomas will note any
SHOPP project changes and report to the Town. Mark
Thomas will coordinate project schedules, design elements with the intention of minimizing conflicts between projects.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 26 ends

It is assumed that Mark Thomas will attend up to twelve (12) Caltrans SHOPP Project coordination meetings.

DELIVERABLES
» Caltrans SHOPP Meeting Attendance (monthly, up to
12 meetings)
Task 7.2. SamTrans GBI Coordination
Mark Thomas will facilitate coordination with the
SamTrans GBI Project. Mark Thomas will note any
updates to the GBI Project and schedule and report to
the Town. Mark Thomas will coordinate project schedules and design elements with the intention of minimizing
conflicts between projects. It is assumed that Mark
Thomas will attend up to six (6) SamTrans GBI Project
coordination meetings.

DELIVERABLES
» SamTrans GBI Meeting Attendance (bi-monthly, up to
6 meetings)
Task 7.3. Outside Agency
Coordination
Mark Thomas will facilitate coordination with other
neighboring jurisdictions or projects identified by the Town.

Tasks included may include email correspondence, phone
calls, or hosting focus meetings to coordinate project
details and schedules with the Selby Intersection project.

A budget has been provided for this task, but the actual level of effort will depend on Town needs and adjacent
projects that arise. This scope assumes that Mark Thomas will schedule 3 meetings with San Mateo County and 3
meetings with Redwood City. Coordination with Caltrans
and SamTrans are covered in tasks 7.1 and 7.2.

DELIVERABLES
» City of Redwood City Coordination Meeting
Attendance (up to 3 meetings)
» San Mateo County Coordination Meeting Attendance
(up to 3 meetings)
TASK 8. BIDDING SUPPORT/

CONSTRUCTION SUPPORT
Task 8.1. Bid Support
Mark Thomas will provide bid assistance, as required, to the Town during bidding of the project. This could include prebid meeting attendance, preparation of addenda, answering questions and other various bid support requests by the Town. A budget has been provided for this task, but the actual level of effort will depend on Town needs that arise during advertisement. This task will be billed on a time and materials basis and may need to be increased based on the level of effort required by the Town.

DELIVERABLES
» Response to Bid RFIs
» Bid Document Addendums
Task 8.2. Construction Support
Mark Thomas will provide design support during
construction, as required, to the Town during construction of the project. This task assumes the Town will provide/ retain a qualified Construction Manager for the project who will act as the Resident Engineer (RE) during construction.

The RE will be responsible for managing the project
through construction including overseeing the Contractor and day-to-day construction activities including, but not limited to, preparing agendas, minutes and logs of action items for construction meetings, distribution of plans and addendums, conducting all payment reviews, responding
to Requests for Information (RFIs) and reviewing shop
drawings. Design support during construction could
include preparation of Contract Change Order (CCO)
plans, supporting responses to RFIs, and supporting shop drawing reviews. A budget has been provided for this task, but the actual level of effort will depend on Town/RE needs that arise during construction. This task will be billed on a time and materials basis and may need to be increased
based on the level of effort required by the Town/RE.

DELIVERABLES
» Response to RFIs
» Shop Drawing Review
» Preparation of Plan Sheet Revisions
TASK 9. ATTEND PUBLIC

MEETINGS
Task 9.1. Public Meetings and
Hearings
The Mark Thomas Team, in collaboration with the Town,
will present the project at key points to the Atherton
Town Council as needed. This scope assumes that Mark
Thomas will attend, present to project stakeholders and review the conceptual and final designs. This scope
assumes that Mark Thomas will prepare meeting materials and presentations and participate in 3 public meetings.

DELIVERABLES
» Public Meeting Attendance (Up to 3 meetings)

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 27 ends

PRINCIPAL-IN-CHARGE
Shawn O’Keefe, PE, QSD

TOWN OF ATHERTON
Douglas Kim

PROJECT MANAGER
Alex Lee, PE, QSD

PROJECT STAFF

CIVIL DESIGN
Aaron Seitz, PE
Christopher Ko, EIT

REGIONAL CORRIDOR LEAD
Jason Fong, PE

ENVIRONMENTAL SPECIALIST
Brianna Bohonok
Danielle Keith

SURVEY/MAPPING
Sherrie Zimmerman, PLS

DRAINAGE
Harfateh Grewal, PE, QSP

STRUCTURES
Marshall Moore, SE

FUNDING
Ryan Bissegger

LANDSCAPE
Christine Anderson, PLA, CLARB

PUBLIC ENGAGEMENT

GRAPHIC SUPPORT
Deanna Gibson

TRAFFIC ANALYSIS
Ryan Whipple, PE (PM)

SIGNALS AND LIGHTING
Andrew Lee, PE, TE, PTOE (PM)

GEOTECHNICAL/ISA
Amando Castro, PE (CA)

RIGHT-OF-WAY
Mark Shindler (AR)
Key Staff
PM Parametrix
CA Crawford

AR AR/WS

KEY STAFF
We have assembled a team of highly qualified professionals with extensive experience delivering complex, communitysensitive transportation projects for local agencies and Caltrans in environments similar to Atherton. Our team’s expertise includes multimodal roadway and corridor design, utility coordination, and preparation of high-quality PS&E, along with a strong understanding of complete streets, green infrastructure, and context-sensitive solutions that reflect community priorities. Alex Lee, PE, QSD, will serve as the Project Manager, bringing over 20 years of municipal and transportation engineering experience and a proven ability to lead multidisciplinary teams and coordinate effectively with stakeholders. In addition to their experience, team members were selected based on their availability and commitment to the project. The organization chart below illustrates the Mark Thomas team, key staff and disciplines, supporting personnel, and lines of communication. All proposed staff are available and committed and will not be changed without prior approval from the Town.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 28 ends

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton
Alex Lee, PE, QSD
Project Manager
» Extensive experience on multimodal facilities
» Strong working knowledge of Caltrans process from concept to final design including: PID, PA&ED, and PS&E
» Experience coordinating with transit agencies, stakeholders and local agencies, including SamTrans
Alex has 20 of municipal and transportation engineering experience, with an emphasis on local roadway and intersection improvements. He has served as project manager and lead designer on numerous of roadway and multimodal improvement projects, including the Downtown Bike/ Pedestrian Crossing in Windsor, the El Camino Real Bike & Pedestrian Improvements in the Town of Colma, and serving as project manager for On-Call Planning Services for SamTrans which included planninglevel alternative development for eight miles of El Camino Real for the El Camino Real Multimodal plan. He has extensive experience on multimodal facilities and a strong working knowledge of the Caltrans process, including PID, PA&ED, and PS&E, as well as experience coordinating with transit agencies, including SamTrans.

Collaboration experience. He collaborates with stakeholders to understand their needs and operations, prioritizing safe access for bicyclists and pedestrians while optimizing flow across all modes of transportation. Alex works closely with agencies and project partners to align design decisions, navigate requirements, and build consensus, helping advance projects efficiently from concept through final design.

Stormwater experience. In addition to geometric design, transportation engineering, and utility coordination, Alex holds a QSD certification and has experience in drainage design as part of his core competencies. He served as project engineer for revitalizing the City of Oakley’s Multimodal Downtown Redevelopment project which included new drainage and clean water facilities to satisfy Contra Costa County’s c.3 requirements.

On the Sycamore Park and Ride Expansion project, Alex Lee served as project manager, which involved c.3 bioretention basins for stormwater runoff.

Bike/pedestrian design experience. Alex specializes in multimodal infrastructure design, with expertise in ADA compliance and bicycle and pedestrian improvements. He served as Civil Lead for the El Camino Real Bicycle and Pedestrian Improvements project in the Town of Colma, advancing accessibility, mobility, and circulation, and as Project Manager for the Windsor Downtown Bicycle/Pedestrian Crossing project in the Town of Windsor.

MEET OUR PROJECT MANAGER
20 years of experience
BS in Civil Engineering
Licenses/Registrations
» California Professional
Engineer (PE) #C73244
» Qualified Storm Water
Pollution Prevention Plan
Developer (QSD) 25792
Core competencies
» Civil and transportation
engineering including
» Stormwater/drainage design
» Multi-modal and active
transportation
» ADA Compliance
» Transit oriented projects
» Stakeholder engagement
» Project management
Alex Lee will
lead the team
as project
manager. In this
role, he will be the
main point of contact
for the Town and
manage team and
internal day-to-day
coordination.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 29 ends

Brianna Bohonok
Environmental
MS in Urban Planning and Policy
BA in Architecture
Brianna has 13 years of experience as a CEQA
practitioner and land use planner, managing
environmental documents for transportation, transit,
development, and land use projects throughout
California. Her experience at Caltrans and on major
transit programs supports her ability to guide projects from initiation through permitting. She develops efficient, defensible environmental strategies informed by current legislation, case law, and best practices.

Shawn O’Keefe, PE, QSD
Principal-in-Charge
BS in Civil Engineering
CA PE C71792, QSD 25799
Shawn has 22 years of experience in transportation
project engineering and management and has a
thorough understanding of project delivery from
inception to completion. He has designed and managed
a wide variety of projects for local cities, counties and transportation agencies. The projects include bike and
pedestrian improvements, trails, local roadways, freeway interchanges and managed lanes, park and ride lots, and transit centers.

Relevant Experience
» El Camino Real Bike & Pedestrian
Improvements PA&ED, Colma
» US 395 Lassen County Wildlife
Crossing, Lassen County
» I-880 Whipple/Industrial
Interchange Improvement Project,
Alameda County
» San Pablo Multi-Modal Corridor,
Alameda County
Jason Fong, PE
Regional Corridor Lead
BS in Civil and Environmental Engineering
CA PE C64542
Jason has 25 years of civil engineering experience
in the public and private sector. He has successfully
managed and designed multimodal and complete
streets improvements within the public right-of-way,
including transit, bicycle, and pedestrian mobility projects.

His expertise spans federal, state, and local design
standards, and he is well-versed in the Caltrans design requirements and Local Assistance Program Manual.

With a strong focus on enhancing connectivity, mobility, and safety, he excels in integrating and executing clients’ visions through the complexities of planning, permitting, and implementation stages.

Relevant Experience
» El Camino Real Bike & Pedestrian
Improvements PA&ED, Colma
» Grand Boulevard Initiative (GBI),
San Mateo and Santa Clara
Counties
» US 395 Lassen County Wildlife
Crossing, Lassen County
» SamTrans On-Call Planning
Services, San Mateo
» I-880/Decoto Road Interchange
PA&ED, Fremont
Relevant Experience
» Grand Boulevard Initiative (GBI),
San Mateo and Santa Clara
Counties
» State Route 116/West Cotati
Avenue Reconfiguration Project,
Cotati
» El Camino Real Bike & Pedestrian
Improvements PA&ED, Colma
» San Mateo Co-2023 Safe Streets,
San Mateo County
» E. Blithedale Avenue
Improvements, Mill Valley

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 30 ends

Harfateh Grewal, PE, QSP
Drainage
MS and BS in Civil Engineering
CA PE C95969, CA QSP 26791
Harfateh has 12 years of experience in small and large
transportation projects in the Bay Area. He has worked
on numerous projects, including complete streets,
local roadway and intersection improvements, and
highway and interchange improvements. His experience
includes stormwater management and regulations, and
experience in design and development of stormwater
retention and treatment features. He will lend his
expertise to the team in drainage design, hydraulics
modeling, hydromodification management as well as
erosion control controls.

Relevant Experience
» El Camino Real Bicycle and
Pedestrian Improvement PSRPDS, Colma
» SR 65/Placer Parkway
Interchange PS&E, Placer County
» I-215/Keller Road Interchange,
Murrieta
» I-280/Winchester Boulevard
Improvements, San Jose
» El Cerrito del Norte TOD
Complete Street, El Cerrito
Ryan Whipple, PE
Traffic Analysis (Parametrix)
BS Civil Engineering
CA PE C2821
Ryan is a traffic engineer and planner with experience in transportation design, traffic operations, and Complete Streets projects across California and Nevada. He has
prepared traffic studies, conducted intersection analyses, and led transportation design efforts, with expertise
in traffic signals, signing and striping, MOT/TCPs, and multimodal transportation planning and design.

