1 | Page

Multi-Modal Transportation & Traffic Safety Committee Bi-Monthly Report June 2025

Projects
The City of Bakersfield Public Works Department is dedicated to proactively identifying, planning, and implementing effective Traffic Calming measures across the City. These initiatives are designed with the goal of enhancing road safety for all users, particularly pedestrians and cyclists, while promoting a safer, more inclusive environment for various modes of transportation. By strategically targeting areas with high traffic volumes and pedestrian activity, the department aims to reduce accidents, improve the overall safety of our roadways, and encourage sustainable transportation options.

The following is a comprehensive list of both current and completed projects, each carefully developed with a focus on multi-modal transportation, traffic safety, and community well-being. These projects reflect the City’s commitment to creating a balanced and accessible transportation system that meets the needs of all residents, whether they’re traveling by foot, bicycle, car, or public transit. Through these efforts, the Public Works Department strives to foster a safer, more connected, and more resilient community.

*Grant Funded
Complete Streets
Project Execution Status
Complete Streets along Stine
Rd: Ming Ave to Wilson Rd
APD (Design)
Streets (Install) Construction Complete
Complete Streets along Baker
St: Monterey St to 21st St*
APD (Design)
Contractor (Install) Preliminary Design.

Corridor Enhancements:

Chester Ave
Design Engineering (Design)
Contractor (Install)
Design Complete. Advertisement pending
additional funding.

Corridor Enhancements: 18th St
and 19th St
Design Engineering (Design)
Contractor (Install)
Design at 100%. Pending Environmental and
Right-of-Way approval through Caltrans.

Corridor Enhancements: MLK
Blvd*
Consultant (Design)
Contractor (Install)
Design at 75%. Construction funding request
for FY25/26.

Corridor Enhancements:

Monitor St
Consultant (Design)
Contractor (Install)
Design at 75%. Construction funding request
for FY27/28.

Corridor Enhancements: H St* Consultant (Design)
Contractor (Install)
Design at 95%. Pending Right-of-Way
approval through Caltrans.

Corridor Enhancements: Niles
St & Monterey St
Consultant (Design)
Contractor (Install)
Design at 65%. Phase 1 Construction funding
request for FY26/27.

2 | Page

Striping
Project Execution Status
Traffic Striping – Ming Ave: Allen Rd to
Buena Vista St
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Ashe Rd: Stockdale Hwy to
Panama Ln
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – White Ln: Allen Rd to
Buena Vista St
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Allen Rd: Stockdale Hwy to
White Ln
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Buena Vista Rd: White Ln
to RR Tracks
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – 18th St Angled Parking APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Fairfax Rd: Auburn St to
Paladino Dr
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Brimhall Rd: Calloway Dr
to Woodmont Dr
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Chester: 24th St to Garces
Circle
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Madison St: E Planz Rd to
White Ln
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Striping along Grand Lakes
Ave
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – 18th St/Franklin
Elementary (Traffic Calming)
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Buena Vista Rd: Harris Rd
to RR Tracks
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Rafer Johnson School Area
(10th & N St)
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Espee St: Niles St to Q St APD (Design) Streets (Install) Construction Complete
Traffic Striping – Fairfax Rd: Auburn St to
Royal Coach Cir
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Ming Ave: Union Ave to H
St
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – P St: Ming Ave to Belle
Terrace
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Planz Rd: S. H St to S.

Chester Ave
APD (Design)
Streets (Install) Construction Complete
Traffic Striping – Wible Rd: Mckee Rd to
Hosking Ave
APD (Design)
Streets (Install) Construction Complete

Traffic Calming and Pedestrian Improvements
Project Execution Status
Traffic Calming - Oleander Ave: E California
Ave to Brundage Ln
APD (Design)
Streets (Install) Final Design Review
Pedestrian Improvements - Wible Rd:

Berkshire Rd to Panama Ln
APD (Design)
Contractor (Install)
Design at 90%. Construction funding
request for FY25/26.

