CITY OF BAKERSFIELD
Thomas Roads Improvement Program
SHEET 1 OF 1
CONTRACT NO. P.O. NO.

PROJECT:

FEDERAL NO. (S)
CONTRACTOR: Security Paving Company
ADDRESS: 2915 Fairhaven Drive
Bakersfield, CA 93309

YOU ARE HEREBY DIRECTED TO MAKE THE HEREIN DESCRIBED CHANGES FROM THE PLANS AND SPECIFICATIONS OR DO THE FOLLOWING WORK DESCRIBED NOT INCLUDED IN THE PLANS AND SPECIFICATIONS ON THIS CONTRACT.

NOTE: This change order is not effective until approved by City Council or City Engineer CHANGE SUBMITTED BY: Arturo Infante, Construction Manager DATE: 5/10/2024 CHANGE REQUESTED BY: Arturo Infante, Construction Manager DATE: 5/10/2024

127-4021-825.80-41 TRCC21 INCREASE $10,000.00
335-4021-825.80-41 TRCC21 DECREASE $0.00
By reason of this order the time of City Council Approval Required YES X completion will be adjusted as follows: NO ADJUSTMENT NO Approved As to Form: CITY ATTORNEY Approved by the Council of City of Bakersfield Approval Recommended: City Engineer Mayor
Countersigned: Finance Director Date
Contractor: Title:

CONTRACT CHANGE ORDER
Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work of contract price, agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. 19-069 104
NCIIPL-5109(251)
CHANGE ORDER NO.

Centennial Corridor MAINLINE
Accepted, Date:

We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above.

As authorized by the Engineer, and in accordance with section 4-1.05 "Changes and Extra Work" perform the following work:
a) Remove and reinstall the street light located at about Station 21+80, rt, while drainage system 14 is installed in the area. b) Locate existing power sources at Morrison St and at Dunlap St.

EXTRA WORK AT FORCE ACCOUNT:

For any costs incured related to removing and reinstalling the street light and locating the power sources, the Contractor will submit invoices and extra work tickets in accordance with Section 9-1.04C of the Standard Specifications.

Extra Work at Force Account = $10,000.00
TIME ADJUSTMENT:

NO ADJUSTMENT