Relevant Experience
» Interstate 280 (I-280)/Ocean
Avenue Interchange, San
Francisco County Transportation
Authority
» El Camino Real and Hill Street
Pedestrian Hybrid Beacon Project
PS&E, Belmont
» Sir Francis Drake Traffic Signal
Warrant Study, Town of Ross
» Lincoln Avenue/Marshall
Way/Pacific Avenue Safety
Improvements, Alameda
Andrew Lee, PE, TE, PTOE
Signals and Lighting (Parametrix)
MS in Urban Planning
BS Civil Engineering
CA TE 86247, CA PE C2455, PTOE 5817
Andrew serves as a project manager, traffic engineer,
and transportation planner for Complete Streets, traffic safety, and active transportation projects. He leads
transportation and civil design from concept through final delivery, with expertise in intersection operations, safety studies, multimodal facilities, traffic signals, roundabouts, and accessible, active transportation infrastructure.

Relevant Experience
» El Camino Real Complete Streets
Study, Town of Atherton
» San Francisco County
Transportation Authority,
Interstate 280 (I-280)/Ocean
Avenue Interchange
» Middle Avenue Complete Street
Project, Menlo Park
» El Camino Real and Hill Street
Pedestrian Hybrid Beacon Project
PS&E, Belmont

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 31 ends

PROJECT STAFF
Our multidisciplinary team brings together experienced transportation, environmental, traffic and signal, drainage, public outreach, and design professionals who will work collaboratively to deliver the Atherton El Camino Real–Selby Lane Intersection Improvements Project from project approval through final design.

Name/Role and Qualifications Experience
Aaron Seitz, PE
Civil Lead
BS in Civil Engineering
CA PE 94922
7 years of experience
» Soquel Drive Multimodal Improvements, Santa Cruz County » Broadway Grade Separation, Burlingame
» Downtown Bike/Ped Crossing, Windsor
» SamTrans South Base BEB Charging, San Mateo County
» SamTrans On-Call Planning Services, San Mateo County
» El Camino Real Bike & Pedestrian Improvements PA&ED, Colma Christopher Ko, EIT
Civil Support
BS in Civil Engineering
CA EIT 176735
11 years of experience
» El Camino Real Bike & Pedestrian Improvements PA&ED, Colma » SamTrans South Base BEB Charging, San Mateo County
» El Camino Real Bicycle and Pedestrian Improvement PSR-PDS, Colma
» I-880/Decoto Road Interchange PA&ED, Fremont
» On-Call Civil Engineering and Surveying Services, Santa Cruz Danielle Keith
Environmental Support
MS in Environmental Studies
BA in Political Science
Coursework in CEQA and NEPA
6 years of experience
» Lindhurst Corridor Improvements, Yuba County
» El Camino Real Bike & Pedestrian Improvements PA&ED, Colma » SR 120/Airport Way Interchange PS&E, Manteca
» Grand Boulevard Initiative (GBI)/El Camino Real Program PSRPDS, San Mateo County » Vasco Road Safety Improvements, Contra Costa County
Ryan Bissegger
Funding
BA in International Business
Funding and Programming
Transportation Projects in CA
» El Camino Real Bicycle and Pedestrian Improvement PSR-PDS, Colma
» El Camino Real Bike & Pedestrian Improvements PA&ED, Colma » US 101/SR 84/Woodside Road Grant Assistance, Redwood City » I-80/I-680/SR 12 Interchange Complex Grant Applications, Solano County
Sherrie Zimmerman, PLS
Survey/Mapping
AS in Survey
AA in Architecture
CA PLS 8964
22 years of experience
» US 395 Lassen County Wildlife Crossing, Lassen County » SR 152/Pacheco Pass Wildlife Crossing, Contra Costa County » East Cypress Road Lane Alignment, Oakley
» El Camino Real Bike & Pedestrian Improvements PA&ED, Colma Marshall Moore, SE, PE
Structures
MS and BS in Civil Engineering
CA PE C95969, SE S6557
14 years of experience
» El Camino Real Bicycle and Pedestrian Improvement PSR-PDS, Colma
» SR 65/Placer Parkway Interchange PS&E, Placer County
» I-215/Keller Road Interchange, Murrieta
» I-280/Winchester Boulevard Improvements, San Jose

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 32 ends

Name/Role and Qualifications Experience
Christine Anderson, PLA, CLARB
Landscape
BS in Landscape Architecture
AS in Architecture
CA RLA 3377, CLARB 36934
36 years of experience
» GBI/El Camino Real Program PSR-PDS, San Mateo County
» El Camino Real Bike & Pedestrian Improvements PA&ED, Colma » Bascom Avenue Complete Street Improvements, Santa Jose » Washington Avenue and Table Mountain Boulevard Complete Streets Project, Oroville
» East Main Street Improvements, Woodland
Deanna Gibson
Graphic Support
20 years of experience
» GBI/El Camino Real Program PSR-PDS, Colma
» Bicycle and Pedestrian Design Services, Atherton
» US 101/Hillsdale Pedestrian/Bicycle Overcrossing Preliminary Design and PSR-PDS, San Mateo
» I-80/Richards Boulevard PSR-PDS, Sacramento County
» Sand Creek Road Interchange PSR-PR and Supplemental PR, Contra Costa County
Crawford
Amando Castro, PE
Geotechnical/ISA
B.S. Civil Engineering
CA PE 94561
8 years of experience
» City of Burlingame Pavement Engineering Services, San Mateo County
» WBSD Flow EQ & Resource Recovery, San Mateo County
» Signalization of Mariposa Road and Jack Tone Intersection, San Joaquin County
» Duncan Road and Comstock Road Roundabout, San Joaquin County
AR/WS
Mark Shindler
Right-of-Way
BS, Business Administration
44 years of experience
» El Camino Real Bicycle and Pedestrian Improvement Project, Town of Colma
» San Mateo County Transportation Authority, Alpine Road Corridor Improvement Project
» SR 17 Corridor Congestion Relief Project, Santa Clara Valley Transportation Authority
» US 101 / SR 152 / 10th Street Interchange Improvement Project, Santa Clara Valley Transportation Authority
» Dublin Boulevard – North Canyons Parkway Extension Project, Alameda County Public Works Agency

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 33 ends

REFERENCES
Mark Thomas provides recent, relevant project experience with demonstrated collaboration alongside the proposed team members. The following references represent projects completed within the past five years that reflect similar scope, including multimodal intersection and corridor improvements, traffic analysis, and Caltrans coordination. Each reference includes a client contact familiar with our work and able to speak to the team’s qualifications, responsiveness, and overall project delivery.

Matthew Ruble
Principal Engineer
South San Francisco
400 Grand Ave
South San Francisco, CA 94080
[email protected]
(650) 829-6671
Grand Boulevard Initiative (GBI)
The Grand Boulevard Initiative is a multi-agency effort to transform El Camino Real (SR 82) into a multimodal corridor. Mark Thomas supported planning, public outreach, and preliminary design for multiple corridor case studies, coordinating with Caltrans, SamTrans, and local cities. The work advances Complete Streets solutions, sustainable design, and corridor-wide consistency to improve mobility, safety, and community integration along this major state highway.

Jenna Caldwell
Senior Civil Engineer
Contra Costa County Public
Works Department (CCCPWD)
1025 Escobar Street
Martinez, CA 94553
[email protected]
(925) 313-2020
Treat Boulevard Corridor Improvements
Mark Thomas is providing civil, traffic, and geotechnical design services for multimodal improvements along Treat Boulevard in Contra Costa County. The project enhances safety and connectivity by removing free right turns, reconfiguring lanes, and adding Class I and Class IV bicycle facilities. Improvements include ADA upgrades, signal modifications, utility coordination, and Caltrans coordination through the DEER process to support efficient corridor operations and project delivery.

Carl Euphrat
Deputy Director Of Engineering
Town of Windsor
9291 Old Redwood Hwy #400
Windsor, CA 95492
[email protected]
(707) 838-1195
Windsor Downtown Bicycle and Pedestrian Crossing
Mark Thomas prepared 30% design for a bicycle and pedestrian crossing on Old Redwood Highway in Windsor, reconfiguring the underpass to include a two-way protected bikeway and separated pedestrian facilities. The project included retaining wall modifications, a planted buffer, and evaluation of design alternatives, with coordination with Caltrans and advancement through the approval process.

Lawrence Henriquez
Senior Engineer
South San Francisco
400 Grand Ave
South San Francisco, CA 94080
[email protected]
(650) 829-6668
I-280 Westborough Study
Mark Thomas is supporting the PID phase for the Junipero Serra Boulevard and I-280 Westborough Boulevard Pedestrian and Bicycle Connectivity and Safety Project, advancing multimodal improvements identified during the feasibility study. Our team developed corridor alternatives, geometric designs, constructability assessments, and cost estimates, while evaluating funding opportunities for safety and active transportation improvements.

We are now refining concepts, coordinating with stakeholders, and preparing PSR-PDS documentation to advance the project toward PA&ED and implementation.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 34 ends

Tara McIntire
Projects & Design Manager
Marin County
1600 Los Gamos Drive, Suite 275
San Rafael, CA 94903
[email protected]
(415) 521-8059
Bolinas Lagoon Wye Wetlands
Mark Thomas provided engineering services for roadway and bridge improvements at the SR 1 and Olema Bolinas Road intersection, supporting wetland restoration and sea-level rise adaptation. The work included intersection analysis, roadway design, and PS&E development, with close coordination among Caltrans and resource agencies. The project integrated transportation safety with environmental restoration while addressing seismic, tsunami, and scour resilience in a sensitive habitat.

Damien O’Bid
City Manager
City of Cotati
201 West Sierra Avenue
Cotati, California 94931
[email protected]
(707) 792-4685
State Route 116/West Cotati Avenue Reconfiguration Project Mark Thomas is providing preliminary engineering services for corridor improvements along SR 116 in Cotati. The work includes developing conceptual plans and advancing preliminary engineering to support multimodal connectivity and coordination with adjacent developments.

The team is also supporting permitting and design within both Caltrans and City right-of-way, maintaining flexibility as the project evolves and aligning improvements with regional active transportation planning.

CORRIDOR

INTEGRATION

EXPERTISE
Mark Thomas provided
corridor-wide multimodal
improvements along El Camino
Real (SR 82), coordinating with
Caltrans, transit agencies, and
local jurisdictions to deliver
consistent, Complete Streets
solutions.