Rapid Rectangular Flashing Beacon - Truxtun
Ave at Pine St*
APD (Design)
Contractor (Install) Preliminary Design.

Rapid Rectangular Flashing Beacon - Chester
Ave at 22nd St*
APD (Design)
Contractor (Install) Preliminary Design.

Pedestrian Improvements: Q St and Espee St Design Engineering (Design) Contractor (Install) Phase 1 of Construction Complete.
3 | Page

Speed Hump – Christmas Tree Ln APD (Design)
Streets (Install)
Design Complete.

Speed Hump – Gasoline Alley Dr APD (Design)
Streets (Install) Design Complete.

Speed Hump – Sundale Ave APD (Design)
Streets (Install) Design Complete.

Speed Hump – Jewett Ave APD (Design)
Streets (Install) Design Complete.

Speed Hump – O St APD (Design)
Streets (Install) Design Complete.

Speed Hump – Real Rd APD (Design)
Streets (Install) Design Complete.

Speed Hump – Beech St APD (Design)
Streets (Install) Design Complete.

Speed Hump – Custer Ave APD (Design)
Streets (Install)
Design Complete.

Speed Hump – District Blvd APD (Design)
Streets (Install) Design Complete.

Speed Hump – Sandra Dr APD (Design)
Streets (Install) Design Complete.

Flashing Beacons: Norris Rd & Stiern Middle
School
APD (Design)
Contractor (Install) In Construction
Garces Memorial Circle Enhancement Consultant (Design)
Contractor (Install) Construction Complete
Flashing Beacon: Veterans Elem, Warren Jr
High*
APD (Design)
Contractor (Install) Construction Complete
Flashing Beacon: Calloway Dr (Norris),
Monitor St*
APD (Design)
Contractor (Install) Construction Complete

Speed Hump – Las Entradas
APD (Design)
Streets (Install)
Construction Complete

Flashing Beacon: Golden Valley High School APD (Design) Contractor (Install)
Construction Complete

Radar Feedback Signs: Various Locations* APD (Design)
Contractor (Install) Construction Complete
Reflective Signal Backplates: Various
Locations*
APD (Design)
Contractor (Install) Construction Complete
Rectangular Rapid Flashing Beacon: Heritage
Park/Mt Vernon Ave
APD (Design)
Contractor (Install) Construction Complete
Traffic Calming Demo - Beale Ave: Niles St
and Monterey St
APD (Design)
Contractor (Install) Construction Complete
Speed Hump – Marella Way @ Stockdale
Christian School
APD (Design)
Streets (Install) Construction Complete
Speed Hump – Sandra Dr and Laurel Dr APD (Design)
Streets (Install) Construction Complete
Speed Hump – Summertree Ln and Canter
Way
APD (Design)
Streets (Install) Construction Complete
Speed Hump – El Potrero Ln and Mesa
Grande St
APD (Design)
Streets (Install) Construction Complete
Speed Hump – Dennen St APD (Design)
Streets (Install) Construction Complete
Speed Hump – Abbott Dr APD (Design)
Streets (Install) Construction Complete

4 | Page

Bike Trails
Project Execution Status
Stonecreek Loop: Class IV Cycle Track APD (Design)
Contractor (Install) Design at 60%.

Kentucky St Urban Greening - Beale Ave to Baker
St, Canal to Mt Vernon Ave* APD (Design) Preliminary Design.

Beach Park Bridge Consultant (Design)
Environmental permitting and review.

Additional Design Funding requested for
FY25/26
Multi-Use Path: Friant-Kern Canal* Consultant (Design)
Contractor (Install) Under Construction.

