CITY OF BAKERSFIELD
Thomas Roads Improvement Program
SHEET 1 OF 1
CONTRACT NO. P.O. NO.
PROJECT:
FEDERAL NO. (S)
CONTRACTOR: Security Paving Company
ADDRESS: 2915 Fairhaven Drive
Bakersfield, CA 93309
YOU ARE HEREBY DIRECTED TO MAKE THE HEREIN DESCRIBED CHANGES FROM THE PLANS AND SPECIFICATIONS OR DO THE FOLLOWING WORK DESCRIBED NOT INCLUDED IN THE PLANS AND SPECIFICATIONS ON THIS CONTRACT.
NOTE: This change order is not effective until approved by City Council or City Engineer CHANGE SUBMITTED BY: Arturo Infante DATE: 4/27/2025
CHANGE REQUESTED BY: Arturo Infante DATE: 4/27/2025
ACCOUNT NO (S) 122-4021-825.80-41 TRCC21
127-4021-825.80-41 TRCC21 INCREASE $100,409.40
335-4021-825.80-41 TRCC21 DECREASE
By reason of this order the time of City Council Approval Required YES X completion will be adjusted as follows: None NO
Approved As to Form: CITY ATTORNEY Approved by the Council of City of Bakersfield Approval Recommended: City Engineer Mayor
Countersigned: Finance Director Date
Contractor: Title:
Adjustment in Compensation at Agreed Lump Sum
Accepted, Date:
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above.
CONTRACT CHANGE ORDER
Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work of contract price, agreed price and force account.
Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. 19-069 80
NCIIPL-5109(251)
CHANGE ORDER NO.
Centennial Corridor MAINLINE
In accordance with Section 9-1.17D, "Final Payment and Claims," of the Standard Specifications, compensate the contractor for Claim No. 36.
This claim was referred to the Dispute Resolution Board (DRB) on Feb 17, 2025. The DRB issued a unanimous decision on March 7, 20255, following the DRB recommendation , the contractor will be compensated for the following:
The estimated amount of colored concrete that the contractor will be compensated as a result of this recommendation is 1,568 cubic yards.
Contractor shall be compensated 1,852.05 CY @ $60/CY = $111,123.00 This adjustment will account for all the concrete barriers, soundwalls, and anchor blocks, excluding median barriers"SR58", West of Sta 568+00. to be integrally pigmented colored concrete. The color must match Davis color No. 5477 "Mesa Buff" The estimated amount of colored concrete to be credited as a result of this recommendation is 186 cubic yards.
Contractor shall credit the City 178.56 CY @ $60/CY = $10,713.60 For the above listed claim, the Contractor agrees to accept a lump sum payment of $100,409.39 including all markups for this change. This change order provides full and final compensation for and resolves all aspects of the Contractor's Claim No. 36 as described above.
UNILATERAL