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 35 ends

ID %
Comp
Task Name Duration Start Finish Predecessors
1 0% ECR & Selby Lane Intersection Improvements 280 days Mon 8/3/26 Fri 8/27/27 2 0% Notice to Proceed 0 days Mon 8/3/26 Mon 8/3/26
3 0% Kick off Meeting & Contracting 20 days Mon 8/3/26 Fri 8/28/26 2 4 0% Task 1 - Project Management 260 days Mon 8/31/26 Fri 8/27/27 3 5 0% Task 2 - Data Collection 30 days Mon 8/31/26 Fri 10/9/26 6 0% 2.1 Data Collection and Review 20 days Mon 8/31/26 Fri 9/25/26 3 7 0% 2.2 Right of Way Survey 15 days Mon 8/31/26 Fri 9/18/26 3 8 0% 2.3 Topographic Survey and Basemapping 15 days Mon 9/21/26 Fri 10/9/26 7 9 0% Task 3 - Finalize Conceptual Design (GADs) 50 days Mon 8/31/26 Fri 11/6/26 10 0% 3.1 - Finalize Conceptual Design (GADs) 20 days Mon 8/31/26 Fri 9/25/26 3 11 0% Town Review 15 days Mon 9/28/26 Fri 10/16/26 10
12 0% Revise Conceptual Design 10 days Mon 10/19/26 Fri 10/30/26 11 13 0% Town Approval 5 days Mon 11/2/26 Fri 11/6/26 12
14 0% Task 4 - Public Outreach and Community Engagement 96 days Mon 12/7/26 Mon 4/19/27 15 0% Community Meeting 1 1 day Mon 12/7/26 Mon 12/7/26 13FS+20 days 16 0% Community Meeting 2 1 day Mon 4/19/27 Mon 4/19/27 13,36 17 0% Task 5 - Final Design and Caltrans Permitting 210 days Mon 11/9/26 Fri 8/27/27 18 0% 5.1 - Technical Reports 50 days Mon 11/9/26 Fri 1/15/27 19 0% Select Preferred Alternative 15 days Mon 11/23/26 Fri 12/11/26 28,13,8 20 0% 5.1.1 Geotechnical Design, Initial Site
Assessment and Materials Report
50 days Mon 11/9/26 Fri 1/15/27 13
21 0% 5.1.2 Right of Way Data Sheet 30 days Mon 11/30/26 Fri 1/8/27 13FS+15 days 22 0% 5.1.3 Drainage Report 30 days Mon 11/30/26 Fri 1/8/27 13FS+15 days 23 0% 5.1.4 Stormwater Data Report 30 days Mon 11/30/26 Fri 1/8/27 13FS+15 days 24 0% 5.1.5 Transportation Management Plan 30 days Mon 11/30/26 Fri 1/8/27 13FS+15 days 25 0% 5.1.6 Intersection Safety and Operational
Assessment Process (ISOAP)
50 days Mon 11/9/26 Fri 1/15/27 13
26 0% 5.1.7 Traffic Operations Analysis Report (TOAR)50 days Mon 11/9/26 Fri 1/15/27 13 27 0% 5.2 - Caltrans Permitting 105 days Mon 11/9/26 Fri 4/2/27 28 0% 5.2.1 - Pre-Permit Screening and Meeting 10 days Mon 11/9/26 Fri 11/20/26 13 29 0% 5.2.2 DEER Preparation 80 days Mon 12/14/26 Fri 4/2/27 19 30 0% Task 5.3 - Final Design 145 days Mon 2/8/27 Fri 8/27/27 31 0% 5.3.1 65% PS&E 50 days Mon 2/8/27 Fri 4/16/27
32 0% Prepare 65% PS&E 20 days Mon 2/8/27 Fri 3/5/27 29FS-40 days 33 0% QA/QC & IDR 5 days Mon 3/8/27 Fri 3/12/27 32
34 0% Update 65% PS&E 5 days Mon 3/15/27 Fri 3/19/27 33 35 0% Submit 65% PS&E 0 days Fri 3/19/27 Fri 3/19/27 34 36 0% Agency Review 20 days Mon 3/22/27 Fri 4/16/27 35SS 37 0% 5.3.2 95% PS&E 50 days Mon 4/19/27 Fri 6/25/27
38 0% Prepare 95% PS&E 20 days Mon 4/19/27 Fri 5/14/27 31,8 39 0% QA/QC & IDR 5 days Mon 5/17/27 Fri 5/21/27 38
40 0% Update 95% PS&E 5 days Mon 5/24/27 Fri 5/28/27 39 41 0% Submit 95% PS&E 0 days Mon 5/31/27 Mon 5/31/27 40FS+1 day 42 0% Agency Review 20 days Mon 5/31/27 Fri 6/25/27 41SS-1 day 43 0% 5.3.3 Final PS&E 45 days Mon 6/28/27 Fri 8/27/27
44 0% Prepare 100% PS&E 15 days Mon 6/28/27 Fri 7/16/27 37 45 0% QA/QC & IDR 5 days Mon 7/19/27 Fri 7/23/27 44
46 0% Update 100% PS&E 5 days Mon 7/26/27 Fri 7/30/27 45 47 0% Submit 100% PS&E 0 days Mon 8/2/27 Mon 8/2/27 46FS+1 day 48 0% Agency Approval 20 days Mon 8/2/27 Fri 8/27/27 47SS-1 day 49 0% Task 6 - Environmental Documentation 50 days Mon 11/9/26 Fri 1/15/27 50 0% 6.1 Environmental Clearance 50 days Mon 11/9/26 Fri 1/15/27 13 51 0% Task 7 - Coordination with other Jurisdictions 260 days Mon 8/3/26 Fri 7/30/27 52 0% 7.1 Caltrans Shopp Project Coordination 260 days Mon 8/3/26 Fri 7/30/27 2 53 0% Task 8 - Bid Support 0 days Fri 8/27/27 Fri 8/27/27 54 0% 5.1 Design Support During Bidding 0 days Fri 8/27/27 Fri 8/27/27 48 55 0% Task 9 - Attend Public Meetings 165 days Fri 11/6/26 Fri 6/25/27 56 0% 9.1 Public Meetings and Hearings 165 days Fri 11/6/26 Fri 6/25/27 57 0% Public Meeting 1 0 days Fri 11/6/26 Fri 11/6/26 13 58 0% Public Meeting 2 0 days Fri 4/2/27 Fri 4/2/27 29
59 0% Public Meeting 3 0 days Fri 6/25/27 Fri 6/25/27 42 8/3
3/19
5/31
8/2
8/27
8/27
11/6
4/2
6/25
9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 4 9 14 19 24 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 July 2026 August 2026 September 2026 October 2026 November 2026 December 2026 January 2027 February 2027 March 2027 April 2027 May 2027 June 2027 July 2027 August 2027 September 2027 Town of Atherton - El Camino Real and Selby Lane Intersection Safety Improvements Tue 7/14/26

PROJECT SCHEDULE

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 36 ends

LITIGATION
Mark Thomas & Company, Inc. operates throughout California and has average annual billings exceeding $50 million over the past five years. The firm has no litigation currently pending that would impact its ability to perform or discharge contractual obligations if awarded this contract.

From time to time, Mark Thomas & Company, Inc. has been involved in claims or litigation typical of firms providing professional engineering and construction management services on complex public infrastructure projects.

These matters have included allegations related to constructability, grading or drainage performance, right-of-way discrepancies, utility work, or third party incidents occurring during construction. The majority of these matters were non-litigated claims that were either resolved through settlement, abandoned by the claimant, or closed without admission of fault.

A limited number of matters proceeded to litigation, generally involving third party injury or property damage claims during construction activities. These cases were resolved through settlement and are now closed. Importantly, no matters resulted in findings that adversely affected the firm’s professional qualifications, licensure, or ability to deliver services, and none remain open as litigation.

Project Name and
Agency Basis of Claim Name of Case Date Closed
State College Blvd Railroad
Grade Separation
City of Fullerton
The lawsuit is dealing with a car accident
at the intersection of Kimberley Drive and
Acacia Avenue.

Deposition Subpoena for
Productions of Business Records
-Oliveros v Garcia, et. al.
3/18/2021
Marin Sonoma Narrows B3
Transportation Authority of
Marin (TAM)
Suit for wrongful death due to a
construction period traffic accident.

Tovar v. Ghilotti Construction Co. 6/17/2022

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 37 ends

DISCLOSURE
Mark Thomas does not have any financial, business, or other relationship with the Town of Atherton that would have an impact upon the outcome of the contract. We do not foresee any of our clients having a financial interest in the outcome of this contract or any other construction project that may follow. Specifically, Mark Thomas does not have any financial interest or relationship with the owner or developer that may have future improvements or development projects with the Town.

The following is a list of current work performed by Mark Thomas within a five-mile radius:

Agency/Client Project Name Services
San Mateo County Transportation
Authority
On Call General Engineering Consultant Services 2025 Civil San Mateo County On Call Grant Support Grant Support
SamTrans/STV Incorporated South Base Battery Electric Bus (BEB) Charging Infrastructure Project
Civil
Belmont/Good City Company Belmont Harbor Industrial Area (HIA) Specific Plan Planning Gray-Bowen-Scott/Redwood City US 101/Woodside Road (SR 84) Interchange Reconstruction Project
Grant Support

EL CAMINO REAL/SELBY LANE INTERSECTION IMPROVEMENTS PROJECT Town of Atherton

MARK THOMAS

Page 38 ends

PROFESSIONAL SERVICES AGREEMENT
Mark Thomas has reviewed the “Town of Atherton Standard Professional Services Agreement” in the RFP. If selected to work on this project, we would like the Town to consider the following modifications.

16. CONSULTANT TO PROVIDE INSURANCE:

The required Commercial General Liability ($5M/$10M) and Automobile Liability ($5M) limits reflect constructioncontractor risk, not professional design services—where the principal exposure is errors and omissions, already covered by the $2M Professional Liability policy. Industry-standard limits for design consultants and their subs are $1M/$2M CGL and $1M auto; many specialty subconsultants carry only those amounts and would have to buy umbrella coverage to reach $5M, narrowing the qualified pool and raising cost to the City for no added protection.

We have agreed to these limits in past agreements.
» Commercial General Liability Insurance: $5M/$10M
» Business Automobile Liability: $5M
El Camino Real/Selby Lane Intersection Improvements Project Town of Atherton
Appendix A

RESUMES

ALEX LEE, PE, QSD
Project Manager

EDUCATION
BS in Civil Engineering

REGISTRATION
California Professional Engineer (PE) #C73244
Qualified Storm Water Pollution Prevention Plan Developer (QSD) 25792 Alex has over 20 years of experience in municipal and transportation engineering, specializing in roadway and intersection improvements. He has extensive expertise in multimodal design and a strong working knowledge of Caltrans processes from concept through final design, including PID, PA&ED, and PS&E. Alex leads project delivery through coordinated stakeholder engagement, guiding teams and agencies to align on design solutions, manage approvals, and advance projects efficiently. His experience also includes integrating stormwater considerations into transportation design to support comprehensive and practical project outcomes.

REPRESENTATIVE PROJECTS
Downtown Bike/Pedestrian Crossing Caltrans Design
Engineering Evaluation Report (DEER), Windsor
Project manager responsible for completing the Final
Design and Caltrans project approval for the Old
Redwood Highway Bike/Pedestrian Crossing project
for the Town of Windsor. This project proposes to
construct new retaining walls to widen the sidewalk area to accommodate a two-way protected bicycle path and
separate pedestrian area. Other improvements include
a planted buffer between the existing roadway and the
proposed bicycle facility. Mark Thomas also reviewed
whether a two-way protected bicycle path is needed on
both sides of the roadway or on the northside only. The project includes coordination with Caltrans and gaining Caltrans project approval. Project responsibilities include overseeing preparation of technical documents including, Geometric Drawings, Design Standard Decision
Documents, DIB 78, Risk Register, Stormwater Data
Report and the Project Study Report - Project Report.

Other responsibilities include coordination with other
project disciplines as well as the Town of Windsor and
Caltrans.

El Camino Real Bike & Pedestrian Improvements
PA&ED Town of Colma
Civil lead for the development of the Project Study
Report-Project Development Support (PSR-PDS) for the
El Camino Real Bicycle and Pedestrian Improvement
Project. This project will enhance the economic
vitality and quality of life of its residents by improving accessibility, mobility, and circulation. The PSR-PDS
serves as the Project Initiation Document (PID) for this project, identifying the project needs and purpose,
stakeholder inputs, project alternatives, anticipated
right-of-way requirements, preliminary environmental
analysis, initial cost estimates, and additional potential funding sources. The PSR-PDS identified the type of
environmental documents to be prepared that moved
the project into the Project Approval and Environmental Document (PA/ED) phase and the coordination with
Caltrans for review and approval.

Main Street Redevelopment, Oakley
Project engineer for revitalizing the City of Oakley ‘s Multimodal Downtown Redevelopment project. This
roadway and streetscape project included parking
reconfiguration; improved transit stops, new drainage and ‘clean water” facilities to satisfy Contra Costa County C3 requirements, a new watermain, a new sewer trunk line,
new traffic signals including a traffic signal interconnect system, and relocation of overhead utilities. The project required stage construction to maintain continuous
vehicular, transit and pedestrian access during
construction.

SamTrans On-Call Planning Services, San Mateo
County
Project manager for an on-call planning contract
to support Samtrans. Task orders have included
development of a countywide bus stop improvement
plan and bus stop guidelines; the El Camino Real
Multimodal plan, which included planning-level
alternative development for 8 miles of El Camino Real;
and analyzing the Colma BART Station park and ride lot
for conversion to a transit-oriented development project.