Bike Lane: Old County Dump Rd* APD (Design) Vehicle Gate Installed. Pending minor pavement and sign
Multi-Use Path: Stockdale Ranch Consultant (Design)
Contractor (Install) Construction Complete

Strategy
Public Works is dedicated to fostering continuous improvement across the City by proactively identifying and implementing opportunities that enhance the quality of life for residents. In addition to carefully evaluating and responding to public requests, the department places a strong focus on critical areas such as prioritizing safety and accessibility around schools, expanding and enhancing multi-modal infrastructure, and revitalizing the City’s historic corridors. A key component of this effort is the ongoing transformation of the Downtown core and Old Town Kern, which serve as a vibrant hub for commerce, culture, and community. By focusing on these strategic initiatives, Public Works aims to build a more sustainable, equitable, and future-ready City for all.

Funding
Safe Streets & Roads 4 All (SS4A): The Safe Streets and Roads for All Program is a U.S.

Department of Transportation initiative that provides funding to local governments and regional entities for planning and implantation projects focused on reducing crashes and improving road safety. The program aims to support efforts on sustainable transportation solutions, particularly for vulnerable road users like pedestrians and cyclists. • City of Bakersfield Comprehensive Safety Action Plan
Transformative Climate Communities (TCC): The Transformative Climate Communities (TCC) program is a California initiative that provides funding to disadvantaged communities for projects that reduce greenhouse gas emissions, improve public health, and enhance local economic opportunities. It aims to support community-driven climate resilience efforts through integrated strategies that address both environmental and social equity challenges.
• Complete Streets Improvements: Dr. Martin Luther King Jr. Blvd

5 | Page

Community Project Funding Grant (CPF): The Community Project Funding (CPF) program allocates federal funds to support local initiatives that address specific community needs, such as affordable housing, infrastructure improvements, and economic development.

These funds are directed toward projects that benefit low- and moderate-income communities, helping to enhance living conditions and promote sustainable growth. • Complete Streets Improvements: Dr. Martin Luther King Jr. Blvd Active Transportation Program (ATP): The Active Transportation Program (ATP) is a California initiative that provides funding for projects that promote walking, biking, and other forms of active transportation. It focuses on improving safety, mobility, and access, particularly for disadvantaged communities, while encouraging healthier and more sustainable transportation options.
• ‘H’ Street Corridor Improvements (Cycle 6 - Funded)
• Monitor St Active Transportation Improvements Project (Cycle 7 – Unfunded) Congestion Mitigation and Air Quality (CMAQ): The Congestion Mitigation and Air Quality (CMAQ) program is a federal initiative that provides funding to state and local governments for projects aimed at reducing traffic congestion and improving air quality.

It supports efforts to enhance transportation systems, promote clean vehicle technologies, and encourage alternatives to driving, such as public transit and non- motorized transportation.
• ‘H’ Street Safety Improvements (FY 25/26)
• 18
th & 19th Street Improvements (FY 25/26)
• Niles Street Corridor Improvements (FY 26/27) – Request due July 17, 2025 • Monitor Street Corridor Improvements (FY 27/28) – Request due July 17, 2025 Transportation Development Act (TDA-3): The Transportation Development Act (TDA-3) is a California funding program that provides financial support for public transportation and bicycle/pedestrian projects through a portion of the state's sales tax revenue. TDA-3 specifically allocates funds to support transit services, including those that serve rural and smaller communities, promoting accessibility and sustainable transportation options. • Rapid Rectangular Flashing Beacons on Truxtun Avenue at Pine Street (FY 24/25) • Rapid Rectangular Flashing Beacons on Chester Avenue at 22 nd Street (FY 24/25)
• Pederstrian Improvements along Potomac at UPRR Crossing (FY 26/27 Co-Applicant with Kern County)
Highway Safety Improvement Program (HSIP): The Highway Safety Improvement Program (HSIP) is a federal initiative aimed at reducing traffic fatalities and serious injuries on public roads by funding safety projects. It provides states with funding to implement data-driven safety improvements, such as road design changes, signage, and intersection upgrades. • Radar Feedback Signs at 14 street segments
• Reflective Signal Backplates