ADMINISTRATIVE REPORT

MEETING DATE: August 27, 2025 AGENDA CATEGORY: Consent – Agreements TO: Honorable Mayor and City Council
FROM: Zachary Meyer, Public Works Director
DATE: August 6, 2025
SUBJECT: Contract Change Order No. 3 to Agreement No. 2024-084 with GSE Construction Co. ($179,539.03 revised not to exceed $3,349,799.03) for the Wastewater Treatment Plant No. 2 Bar Screen Rehabilitation Project. (Ward 1).

RECOMMENDATION:

Staff recommends approval of the change order.

BACKGROUND:

The work to be performed consists, in general, of the replacement of existing mechanical bar screen and conveyor system and installation of electrical and instrumentation equipment at Wastewater Treatment Plant No.2.

Change Order No. 3 provides for the cleaning of the headworks channel, which has not been performed due to the extended shutdown of the headworks. During the installation of the bypass pump ing system, a significant amount of rags and debris was discovered in the bar screen channel as a result pf insufficient routine cleaning during this period of inactivity. To facilitate the upcoming repairs and ensure proper surface preparation for the coa ting of the channel area, thorough cleaning and removal of all debris is required. The contractor agrees to do the above-mentioned work for the lump sum price of $3,990.00.

Also, during construction, approximately 2 feet of rags were found in the channel between the headworks and the Operations building wet well. To ensure proper operation of the headworks at startup, the rag/debris buildup must be removed. The contractor agrees to do the above -mentioned work for the lump sum price of $14,163.00.

Additionally, during construction, it was discovered that the concrete channel between the headworks and the wet well was badly deteriorated. In order to ensure structural integrity and operational reliability, the damaged concrete must be repaired. The contractor agrees to do the above-mentioned work for the lump sum price of $156,339.00.

This change order also provides for the necessary repairs to the influent box; a large void was discovered in the south concrete wall. In order to properly coat the influent box, all concrete must be repaired and patched as needed. The contractor agrees to do the above mentioned work for the lump sum price of $5,047.03.

FISCAL IMPACT:

The Sewer Enterprise funding is available in Project E3K306 to cover this cost , therefore has no City General Fund impact associated with this change order.

The Total construction cost increase for Contract Change Order No.3 is $179,539.03 . This is the final change order for this project, and the project has been completed. This final change order reflects a total project cost increase of 242,799.03 (7.8% increase to the original contract amount) as illustrated below:

Original Contract Amount = $ 3,107,000.00 Total of Previous Change order approved by council
contingency
= $ 63,260.00
Current Contract change order = $ 179,539.03 Amended Contract Amount after Change order = $ 3,349,799.03 Net Increase to Date = $ 242,799.03

COUNCIL GOAL:

Reliable Infrastructure

ATTACHMENTS:

Contract Change Order No. 3 to Agreement No. 2024-084