CITY OF BAKERSFIELD
Thomas Roads Improvement Program
SHEET 1 OF 1
CONTRACT NO. P.O. NO.

PROJECT:

FEDERAL NO. (S)
CONTRACTOR: Security Paving Company
ADDRESS: 2915 Fairhaven Drive
Bakersfield, CA 93309

YOU ARE HEREBY DIRECTED TO MAKE THE HEREIN DESCRIBED CHANGES FROM THE PLANS AND SPECIFICATIONS OR DO THE FOLLOWING WORK DESCRIBED NOT INCLUDED IN THE PLANS AND SPECIFICATIONS ON THIS CONTRACT.

NOTE: This change order is not effective until approved by City Council or City Engineer CHANGE SUBMITTED BY: Arturo Infante, Construction Manager DATE: 1/1/2025 CHANGE REQUESTED BY: Arturo Infante, Construction Manager DATE: 1/7/2025 ACCOUNT NO (S) 122-4021-825.80-41 TRCC21
127-4021-825.80-41 TRCC21 INCREASE $20,000.00
335-4021-825.80-41 TRCC21 DECREASE $0.00
By reason of this order the time of City Council Approval Required YES X completion will be adjusted as follows: NO ADJUSTMENT NO Approved As to Form: CITY ATTORNEY Approved by the Council of City of Bakersfield Approval Recommended: City Engineer Mayor
Countersigned: Finance Director Date
Contractor: Title:

CONTRACT CHANGE ORDER
Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work of contract price, agreed price and force account.

Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. 19-069 158
NCIIPL-5109(251)
CHANGE ORDER NO.

Centennial Corridor MAINLINE
Accepted, Date:

We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above.

Extra Work at Force Account
Furnish flaggers to provide for passage of traffic through the work as specified in Sections 7-1.03, "Public Convenience," and 7-1.04, "Public Safety.” In accordance with Section 12-1.03, “Flagging Costs,” of the Standard Specifications, the State and the contractor will share the cost of furnishing flaggers to provide for passage of traffic through the work. The Department determines the cost under Section 9-1.04, “Force Account,” of the Standard Specifications, and pays the contractor one half of the cost.

Perform the following work, as determined necessary by the Engineer:

Move barricades from location to location. Comply with Section 12-3.02, “Barricades,” of the Standard Specifications Furnish, install, maintain, move, and remove additional construction area signs. Comply with Section 12-3.06, “Construction Area Signs,” of the Standard Specifications
Repaint concrete barrier. Comply with Section 12-3.08, “Type K Temporary Railing,” of the Standard Specifications Move Type K Temporary Railing. Comply with Section 12-3.08, “Type K Temporary Railing,” of the Standard Specifications Move plastic traffic drums from location to location. Comply with Section 12-3.11, “Plastic Traffic Drums,” of the Standard Specifications Repair temporary crash cushions modules damaged by traffic. Comply with Section 12-3.15 “Temporary Crash Cushion Module,” of the Standard Specifications Reposition temporary crash cushions. Comply with Section 12-3.15 “Temporary Crash Cushion Module,” of the Standard Specifications This work will be paid by force account. Labor, materials, and equipment, as approved by the Engineer, will be paid for in accordance with the provisions in Section 9-1.04, “Force Account,” of the Standard Specifications.

Extra Work at Force Account $20,000.00

UNILATERAL