Shoreline Boulevard Interim Bus Lane and Utility
Improvements, Mountain View
Lead civil designer responsible for design of road
improvements along the proposed bus lane corridor. The
project improvements will run along Shoreline Boulevard from Middlefield Road to Space Park Way. Improvements
include a reversible bus lane, replacement of a sewer
trunk line, and Dutch-inspired protected intersections.

The project requires Caltrans coordination and approval through the PEER process, as the modifications to the
median in the US 101 overcrossing and at the interchange ramps are in Caltrans right-of-way.

SR 4/Mokelumne Trail Pedestrian and Bicycle
Overcrossing, Mountain View
Project engineer responsible for design of the
Mokelumne Trail Pedestrian Overcrossing at SR 4.

The pedestrian overcrossing with bridge the gap in
the Mokelumne Coast to Crest Trail in Brentwood. The
project includes design and analysis of multiple bridge and path alignment alternatives with varying construction costs and project impacts. Mark Thomas prepared PEER
approval documentation for the CCTA and the project
gained PID and PA&ED approval with the approval of the
PEER document. Mark Thomas moved the project into
the PS&E phase, conducting structures type selection
through Caltrans. Mark Thomas prepared preliminary
maintenance agreement exhibits and has provided input
to the CCTA and City of Brentwood regarding the long
term maintenance issues and agreement.

Linden Avenue and Spruce Avenue Traffic Calming
Improvements, South San Francisco
Project engineer responsible for designing the final
design of street improvements to this older downtown
street, including pavement rehabilitation at intersections, construction of bulb-outs and bus pads, and updating
pedestrian ramps.

HSIP Signal Improvements, Concord
Deputy project manager responsible for providing civil
design of thirteen intersections in the City of Concord.

Survey information was used in our analysis of curb
ramps for ADA compliance as well as other design
deficiencies including sidewalk width. Mark Thomas
provided final design of improvements for those ramps
that were found to be non-compliant and relocated
utilities structures and drainage facilities that were in conflict. Further assistance was provided to the City with the E-76 paperwork for their federal funding package.

West Las Positas Corridor Plan, Pleasanton
Project manager to develop multiple preliminary design
alternatives for improvements to the West Las Positas
Boulevard Corridor (from Foothill Road to Fairlands Drive) with Toole Design. The corridor improvements include
a complete roadway improvement from sidewalks,
bike lanes, medians, intersections, traffic signals, and signaling. Mark Thomas is providing preliminary cost
estimates for the alternatives and 35% construction
documents for the chosen alternative.

SR 4 East Widening - Somersville Road to SR 160,
Antioch
Lead designer for the SR 4 widening and Somersville
Road interchange reconstruction, leading PS&E
development, roadway design, and geometric
refinements for a complex multimodal corridor
improvement project. Developed Caltrans-approved
design solutions that improved traffic operations,
enhanced pedestrian and bicycle access, minimized
right-of-way impacts, and reduced project costs by
more than $3 million. Coordinated with CCTA, Caltrans,
local agencies, and stakeholders to support accelerated project delivery and future transit accommodations.

SHAWN O'KEEFE, PE, QSD
Principal-in-Charge

EDUCATION
BS in Civil Engineering

REGISTRATION
PE California C71792
QSD California 25799
Shawn has more than 22 years of experience in municipal, land development and transportation engineering. He has designed and managed a wide variety of projects, including transit centers, park and ride lots, bike and pedestrian improvements, trails, local roadways, freeway interchanges and managed lanes, utility relocations, residential subdivisions, and industrial and commercial developments. Shawn brings a thorough understanding of a project from inception to completion. His experience includes leading the master plan preparation, through geometric design, drainage and utility design, utility coordination and the preparation of plans, specifications and estimates.

REPRESENTATIVE PROJECTS
Grand Boulevard Initiative (GBI), San Mateo and
Santa Clara Counties
Project manager for corridor-level planning and
preliminary design efforts for a multi-agency initiative to advance multimodal improvements along a state
highway corridor. Coordinated with transit agencies, local jurisdictions, and state partners to develop Complete
Streets solutions that enhance pedestrian, bicycle, and transit access. Contributed to public outreach, concept development, and integration of sustainable design
strategies to improve safety, mobility, and community
connectivity.

El Camino Real Bicycle and Pedestrian Improvement
PSR-PDS, Colma
Project manager providing oversight and management
for the development of the Project Study Report-Project Development Support (PSR-PDS) for the El Camino
Real Bicycle and Pedestrian Improvement Project. This
project will enhance the economic vitality and quality of life of its residents by improving accessibility, mobility, and circulation. The PSR-PDS serves as the Project
Initiation Document (PID) for this project, identifying the project needs and purpose, stakeholder inputs, project
alternatives, anticipated right-of-way requirements,
preliminary environmental analysis, initial cost estimates, and additional potential funding sources. The PSR-PDS
identified the type of environmental documents to be
prepared that moved the project into the Project Approval and Environmental Document (PA/ED) phase and the
coordination with Caltrans for review and approval.

Decoto Road Corridor Improvements, Fremont
Project manager responsible for this complete street
multi-modal connection project. Key goals for this
project include improved safety and enhanced
multimodal mobility and connectivity on Decoto Road.

Improvements include the realignment of ramps for
safety, implementation of continuous bike facilities and ADA-compliant sidewalks with enhanced crossings
through the interchange.

SR 116/West Cotati Avenue Reconfiguration Project
Cotati
Project manager supporting the City of Cotati with
preliminary engineering services to develop a vision
for a safer, connected, cohesive SR 116 corridor from
Alder Avenue to Redwood Drive and leading the design
development phase of the corridor improvements.

E. Blithedale Avenue Improvements, Mill Valley
Project manager for improvements on East Blithedale
Avenue in the City of Mill Valley. The project included widening the roadway for new Class IV bikeways,
restriping for new Class II and Class III bike facilities, reconstruction of curb ramps, drainage modifications and pavement rehabilitation on a key arterial corridor serving residents, schools and providing access to downtown
Mill Valley. Improvements were completed at existing
traffic signals with evaluation of potential roundabouts at multiple locations on East Blithedale Avenue between Sunnyside Avenue and Highway 101.

JASON FONG, PE
Regional Corridor Lead

EDUCATION
BS in Civil and Environmental Engineering

REGISTRATION
PE California C64542
Jason has more than 25 years of civil engineering experience in the public and private sector. He has successfully managed and designed multimodal and complete streets improvements within the public right-of-way, including transit, bicycle, and pedestrian mobility projects. His expertise spans federal, state, and local design standards, and he is wellversed in the Caltrans design requirements and Local Assistance Program Manual. With a strong focus on enhancing connectivity, mobility, and safety, he excels in integrating and executing clients' visions through the complexities of planning, permitting, and implementation stages.

REPRESENTATIVE PROJECTS
El Camino Real Bike & Pedestrian Improvements
PA&ED, Colma
Project manager responsible for advancing multimodal
improvements along the El Camino Real (SR 82) corridor
through the PA&ED phase. Led coordination with
Caltrans, local agencies, and stakeholders to support
environmental clearance (CEQA/NEPA) and maintain an
accelerated delivery schedule aligned with a concurrent SHOPP project. Oversaw alternatives refinement, traffic and utility investigations, and development of preliminary design and project reporting to improve safety,
accessibility, and multimodal connectivity.

Grand Boulevard Initiative (GBI), San Mateo and
Santa Clara Counties
Senior project engineer for corridor-level planning and preliminary design efforts for a multi-agency initiative to advance multimodal improvements along a state
highway corridor. Coordinated with transit agencies, local jurisdictions, and state partners to develop Complete
Streets solutions that enhance pedestrian, bicycle, and transit access. Contributed to public outreach, concept development, and integration of sustainable design
strategies to improve safety, mobility, and community
connectivity.

SamTrans On-Call Planning Services
Senior project engineer for planning and conceptual
design efforts under an on-call contract for a regional transit agency. The work included developing bus
stop improvement guidelines, multimodal corridor
planning with alternatives analysis and implementation
strategies, and transit-oriented development support.

Responsibilities included stakeholder coordination,
conceptual design, and evaluation of accessibility,
circulation, and transit facility improvements to enhance system performance and user experience.

I-880/Decoto Road Interchange PA&ED, Fremont
Senior engineer supporting the delivery of the Project
Approval and Environmental Document for the I-880/
Decoto Road Interchange Modernization Project. The
project will upgrade the existing interchange to better accommodate multimodal travel through the Decoto
Road and SR 84 (Dumbarton) corridor. Key improvements
include the implementation of new dedicated bus-only
lanes in the eastbound-westbound direction, as well as a physically separated Class I trail through the interchange to enhance bicycle and pedestrian comfort and safety.

US 395 Lassen County Wildlife Crossing, Susanville
Senior project engineer for engineering and
environmental services for a wildlife crossing program
along a state highway corridor, advancing the project
from alternatives analysis through PID, PA&ED, and
preliminary design. The work included coordination
with Caltrans and resource agencies, development
of environmental documentation (CEQA/NEPA), and
preparation of preliminary design and project reports to support approvals, improve safety, and enhance habitat
connectivity.

BRIANNA BOHONOK
Environmental

EDUCATION
MS in Urban Planning and Policy
BA in Architecture
Brianna has more than 13 years of experience as both a CEQA practitioner and land use planner. She has managed CEQA and NEPA documents for projects across the state, including highway/roadway projects, transit line extensions, mixed-use development, and land use projects. Her work is enriched by her experience as an environmental planner at Caltrans, District 4 and on major BART projects. Brianna has worked from the project initiation and programming phase through the final design and permitting phase of project approval. Her diverse experience allows her to be particularly effective in strategizing on the most efficient and defensible approach to environmental review. She offers flexible and thoughtful strategies based on the latest legislation, case law, emerging trends, and best practices.

REPRESENTATIVE PROJECTS
El Camino Real Bike & Pedestrian Improvements
PA&ED, Colma
Environmental lead responsible for management and
oversight for the environmental clearance, expected
in the form of a Categorical Exemption (CE) under
the California Environmental Quality Act (CEQA
and Categorical Exclusion (CE) under the National
Environmental Policy Act (NEPA). During this phase,
our team will conduct further investigations to better
understand impacts to traffic, properties and utilities, further refine the preliminary design, and develop the
Project Report. The El Camino Real (ECR) corridor serves as key north-south principal arterial that traverses the Town, connecting the City of South San Francisco with
Daly City and beyond to San Francisco and the greater
peninsula. ECR is part of the state highway system as
SR 82 and provides access to the Colma and South San
Francisco BART stations and serves SamTrans buses with
stops throughout the corridor. This project will improve multimodal infrastructure, accessibility, and safety for pedestrians, cyclists, transit users, and motorists.

US 395 Lassen County Wildlife Crossing, Susanville
Advisor for the environmental process for project delivery.

The project will design and construct two wildlife crossing structures (WCS) along U-395 between the California/
Nevada border and Susanville. The scope of work
involves developing and screening alternatives through
the PID document and to carry forward in environmental
and developing 65% design for two crossing locations.

The project involves coordinating planning and design
efforts with stakeholders including LCTC, Caltrans District 2, Wildlife Conservation Board (WCB), utility companies, and private property/business owners.

I-880/Decoto Road Interchange PA&ED, Fremont
Environmental lead for the delivery of the Environmental Document for the I-880/Decoto Road Interchange
Modernization Project. The project will upgrade the
existing interchange to better accommodate multimodal
travel through the Decoto Road and SR 84 (Dumbarton)
corridor. Key improvements include the implementation
of new dedicated bus-only lanes in the eastboundwestbound direction, as well as a physically separated Class I trail through the interchange to enhance bicycle and pedestrian comfort and safety.

SR 152/Pacheco Pass Wildlife Crossing, Santa Clara
County
Advisor for environmental strategy and oversight for
a wildlife crossing project along SR 152 in partnership with the Santa Clara Valley Habitat Agency and
High-Speed Rail Authority. Responsibilities included
coordinating with technical and agency stakeholders,
identifying and evaluating priority crossing locations, and advancing alternatives through PID and ongoing CEQA
clearance. The team developed conceptual designs,
supported Project Report approvals, and advanced
select alternatives toward 65% design to improve habitat connectivity, enhance highway safety, and protect
sensitive species.

