ADMINISTRATIVE REPORT

MEETING DATE: January 8, 2025 AGENDA CATEGORY: Consent - Agreements TO: Honorable Mayor and City Council
FROM: Zachary Meyer, Public Works Director
DATE: December 18, 2024
SUBJECT: Amendment No. 7 to Agreement No. 19-070 with AECOM Technical Services, Inc. (increasing compensation by $127,376.57; not to exceed $25,579,021.98) for additional construction management services for the Centennial Corridor Mainline Project.

RECOMMENDATION:

Staff recommends approval of the amendment.

BACKGROUND:

The Mainline Project extend s State Route 58 (SR -58) from the current terminus as a freeway at State Route 99 (SR-99) to the Westside Parkway. At the SR-58/SR-99 interchange, the Project adds a collector- distributor on the northbound SR -99 and constructs a new northbound to westbound connector. The Project also includes various local road improvements including; realignment and introducing cul-de-sacs at the end of local roads along the corridor, widening and realignment of Chester Avenue at SR -58, and construction of a traffic signal at the eastbound SR-58 ramps/Brundage Lane intersection (which is part of the SR-58/Cottonwood Road interchange). This Project was awarded in July of 2019 and has an estimated completion date of winter 2024.

On August 31, 2022, City Council approved Amendment No. 1 extending the term for services and added $3,729,925 to Agreement No. 19-070.

On May 24, 2023, City Council approved Amendment No. 2 extending the term for services and added $2,211,378 to Agreement No. 19-070.

On October 11, 2023, City Council approved Amendment No. 3 extending the term for services and added $287,065 to Agreement No. 19-070.

On February 14, 2024, City Council approved Amendment No. 4 extending the term for services and added $499,814 to Agreement No. 19-070.

On June 12, 2024, City Council approved Amendment No. 5 adding $253,609 to Agreement No. 19-070.

On October 23, 2024, City Council approved Amendment No. 6 adding $120,000 to Agreement No. 19 - 070.

The amendment for additional Construction Management (CM) services in cludes construction inspections, contract administration, and project closeout. Amendment No. 7 to Agreement No. 19-070 adds $127,376.57 to the Mainline Project CM agreement.

FISCAL IMPACT:

The project is funded with 26% Federal INFRA Grant, 24% SAFETEA-LU Federal funds, 34% State STIP funds, and 16% Local Funds. Local funds will be comprised of Utility Surcharge funds, Traffic Development funds, and Gas Tax funds. There is no General Fund impact associated with this amendment.”

COUNCIL GOAL:

Reliable Infrastructure