HARFATEH GREWAL, PE, QSP
Drainage

EDUCATION
BS in Civil Engineering
MS in Civil Engineering

REGISTRATION
PE California C95969
QSP California 26791
Harfateh has more than 12 years of experience in small and large transportation projects in the Bay Area. He has worked on numerous projects, including complete streets, local roadway and intersection improvements, and highway and interchange improvements. His experience includes geometric design, stormwater, grading and drainage design, utility coordination, ADA compliance, and preparation of PSR/PDS, PA&ED, and PS&E.

REPRESENTATIVE PROJECTS
El Camino Real Bicycle and Pedestrian Improvement
PA&ED, Colma
Project engineer for planning and preliminary engineering services for multimodal corridor improvements along
a state highway. The work included advancing prior
concepts, supporting environmental clearance (CEQA/
NEPA), refining design alternatives, and developing
project documentation. Coordination with Caltrans and
local agencies supported an accelerated schedule
and alignment with concurrent projects, focusing
on improving safety, accessibility, and multimodal
connectivity.

SR 65/Placer Parkway Interchange PS&E, Placer
County
Project engineer assisting with the environmental
compliance for the first phase of the 14-mile Placer
Parkway Corridor. The first phase will complete a new
interchange at State Route 65 and a 1.8-mile extension to Foothills Boulevard. A grade crossing of the UPRR tracks and Industrial Boulevard is also included. The project will build off the approved Tier 1 environmental document
and will also complete Caltrans approval for both a PSR (PDS) and project report.

El Cerrito del Norte TOD Complete Street, El Cerrito
Project engineer for preliminary engineering, construction documents, local assistance coordination, and bidding
and construction support for the City of El Cerrito. This transit and complete streets improvement project will
provide new and enhanced pedestrian facilities and
bikeways along San Pablo Avenue, Eastshore Boulevard,
Hill Street, Cutting Boulevard, and Knott Avenue.

I-280/Winchester Boulevard Improvements, San Jose
Project engineer for engineering services to advance
interchange and local roadway improvements for a
high-activity urban corridor serving major commercial,
medical, and residential areas. The work included
progressing the project through PID, PA&ED, and
PS&E phases, with coordination among Caltrans, local
agencies, and stakeholders to improve traffic operations, reduce congestion, and enhance local circulation.

E. Blithedale Avenue Improvements, Mill Valley
Project engineer for improvements on East Blithedale
Avenue in the City of Mill Valley. Design elements
include the use of roundabouts, upgrades to existing
signal infrastructure, widening existing bikeways, and
improvements to pedestrian crossing paths along the
corridor from Sunnyside Avenue to US 101.

Charleston-Arastradero Corridor Improvements,
Palo Alto
Design engineer assisted in preparing “complete street” roadway improvement plans along the corridor. The
project would add innovative bicycle transportation
solutions which consist of modified signals, green bike lanes, cycle tracks and Copenhagen bike left turn lanes.

RYAN WHIPPLE, PE
Traffic Engineering
San Francisco County Transportation Authority, Interstate 280 (I-280)/Ocean Avenue Interchange
Parametrix provided the traffic signal, lighting, and electrical utility design work for the consultant team that is redesigning the I-280 southbound ramp intersection at Ocean Avenue in the City of San Francisco. The Parametrix team worked with the San Francisco County Transportation Authority (SFCTA), San Francisco Municipal Transportation Agency (SFMTA),
Caltrans, and PG&E on this project. As senior traffic engineer, Ryan was responsible for the final QA/QC of the traffic signal and illumination improvements. The design realigned the offramp, creating a new signalized intersection in the Caltrans right-of-way.

City of Belmont, El Camino Real and Hill Street Pedestrian Hybrid Beacon Project PS&E
Ryan served as the senior traffic engineer responsible for providing design guidance and quality control review for El Camino Real and Hill Street Pedestrian Hybrid Beacon Project for the City of Belmont. The project will improve pedestrian safety and bicycle connectivity, and includes design for a new pedestrian hybrid beacon across El Camino Real, consisting of new ADA-compliant curb ramps and a pedestrian passageway through an existing median island, as well as the extension of a left-turn pocket onto Ralston Avenue. Ryan provided quality control review of the signal Plans, Specifications, and Cost Estimates (PS&Es).

Town of Ross, Sir Francis Drake Traffic Signal Warrant Study Ryan was the project manager for a traffic signal warrant analysis study for a multi-legged intersection along Sir Francis Drake Boulevard in the Town of Ross in Marin County. In addition to evaluating the signal location against CA MUTCD warrants, Ryan also led discussions with local Town Council members to educate the overall warrant process.

City of Alameda, Lincoln Avenue/Marshall Way/Pacific
Avenue Safety Improvements
Ryan is the traffic design lead for the 30% through 100% PS&E phase for the Lincoln Avenue corridor. He is responsible for leading signing/striping, traffic signal, lighting, and traffic control design for the 3.1-mile-long corridor. The project provides for a “road diet” reducing the number of through lanes from four to two, adding a center two-way left-turn lane, and either buffered bike lanes or separated Class IV bikeways.

Additional improvements include new flashing beacons,
pedestrian hybrid beacons, roundabouts, storm water
improvements like bioretention and detention vaults, school access enhancements, crosswalk enhancements, and both
quick-build and permanent curb bulb extensions.

Town of Tiburon, State Route 131 (SR-131) Transportation Infrastructure Study
Ryan served as a senior traffic engineer on the overall SR131 Transportation Infrastructure Study. As a senior traffic engineer, he developed an ITS technical memo that provided justification for installing fiber optic conduit and cable along Tiburon Boulevard (SR-131), to be implemented in coordination with an upcoming Caltrans pavement preservation project.

This investment will support modern traffic signal operations, enable adaptive signal control technologies, and provide a long-term, multi-use communications backbone for the Town.

City of Paso Robles, On-Call Traffic Engineering
Ryan served as contract manager and senior traffic engineer for the City of Paso Robles’ on-call traffic control plan review services, a staff augmentation assignment supporting
review of traffic control plans and encroachment permits for construction projects and special events on state highways and local streets. Ryan provided traffic control plan review and oversight, including high-level Synchro-based capacity and delay analysis when needed, and supported refinement of signs, traffic signal equipment, signal timing, pavement markings, and other miscellaneous traffic engineering issues.

City of Albany, Marin Avenue Paving
Ryan provided QA/QC and high level design guidance for
various intersections along Marin Avenue in the City of Albany. Marin Avenue is a key corridor that experiences heavy commuter and school traffic, emphasizing the need for inclusive and safe transportation design. The 0.5-mile-long pavement rehabilitation project involves several intersection civil and transportation upgrades, including the retrofit and design of signal infrastructure to improve ADA compliance and be consistent with the latest construction standards.

Ryan is a traffic engineer and planner with extensive experience in transportation design and traffic operations analysis throughout California and Nevada. His background includes work with both public agencies and private consulting firms, giving him a wellrounded perspective and a strong technical foundation. Ryan has led the preparation of accurate and detailed traffic impact studies, conducted comprehensive transportation facility and intersection control analyses, and managed transportation and Complete Streets design projects. His expertise spans multiple design disciplines, including traffic signal design, signing and striping, maintenance of traffic (MOT), traffic control plans (TCP), and overhead sign design. Ryan is passionate about shaping the future of multi-modal transportation through thoughtful analysis and innovative design.

RELEVANT EXPERIENCE
Education: BS, Civil Engineering, University of California, Berkeley Registrations: Professional Engineer - Traffic, CA, #2821 | Professional Engineer - Civil, NV, #029432 Years of Experience: Total - 14 | With Parametrix - 2

ANDREW LEE, PE, TE, PTOE
Project Manager
Town of Atherton, El Camino Real Complete Streets Study As a subconsultant, Parmetrix developed the conceptual
plan alternatives for State Route 82/El Camino Real in the Town of Atherton and adjacent sections in Menlo Park and unincorporated San Mateo County. Andrew led the effort, which included developing conceptual cross-sections to
reimagine a six-lane suburban arterial to fill sidewalk gaps and add painted or separated bikeways. The project team advanced three alternatives for further study; the Parametrix team supported this effort by developing conceptual plan drawings that included add ADA-compliant bus stops and
intersection modifications and providing review support of the traffic modeling. The project is moving through the second phase public outreach process and aims to recommend a
preferred alternative to advance into environmental review and final design.

San Francisco County Transportation Authority, Interstate 280 (I-280)/Ocean Avenue Interchange
Andrew led the traffic signal, lighting, and electrical utility design work for the consultant team that is redesigning the I-280 southbound ramp intersection at Ocean Avenue in the City of San Francisco. The Parametrix team worked with the San Francisco County Transportation Authority (SFCTA), San Francisco Municipal Transportation Agency (SFMTA), Caltrans, and PG&E on this project. Parametrix developed the electrical design that accounts for the unique off-ramp alignment, center-running light rail tracks, overhead catenary lines and support poles, and a PG&E vault providing access to highvoltage transmission lines. The project reached its 60% design milestone in Summer 2025.

City of Menlo Park, Middle Avenue Complete Street Project Andrew led the planning study for the Middle Avenue project to identify near-term, multimodal traffic safety improvements for the one-mile-long corridor through a residential neighborhood in the City of Menlo Park. The Parametrix team analyzed traffic speeds, sight distances, intersection operations, and trip-generating land uses, like parks and churches. The team recommended signing and striping upgrades, improvements to storm drains, raised crosswalks, rectangular rapid flashing beacons, and pavement rehabilitation; Parametrix also
provided the design services for these improvements. Andrew provided construction support to identify an alternative design.

City of Belmont, El Camino Real and Hill Street Pedestrian Hybrid Beacon Project PS&E
Andrew served as project manager during the El Camino Real and Hill Street Pedestrian Hybrid Beacon Project for the City of Belmont, which will improve pedestrian safety and bicycle connectivity to the Belmont Caltrain Station and future housing sites. The project includes design for a new pedestrian hybrid beacon across El Camino Real, consisting of new ADAcompliant curb ramps and a pedestrian passageway through an existing median island, as well as the extension of a leftturn pocket onto Ralston Avenue. Parametrix also provided quality control review of the signal Plans, Specifications, and Cost Estimates (PS&Es).

City of Menlo Park, Middlefield Complete Streets
Andrew served as project manager during conceptual design and public outreach services that will build on the progress achieved in the first phase by refining the previously developed conceptual design, analyzing the corridor’s multimodal
safety and circulation needs, recommending a preferred
alternative, and supporting City staff in engaging the Menlo Park community to present the recommended design, solicit feedback, and refine the design.

City of Alameda, Masonic Intersections
Andrew was the lead transportation engineer for traffic signal, striping, and signage upgrades at two pathway crossings on the Ohlone Greenway (Masonic Avenue) in the City of Albany.

Andrew led the planning and analysis to add protected left turn signal phasing and presented the results to the City Transportation Commission. He led the Parametrix team that developed the construction documents for electrical, pavement delineation, and traffic signing improvements. Parametrix worked closely with City staff to provide construction support and coordination with the electrical contractor and the County of Alameda, which manages the City’s traffic signals.

Andrew serves as project manager, traffic engineer, and transportation planner for Complete Streets, traffic safety, and active transportation projects. He leads conceptual through final design for transportation and civil work; these include Complete Streets corridors, multiuse paths, controlled and uncontrolled intersections, traffic signals, and quick-build safety projects. Andrew’s planning work includes safety studies for schools and high-collision corridors, intersection operations, microsimulation models, and traffic signal phasing and timing plans. His project highlights include intersection safety retrofits, separated bikeways (cycle tracks), protected intersections, multiuse paths, traffic signals, roundabouts, and accessible design.

RELEVANT EXPERIENCE
Education: MA, Urban Planning, University of California, Los Angeles | BS, Civil Engineering, California Polytechnic University, San Luis Obispo | Project Management, University of California, Berkeley Extension Registrations/Certifications: Professional Engineer - Civil, CA, #86247 | Professional Engineer - Traffic, CA, #2455 | Professional Engineer - Civil, NV, #031456 | Professional Traffic Operations Engineer, #5817 Years of Experience: Total - 19 | With Parametrix - 3

AARON SEITZ, PE
Civil Lead

EDUCATION
BS in Civil Engineering

REGISTRATION
PE California 94922
Aaron has more than seven years of engineering design experience for public works projects and transportation facilities. His experience includes local roadway improvements, active transportation facilities, transit facilities, traffic control, construction staging, and streetscape designs.

REPRESENTATIVE PROJECTS
Soquel Drive Multimodal Improvements, Santa Cruz
County
Design engineer responsible for the design of active
transportation, bus transit, and pedestrian improvements along Soquel Drive between La Fonda Drive and State
Park Drive. This segment of the corridor serves as an
alternate vehicular route to Highway 1 which leads to
heavy traffic congestion, frequently by speeding vehicles associated with cut-through traffic. Through this project, the County intends to improve safety for all modes of
transportation, increase multi-modal options, reduce
traffic congestion, decrease incidence of collision, and improve transit reliability along this segment.

SamTrans On-Call Planning Services
Project engineer for planning and conceptual design efforts under an on-call contract for a regional transit agency.

The work included developing guidelines for transit facility improvements, preparing corridor-level multimodal planning studies with alternatives analysis and implementation
strategies, and supporting transit-oriented development concepts. Responsibilities included stakeholder
coordination, conceptual design, and evaluation of
accessibility, circulation, and transit operations to enhance system performance and user experience.

El Camino Real Bicycle and Pedestrian Improvement
PA&ED, Colma
Project engineer for planning and preliminary engineering services for multimodal corridor improvements along
a state highway. The work included advancing prior
concepts, supporting environmental clearance (CEQA/
NEPA), refining design alternatives, and developing
project documentation. Coordination with Caltrans and
local agencies supported an accelerated schedule
and alignment with concurrent projects, focusing
on improving safety, accessibility, and multimodal
connectivity.

Windsor Downtown Bike/Ped Crossing, Town of
Windsor
Project engineer for design services for a bicycle and
pedestrian crossing improvement within a constrained
corridor. The work included development of preliminary
design concepts, evaluation of multimodal alternatives, and coordination with Caltrans to advance the project
through the approval process. Improvements focused
on enhancing safety, accessibility, and separation of
pedestrian and bicycle facilities while addressing site constraints and existing infrastructure conditions.

Broadway Grade Separation, Burlingame
Project engineer for the grade separation of Caltrain
tracks and Broadway Avenue in Burlingame. It includes
temporary at-grade crossings on Broadway that will
be relocated for the shoofly tracks and then eventually removed once the grade separation is completed.

Modifications of the at-grade crossing required close
coordination with Caltrain, UPRR and CPUC.

CHRISTOPHER KO, EIT
Civil Support

EDUCATION
BS in Civil Engineering

REGISTRATION
CA EIT 176735
Chris has more than 11 years of engineering design experience for public works projects and transportation facilities.

His experience includes local roadway improvements, corridor studies, active transportation facilities, and streetscape designs. Chris’ attention to detail and skill with AutoCAD plan preparation will provide an efficient use of resources in developing alternative conceptual plans and cost estimates.

REPRESENTATIVE PROJECTS
El Camino Real Bicycle and Pedestrian Improvement
PSR-PDS, Colma
Design engineer for the development of the Project Study Report-Project Development Support (PSR-PDS) for the
El Camino Real Bicycle and Pedestrian Improvement
Project. This project will enhance the economic
vitality and quality of life of its residents by improving accessibility, mobility, and circulation. The PSR-PDS
will serve as the Project Initiation Document (PID) for this project, identifying the project needs and purpose, stakeholder inputs, project alternatives, anticipated
right-of-way requirements, preliminary environmental
analysis, initial cost estimates, and additional potential funding sources. The PSR-PDS will also identify the type of environmental documents to be prepared to move
into the Project Approval and Environmental Document
(PA&ED) phase and the coordination with Caltrans for
review and approval.

El Camino Real Bicycle and Pedestrian Improvement
PA&ED, Colma
Design engineer for planning and preliminary engineering services for multimodal corridor improvements along
a state highway. The work included advancing prior
concepts, supporting environmental clearance (CEQA/
NEPA), refining design alternatives, and developing
project documentation. Coordination with Caltrans and
local agencies supported an accelerated schedule
and alignment with concurrent projects, focusing
on improving safety, accessibility, and multimodal
connectivity.

I-880/Decoto Road Interchange PA&ED, Fremont
Design engineer for engineering services to support
interchange modernization and multimodal corridor
improvements on a state highway facility. The work
included advancing projects through planning,
environmental, and design phases; coordinating with
Caltrans, local agencies, and transit providers; and
supporting stakeholder engagement. Efforts focused
on improving traffic operations, enhancing multimodal
access, and integrating transit, bicycle, and pedestrian facilities within a complex urban corridor.

On-Call Civil Engineering and Surveying Services,
Santa Cruz
Design engineer for engineering and planning support
across multiple transit facility and corridor improvement projects. Services included conceptual design, facility planning, and system upgrades for operations, safety,
and accessibility. The work involved optimizing site
layouts, evaluating transit circulation and parking
needs, developing preliminary infrastructure and utility improvements, and supporting feasibility studies
for transit-enhancing strategies to improve system
performance and user experience.

SamTrans On-Call Planning Services
Design engineer for planning and conceptual design efforts under an on-call contract for a regional transit agency.

The work included developing guidelines for transit facility improvements, preparing corridor-level multimodal planning studies with alternatives analysis and implementation
strategies, and supporting transit-oriented development concepts. Responsibilities included stakeholder
coordination, conceptual design, and evaluation of
accessibility, circulation, and transit operations to enhance system performance and user experience.

DANIELLE KEITH
Environmental Support

EDUCATION
MS in Environmental Studies
BA in Political Science
Training in Coursework in CEQA and NEPA
Danielle has more than six years of experience as a dedicated CEQA/NEPA environmental planner, specializing in environmental documentation, project management, and regulatory compliance for major infrastructure projects such as multimodal transportation, interchange improvements, and rail. She excels at coordinating multidisciplinary teams, building strong client and stakeholder relationships, and navigating complex regulatory frameworks to consistently deliver projects on time and within budget. Her expertise includes CEQA and NEPA documentation, environmental economics and policy, U.S. Department of Housing and Urban Development (HUD) environmental assessments, and technical knowledge in hydrology, geology, hydrogeology, and agricultural analysis. Danielle is highly skilled in environmental impact analysis, permitting, and integrating environmental considerations into transportation planning and design, with a commitment to innovative solutions that balance sustainability with project goals and client needs.

REPRESENTATIVE PROJECTS
Grand Boulevard Initiative (GBI), San Mateo and
Santa Clara Counties
Environmental planner for corridor-level planning and
preliminary design efforts for a multi-agency initiative to advance multimodal improvements along a state highway
corridor. Coordinated with transit agencies, local jurisdictions, and state partners to develop Complete Streets solutions that enhance pedestrian, bicycle, and transit access.

Contributed to public outreach, concept development, and integration of sustainable design strategies to improve safety, mobility, and community connectivity.

Lindhurst Corridor Improvements, Linda
Environmental planner for a roadway revitalization project transforming Lindhurst Avenue and the western segment
of North Beale Road into a multimodal, communitycentered “Main Street.” Contributed to the planning and design of pedestrian-oriented streetscapes, landscaped
parkways, gateway features, and public art elements that reflect local character and cultural identity. Assisted in advancing improvements that enhance mobility, safety, and accessibility for all users, including drivers, transit riders, pedestrians, and cyclists. The project promotes sustainable development, supports long-term community investment,
and creates a more attractive and connected corridor that serves as a central focal point for the community.

El Camino Real Bicycle and Pedestrian Improvement
PA&ED, Colma
Environmental planner for planning and preliminary
engineering services for multimodal corridor
improvements along a state highway. The work included
advancing prior concepts, supporting environmental
clearance (CEQA/NEPA), refining design alternatives,
and developing project documentation. Coordination
with Caltrans and local agencies supported an
accelerated schedule and alignment with concurrent
projects, focusing on improving safety, accessibility, and multimodal connectivity.

US 101/Dry Creek Interchange, Headlsburg
Environmental planner for a corridor and interchange
improvement project addressing congestion, safety,
and multimodal access along Dry Creek Road and US
101. Contributed to preparation of the Project Study
Report–Project Development Support (PSR‑PDS) under
Caltrans oversight, including defining project purpose
and need, evaluating alternatives, and informing the
scope of future environmental review and technical
studies for the PA&ED phase. Assisted in assessing
improvements such as roundabout configurations,
ADA-compliant pedestrian facilities, separated sidewalks and bikeways, and protected intersection concepts to
enhance safety and connectivity for all users. The project aims to reduce congestion and queuing, improve traffic
operations, and expand bicycle and pedestrian access
across the corridor while supporting regional mobility and community growth.

RYAN BISSEGGER
Funding

EDUCATION
BA in International Business
Training in Funding and Programming Transportation Projects in CA Ryan has more than 22 years of experience in the engineering industry. He has held various roles including technical editor, proposal writer, and business development. Ryan has grown to become Mark Thomas' funding expert. He is very knowledgeable of federal and state funding sources including the Active Transportation Program (ATP), Highway Safety Improvement Program (HSIP), and the new Senate Bill (SB 1) programs. He tracks the programs and is knowledgeable of call for project schedules. He has provided funding recommendations to agencies to pursue in order to implement improvements. Ryan has experience developing and reviewing grant applications. His understanding of the funding programs and experience developing proposals has been leveraged in the preparation of competitive grants.

REPRESENTATIVE PROJECTS
US 101/SR 84/Woodside Road Grant Assistance,
Redwood City
Project manager for providing ongoing funding support
and agency coordination with Caltrans District 4 and
Headquarters. Developed grant narratives, supporting
maps, and economics analysis for grant applications.

Prepared multiple grant applications for the Project,
including a successful INFRA grant for $105 million and a regional grant application for Measure A funds from
SMCTA. Following the grant submittals, involvement
continued through development of updated project fact
sheets, engagement strategies with elected officials,
updated funding plan, and preparation of project
branding.

I-80/I-680/SR 12 Interchange Complex Initial
Construction Package PS&E, Solano County
Grant writer responsible for preparing a TCEP and INFRA grant applications for components of the I-80/I-680/SR12 Interchange Project. Overall, this project is a $2 billion program to redesign this freeway-to-freeway interchange to improve traffic operations and goods movement. The
work included developing grant application narratives,
coordinating with Caltrans, researching economic
impacts of the project on I-80 and demonstrating the
improved freight operations on the highway.

El Camino Real Bike & Pedestrian Improvements
PA&ED, Colma
Grant writer supporting planning and preliminary
engineering services for multimodal corridor
improvements along a state highway. The work included
advancing prior concepts, supporting environmental
clearance (CEQA/NEPA), refining design alternatives,
and developing project documentation. Coordination
with Caltrans and local agencies supported an
accelerated schedule and alignment with concurrent
projects, focusing on improving safety, accessibility, and multimodal connectivity.

El Camino Real Bicycle and Pedestrian Improvement
PSR-PDS, Colma
Grant writer supporting planning and preliminary
engineering services for multimodal corridor
improvements along a state highway. The work included
development of project initiation documentation,
alternatives evaluation, environmental coordination,
and refinement of preliminary design concepts.

Coordination with Caltrans and local agencies supported environmental clearance and advancement into
subsequent design phases, with a focus on improving
safety, accessibility, and multimodal connectivity.

SHERRIE ZIMMERMAN, PLS
Survey/Mapping

EDUCATION
AA in Architecture
AS in Survey

REGISTRATION
PLS California 8964
Sherrie has more than 22 years of experience as a city surveyor, survey manager, project surveyor, party chief and survey technician. Her projects includes complex boundary and topographic surveys, preparation and filing of records of survey, ALTA surveys, parcel and final maps, lot line adjustments, certificates of compliance, survey, and mapping reviews for compliance with the Subdivision Map Act and Land Surveyors Act, construction staking, plat and legal description preparation. She works with GPS equipment (Trimble R-8 and R-10), conventional total stations (Trimble S6 and S7) and high-definition scanning HDS (Leica C-10, Trimble SX-10, and TX-8).

REPRESENTATIVE PROJECTS
SR 152/Pacheco Pass Wildlife Crossing, Santa Clara
County
Lead surveyor for planning and design services for a
new wildlife crossing along SR 152 at Pacheco Pass. SR
152 Pacheco Pass is a prime area for linking populations of mountain lions, tule elk, mule and black-tailed deer, American badgers, bobcats, and other wildlife species.

The CA Department of Fish and Wildlife identified
the area as a wildlife movement barrier, as it impedes
important North-to-South wildlife movement, fragments
habitats, and hinders wildlife 's ability to adapt to climate change. The new crossing will lessen infrastructure
impacts on natural resources, enhance highway safety
for vehicles, protect endangered species, and avoid
fragmenting natural habitats for local wildlife.

Oakley-East Cypress Road Lane Alignment, Oakley
Project surveyor supporting professional engineering
services for this feasibility study of the westbound (WB) Cypress Road and right turn lane improvements onto
Main Street at the Cypress Road/Main Street intersection.

The purpose of the feasibility study is to determine the feasibility, cost, and design options of constructing a dedicated right turn lane for westbound Cypress Road
onto Main Street.

El Camino Real Bike & Pedestrian Improvements
PA&ED, Colma
Lead surveyor for planning and preliminary engineering
services for multimodal corridor improvements along
a state highway. The work included advancing prior
concepts, supporting environmental clearance (CEQA/
NEPA), refining design alternatives, and developing
project documentation. Coordination with Caltrans and
local agencies supported an accelerated schedule
and alignment with concurrent projects, focusing
on improving safety, accessibility, and multimodal
connectivity.

US 395 Lassen County Wildlife Crossing, Susanville
Lead surveyor for engineering and environmental
services for a wildlife crossing program along a state
highway corridor, advancing the project from alternatives analysis through PID, PA&ED, and preliminary design. The work included coordination with Caltrans and resource
agencies, development of environmental documentation
(CEQA/NEPA), and preparation of preliminary design and
project reports to support approvals, improve safety, and enhance habitat connectivity.

MARSHALL MOORE, PE, SE
Structures

EDUCATION
BS in Civil Engineering
MS in Civil Engineering

REGISTRATION
PE California C81380
SE California S6557
Marshall has more than 14 years of transportation engineering experience. He has been involved in designing and checking various structural and roadway elements related to transportation projects. He has been responsible for applying national, local, and project specific structural and roadway design codes to structures and roadways including viaducts, bridges, retaining walls, sign structures, foundations, Interstate highways, High Occupancy and Toll (HOT) Lane facilities, County and local roadways and transit structures. Marshall has also been responsible for project plans, including structural and roadway plans.

REPRESENTATIVE PROJECTS
SR 65/Placer Parkway Interchange PS&E, Placer
County
Project engineer for the preparation of the project report, utility coordination, and preliminary engineering and
cost estimates for the first phase of the 14 mile Placer Parkway Corridor. The first phase will complete a new
interchange at SR 65 and a 1.8 mile extension to Foothills Boulevard. A grade crossing of the UPRR tracks and
Industrial Boulevard is also included. The project will build off the approved Tier 1 environmental document and will complete Caltrans approval for both a PSR (PDS) and
project report.

I-280/Winchester Boulevard Improvements, San
Jose
Project engineer for PA&ED for improvements to alleviate congestion on the freeway, evaluated alternatives for
adding an off-ramp from I-280 North to Winchester
Boulevard. Also evaluated local roadway connections
and widening the Winchester Boulevard overcrossing of
I-280. Project involved coordination with local agencies, community groups, and property owners and developers.

On-Call Design Services, Humboldt County
Project engineer for the storm damage projects funded
by FEMA and FHWA. Managed the preparation of
funding and PS&E packages for several storm damage
projects. Projects included sites with soldier pile walls up to 40 feet in height, reconstruction of roadways and drainage, roadway retreats and other improvements.

US 50/Hazel Avenue Interchange, Sacramento
County
Project engineer supporting the delivery of a PSR and
PA&ED for modifications of the existing interchange
and new roadway improvements associated with the
extension and grade separation of Hazel Avenue over
Folsom Boulevard to a future intersection within the
approved Easton Place development. Hazel Avenue is
one of three major crossings of the American River in
Sacramento County and will ultimately be a six-lane
thoroughfare. This project has a number of stakeholders (Sacramento County, City of Rancho Cordova, Caltrans
and the eastern development) that had conflicting
interests.

I Street Bridge Deck Conversion, West Sacramento
Structures engineer for PA&ED to convert the existing
upper deck of the bridge to dedicated bike and
pedestrian use. Part of the deck conversion will include the removal of the existing ramps and viaducts leading
to the upper deck of the I Street Bridge which would
remove vehicle access to the bridge. Pedestrian access
across the river and maintaining the pedestrian and
bicycle access for improved walkability and bike-ability to both sides of the river was evaluated.

CHRISTINE ANDERSON, PLA,
CLARB
Landscape

EDUCATION
BS in Landscape Architecture

REGISTRATION
CLARB California 36934
RLA California 3377
Christine has more than 36 years of experience in landscape architecture, urban design, landscape design and master planning. While her specific forte is that of urban design and redevelopment, she has consulted on a diverse range of projects, including redevelopment streetscapes, schools, urban developments, commercial centers, municipal and private office developments, open spaces, parks and playgrounds, interpretive trails, sports facilities, and master planned communities. Christine has extensive experience in all phases of design and construction documentation, including project management and community facilitation.

REPRESENTATIVE PROJECTS
Grand Boulevard Initiative (GBI), San Mateo and
Santa Clara Counties
Landscape architect for corridor-level planning and
preliminary design efforts for a multi-agency initiative to advance multimodal improvements along a state highway
corridor. Coordinated with transit agencies, local jurisdictions, and state partners to develop Complete Streets solutions that enhance pedestrian, bicycle, and transit access.

Contributed to public outreach, concept development, and integration of sustainable design strategies to improve safety, mobility, and community connectivity.

Washington Avenue and Table Mountain Boulevard
Complete Streets Project, Oroville
Landscape architect for a Complete Streets corridor
improvement project. The work included advancing
design through preliminary and final phases,
coordinating with state and local agencies, and
supporting environmental clearance and right-of-way
considerations. Improvements focused on enhancing
multimodal connectivity, safety, and accessibility through development of pedestrian, bicycle, and roadway
enhancements within an existing corridor.

East Main Street Improvements, Woodland
Landscape architect responsible for aesthetic design
for improvements to the E. Main Street corridor which
include safety upgrades along rail lines, multi modal
access for cyclist and pedestrians, enhanced drainage
facilities and aesthetics to achieve a complete street. Part of these improvements are located at the I-5 southbound on-ramp which requires Caltrans coordination.

El Camino Real Bike & Pedestrian Improvements
PA&ED, Colma
Landscape architect for planning and preliminary
engineering services for multimodal corridor
improvements along a state highway. The work included
advancing prior concepts, supporting environmental
clearance (CEQA/NEPA), refining design alternatives,
and developing project documentation. Coordination
with Caltrans and local agencies supported an
accelerated schedule and alignment with concurrent
projects, focusing on improving safety, accessibility, and multimodal connectivity.

Bascom Avenue Complete Street Improvements,
Santa Clara County
Landscape architect responsible for the landscape
design elements for the project. The Bascom Corridor
Complete Streets project is a joint project with VTA, the City of San Jose, the City of Campbell, and the County
of Santa Clara. The project prioritizes multi-modal transit stop enhancements, wayfinding, street tree planting
for pedestrian and cyclist shade and proposes use
of stormwater and flow-through planters to augment
traditionally irrigated plantings.

DEANNA GIBSON
Graphic Support

EDUCATION
Training in Geographic Information Systems, Diablo Valley College Training in Art History, University of London

REGISTRATION
Deanna has more than 20 years of experience providing 3D models, project visualization exhibits and geographic information system (GIS) project support for a diversity of transportation projects including interchanges, highways, and local roadways. Her experience includes using ArcGIS Desktop 10.4 and AutoCAD software for mapping, spatial analysis, data conversion, geodatabase creation from spatial and non-spatial data, spatial analysis including raster calculation and analysis, and managing and maintaining GIS data. Trimble SketchUp, AutoCAD Civil 3D, 3D Studio Max, and the Adobe suite for the production of project visualization materials. Deanna works with internal and external clients to develop project visualization graphics, GIS data and map products per project and client guidelines. She also prepares data documentation or metadata for GIS projects following client and/or corporate standards.

REPRESENTATIVE PROJECTS
Bicycle and Pedestrian Design Services, Town of
Atherton
GIS specialist responsible for developing project maps and exhibits. MTCo is designing Class III improvements on 13 streets while preparing preliminary engineering documents and cost estimates for Class I and II improvements along six additional roads. The firm also is designing and coordinating the modification of a major pedestrian crossing on El
Camino Real and Selby Lane. When completed, these
improvements will provide the most comprehensive bicycle accommodation in the Town’s history.

Grand Boulevard Initiative (GBI), San Mateo and
Santa Clara Counties
Graphics lead supporting corridor-level planning and
preliminary design efforts for a multi-agency initiative to advance multimodal improvements along a state highway
corridor. Coordinated with transit agencies, local jurisdictions, and state partners to develop Complete Streets solutions that enhance pedestrian, bicycle, and transit access.

Contributed to public outreach, concept development, and integration of sustainable design strategies to improve safety, mobility, and community connectivity.

I-80/Richards Boulevard PSR-PDS, Davis
Graphics lead supporting engineering services to
advance interchange improvements on a state highway
facility. The work included progressing the project
through planning, environmental clearance, and final
design phases, and coordinating with Caltrans and
local agencies. Improvements focused on enhancing
multimodal safety and accessibility, including separation of bicycle and pedestrian facilities from vehicular traffic to improve operations and overall corridor performance.

Design Services During Construction State Route 4
Bypass Sand Creek Road Interchange and 4 Lanes
Laurel to Sand Creek Road, Contra Costa County
GIS specialist responsible for developing exhibits
generated from ArcMap and georeferencing nonspatial
data for use in AutoCAD, Microstation, and ArcGIS.

US 101/Hillsdale Pedestrian/Bicycle Overcrossing
Preliminary Design and PSR-PDS, San Mateo
Graphics lead supporting planning and preliminary
engineering services for a bicycle and pedestrian
overcrossing project on a state highway facility. The work included development of project initiation documentation, conceptual design, and coordination with Caltrans and
local agencies. Efforts also involved public outreach and aesthetic studies to support design decisions, with a
focus on improving multimodal connectivity, safety, and user experience across a major transportation corridor.

Amando Castro, PE
Project Manager
Amando is a Project Manager with extensive experience in geotechnical engineering, pavement design, and construction support for transportation and public infrastructure projects. He has led geotechnical investigations, slope stability analyses, and pavement evaluations across California, including levee repairs, roadway rehabilitation, bridge foundations, and water infrastructure. Amando regularly prepares design recommendations, foundation reports, and construction-phase support documents, integrating subsurface data and site constraints to ensure constructability, performance, and compliance.

REPRESENTATIVE PROJECTS
City of Burlingame Pavement Engineering Services, San Mateo County, CA Project Engineer II. Prepared a Draft Pavement Design Report for the City of Burlingame 2024 Street Resurfacing Program at Airport Boulevard Between Anza Blvd and Bay View Place. The City requested rehabilitation options using Partial Depth Recycling (PDR) such as Cold In-place Recycling (CIR) or Cold Central Plant Recycling (CCPR). Completed pavement corings at 8 locations, performed laboratory testing, and evaluated the condition of the pavement. Provided CIR, CCPR, and Mill and Overlay options for a portion of the roadway, and full depth rehabilitation for a section that required a more robust rehabilitation strategy.

WBSD Flow EQ & Resource Recovery, San Mateo County, CA
Project Engineer. Prepared a Geotechnical Memorandum to evaluate subsurface conditions for a new outfall consisting of twin 24-inch pipelines beneath a raised levee and future site development. Work addressed a site underlain by soft Bay Mud with variable fill, assessing settlement, temporary slope instability, groundwater, and corrosion potential.

Services included site reconnaissance, exploratory boring, laboratory testing, subsurface characterization, and geotechnical analysis to support design recommendations for levee grading, shoring, dewatering, and trench stabilization.

Signalization of Mariposa Road and Jack Tone Intersection, San Joaquin County, CA
Served as Senior Engineer on a roadway signalization and widening project, performing geotechnical investigations including hand auger borings, lab testing, pavement evaluation, and engineering analysis. Evaluated subgrade conditions, concrete and asphalt pavement performance, and impacts from frequent heavy truck traffic. Developed pavement design recommendations such as Joint Plane Concrete Pavement (JPCP), traditional HMA sections with and without lime-treated subgrade, and full-depth HMA alternatives. Addressed construction challenges related to clayey soils and provided guidance on subgrade preparation and compaction to ensure long-term durability under high loading conditions.

Duncan Road and Comstock Road Roundabout, San Joaquin County, CA As Project Engineer, Amando completed a Geotechnical Memorandum for a new roundabout with roadway widenings to the roadway leading up to the roundabout.

Crawford staff completed 6 hand auger borings, performed an R-value test on soil samples, and developed recommendations for new pavement at the road widening sections.

Gibson Road at SR-113 Interchange Modification, Yolo County, CA Project Engineer for a Geotechnical Design and Materials Report. Improvements include widening the off-ramp, adding a new right turn lane, new pedestrian walkway, and traffic signal modifications. The report included results of laboratory testing on soil samples and a review of site conditions, geology, soil, and groundwater conditions. Provided recommendations structural pavement sections. Key geotechnical issues include slope stability of the embankment and pavement section thicknesses required to meet the design TI.

Broadway Complete Streets Project, Sacramento County, CA Project Engineer. Performed 6 pavement corings to measure existing pavement structure section thickness and collect subgrade samples for laboratory testing; performed hang auger borings; and performed R-Value testing. Recommended digout locations by walking

EDUCATION
B.S. Civil Engineering,
California State University,
Sacramento, 2019

REGISTRATIONS
• Civil Engineer, CA #94561
• APNGA Nuclear Gauge
Safety & U.S. DOT
Hazmat Certification

EXPERIENCE
At Crawford: 8 years
Total: 8 years
Amando Castro, PE
the roadway and reviewing pavement core data. Provided recommendations for new pavement sections, Deep Lift HMA, and Mill and Overlay.

Fred Jackson Way First Mile/Last Mile Connection Project, Contra Costa County, CA The project includes design for pavement rehabilitation, reduction in the pavement profile, relocation of utility poles, striping/signage, ADA compliant ramps, roadway/sidewalk widening, buffered bike lanes, and bulb-outs. The project segment is about 3,200 ft long. Completed four pavement corings and evaluated the condition of the existing pavement, performed R-Value testing, and performed pavement calculations and engineering analysis. Provided overlay recommendations, new pavement sections, and minimum concrete sidewalks/flatwork sections.

City of Turlock Various Streets Pavement Rehab, Stanislaus County, CA Project Manager. Prepared a Pavement Condition Assessment Memo for the City of Turlock’s on-call pavement rehabilitation program covering multiple assessment districts. The project focused on evaluating pavement conditions across more than 400 streets historically maintained by slurry seals, primarily in northern and outer portions of the city.

Objectives were to document existing pavement distress, compare findings with StreetSaver Pavement Condition Index (PCI) data, and guide future maintenance and rehabilitation strategies. Services included walking surveys, distress measurement (shrinkage, block, and alligator cracking, rutting), and correlation with PCI ratings. Key findings showed most streets in good to fair condition with low-severity shrinkage cracking, while several corridors displayed severe block and alligator cracking, requiring mill and overlay or full reconstruction rather than slurry seals.

Kewin Mill Road Rehab and Standard Road Rehab, Tuolumne County, CA Tuolumne County plans to perform pavement rehabilitation in the form of full depth reclamation - cement (FDR-C) along ~1 mile of roadway with site grading of the shoulders to improve drainage. Amando was Project Engineer and performed verification of depth of mix and moisture seal/moisture conditioning; compaction testing; pan testing; checking for microcracking; documenting cement tags and HMA load tickets; retrieved HMA samples and checked for temperature; performed HMA compaction testing and observation; and observed the rehabilitated roadway during use. Provided daily field reports to the client.

Granger Neighborhood Pavement Rehabilitation, Stanislaus County, CA Project Engineer for a Draft Pavement Memo to present the results of pavement coring and R-value testing. The project includes pavement rehabilitation, new signage, replacement striping, ADA upgrades, improved storm drainage, and traffic modifications. Cored the pavement at 28 locations along 10 streets in the Granger Neighborhood to measure the existing asphalt concrete and aggregate base section thicknesses, collected subgrade samples for R-value testing, and provided core results. The City of Modesto will be utilizing the core results to develop pavement section recommendations.

Petersen Memorial Way Pavement Rehabilitation, Butte County, CA Senior Engineer. The project includes rehabilitation of 2.5 miles of pedestrian train, bike path, and access route for vehicles.

Completed site visits, pavement coring, and laboratory testing to prepare a Pavement Design Report. The report recommends Full Depth Reclamation (FDR) as a cost-effective solution for rehabilitation. This method involves recycling existing pavement materials with additives, enhancing the structural pavement section. Traditional two-part pavement sections are presented as an alternative.

Walnut Avenue Improvements, Sacramento County, CA
Senior Engineer. Prepared a Draft Geotechnical Design Report for the rehabilitation of Walnut Avenue, a major east–west corridor serving schools, parks, fire services, and Highway 99 access, with improvements including 400 feet of new sidewalks, ADA-compliant ramps, pedestrian safety features, and pavement rehabilitation between Carillion Boulevard and Elk Hills Drive, as well as Stockton Boulevard and Emerald Vista Drive. Objectives included providing geotechnical recommendations to support roadway upgrades and correcting localized settlement near underground utilities. Services included site reconnaissance, hand auger borings, Wildcat and Kessler dynamic cone penetrometer testing, pavement coring, laboratory testing, and engineering analysis. Key issues addressed were poor pavement condition, expansive clay subgrade, and settlement linked to improperly compacted trench backfill, with recommendations for Full Depth Reclamation (FDR), HMA overlays, and utility coordination
Geer Road Pavement Rehabilitation, Stanislaus County, CA Project Manager in charge of a Pavement Design Report to provide rehabilitation recommendations for about 2.6 miles of roadway. Completed 29 pavement corings to measure existing pavement sections and walked the length of the pavement to review existing conditions. Utilized the Caltrans Highway Design Manual to back calculate Traffic Index. Rehabilitation recommendations included Mill and Overlay; Full Depth Reclamation (FDR); Full Depth HMA; Traditional Pavement Sections; and Reduced TI Mill and Overlay to extend pavement life.

Herndon Infrastructure Improvement, Stanislaus County, CA Proposed project elements include pavement rehabilitation; new sidewalk, curb, and gutter; new storm drainage facilities; new sewer piping, manholes, and connections; and new water piping. Prepared a Draft Geotechnical Design and Materials Report to provide results of subsurface exploration and testing, engineering analysis, and conclusions. Pavement recommendations include Traditional Pavement Sections; Overlay; Modified Full Depth HMA; and Full Depth Reclamation (FDR). Other Geotechnical recommendations provided include concrete sidewalks and flatwork; trench stability for piping; and grading recommendations.
1 Mark Shindler
Right of Way Consultant
Mark Shindler joined Associated Right of Way Services, Inc. in 2023 as a Right of Way Consultant providing valuation services and general right of way consulting, with an emphasis on transportation assignments involving Caltrans oversight. His in-depth knowledge of federal and state guidelines related to right of way, in addition to his strong managerial skills, makes him a valuable team member and asset to AR/WS clients. Mr. Shindler started his career in 1982 as a Junior Right of Way Agent and retired as the District Office Chief over Appraisals, Estimating, Property Management and Excess Land Sales in the Property Management Section.

Relevant Experience
Town of Colma
El Camino Real Bicycle and Pedestrian Improvement Project Cost Estimating
The project proposes to improve safety and mobility for people who walk and bike along El Camino Real. The right of way estimate for the project’s PID phase involved the analysis of 2 alternatives with impact analysis required for over 70 properties. Mr. Shindler prepared the right of way conceptual cost estimate.

San Mateo County Transportation Authority
Alpine Road Corridor Improvement Project
Cost Estimating
Mr. Shindler prepared Caltrans Right of Way Data Sheets for two alignment alternatives, including 3 and 2 parcels. The properties were commercial uses and acquisitions include partial fee takes and temporary construction easements.

Santa Clara Valley Transportation Authority
SR 17 Corridor Congestion Relief Project
Cost Estimating
The project proposes to relieve congestion and improve traffic operations on the freeways and local roadways, reduce cut through traffic in the Town of Los Gatos and improve bicycle and pedestrian facilities and connectivity. The right of way estimate involved the analysis of 18 properties. Mr. Shindler assisted in the preparation of the right of way estimate, including comparable sales research, valuation conclusions, and identification of site improvements impacted by the proposed design.

Santa Clara Valley Transportation Authority
US 101 / SR 152 / 10th Street Interchange Improvement Project Cost Estimating
The project proposes to widen the existing 10th Street Bridge from four lanes to six lanes, upgrade the northbound and southbound USFirm Associated Right of Way
Services
Education
BS, Business Administration,
California State University,
Hayward
Memberships
International Right of Way
Association
Experience Highlights
• 44 years of industry
experience
• 3 years at AR/WS
• In depth knowledge of
federal and state
guidelines
• Former Caltrans District
Office Chief
2 101 on and off ramps, construct intersection improvements between Automall Parkway/Chestnut Street and Camino Arroyo, implement complete street elements, and improve bicycle and pedestrian connectivity. The right of way conceptual cost estimate involved the analysis of 2 alternatives with impact analysis required for 18 properties. Mr. Shindler assisted in the preparation of the right of way estimate, including comparable sales research, valuation conclusions, and identification of site improvements impacted by the designs.

Alameda County Public Works Agency
Dublin Boulevard – North Canyons Parkway Extension Project Cost Estimating
Mr. Shindler assisted in the preparation of a Right of Way estimate for potential right of way acquisitions from 7 parcels in Dublin, Livermore and unincorporated Alameda County.

Bay Area Toll Authority
West Oakland Link Project
Right of Way Consulting and Cost Estimating
The purpose this project is to build an elevated pedestrian and bicycle pathway that will connect Mandela Parkway with the existing San Francisco-Oakland Bay Bridge East Span path. Mr. Shindler prepared a right of way cost estimate in Caltrans Right of Way Data Sheet format. Mr. Shindler has provided right of way consultation to BATA and the project team and has assisted in the coordination with the City of Oakland and its tenant in gaining access to perform onsite boring activities. The next phase of the project has commenced, with AR/WS providing project management, right of way coordination, appraisal, appraisal review, acquisition, and Right of Way Certification services.

City of Oakland
Oakland Bay Trail Project
Cost Estimating
This project is for a proposed bicycle and pedestrian path, authorized and funded by Measure DD. The right of way estimate involved the analysis of 2 alternatives with 3 acquisition scenarios, with 3 potentially impacted parcels. Mr. Shindler assisted in the preparation of the right of way estimate.

Contra Costa Transportation Authority
I-680 NB Express Lane Project
Cost Estimating
This project is intended to bridge the gap in the existing express lane network on I-680, between Livorna Road and SR-242. Mr. Shindler assisted in the preparation of Right of Way Data Sheets for 4 project alternatives, which included potential right of way acquisitions from 10 parcels in Walnut Creek and Pleasant Hill.

County of Napa
Napa Valley Vine Trail Project
Cost Estimating
The project proposes to construct 47 miles of Class 1 trail from Vallejo’s Ferry to Calistoga. The proposed project includes permanent easements from approximately 70 properties. Mr. Shindler assisted in the preparation of the right of way estimate, including comparable sales research, valuation conclusions, and identification of site improvements impacted by the proposed design.

North Marin Water District
Rush Creek Place Project
Cost Estimating
Mr. Shindler assisted in preparing an Estimate of Value for a commercial/industrial site in Novato.